Water Pollution Control Authority of the City of Norwalk v. Flowserve US

Court of Appeals for the Second Circuit·Decided July 30, 2019·No. 18-1288·Unpublished

Opinion

18-1288 Water Pollution Control Authority of the City of Norwalk v. Flowserve US, Inc.

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT

SUMMARY ORDER

RULINGS BY SUMMARY ORDER DO NOT HAVE PRECEDENTIAL EFFECT. CITATION TO A SUMMARY ORDER FILED ON OR AFTER JANUARY 1, 2007, IS PERMITTED AND IS GOVERNED BY FEDERAL RULE OF APPELLATE PROCEDURE 32.1 AND THIS COURT=S LOCAL RULE 32.1.1. WHEN CITING A SUMMARY ORDER IN A DOCUMENT FILED WITH THIS COURT, A PARTY MUST CITE EITHER THE FEDERAL APPENDIX OR AN ELECTRONIC DATABASE (WITH THE NOTATION “SUMMARY ORDER”). A PARTY CITING TO A SUMMARY ORDER MUST SERVE A COPY OF IT ON ANY PARTY NOT REPRESENTED BY COUNSEL.

At a stated term of the United States Court of Appeals for the Second Circuit, held at the Thurgood Marshall United States Courthouse, 40 Foley Square, in the City of New York, on the 30th day of July, two thousand nineteen.

Present:

DENNIS JACOBS,

DEBRA ANN LIVINGSTON,

JOSEPH F. BIANCO,

Circuit Judges.

WATER POLLUTION CONTROL AUTHORITY OF THE CITY OF NORWALK,

Plaintiff-Third-Party-Plaintiff-Appellant, v. 18-1288 FLOWSERVE US, INC.,

Defendant-Third-Party-Plaintiff-Counter-Defendant-

Counter-Claimant-Appellee,

GILBANE BUILDING COMPANY,

Third-Party-Defendant-Counter-Claimant-Appellee.

For Plaintiff-Third-Party- Plaintiff-Appellant: MARTHA C. GAYTHWAITE, Verrill Dana LLP, Portland ME; Calvin K. Woo, Verrill Dana LLP, Westport, CT.

For Defendant-Third-Party-Plaintiff- Counter-Defendant-Counter- Claimant-Appellee: JASON P. ECKERLY, Martha E. Drouet, Segal McCambridge Singer & Mahony, Ltd., Chicago, IL.

For Third-Party-Defendant-Counter- Claimant-Appellee: JARED COHANE, Esq., Jeffrey J. Mirman, Esq., Hinckley, Allen & Snyder LLP, Hartford, CT.

Appeal from a judgment of the United States District Court for the District of Connecticut (Bryant, J.).

UPON DUE CONSIDERATION, IT IS HEREBY ORDERED, ADJUDGED, AND DECREED that the judgment of the district court is AFFIRMED.

I. Background In 2008, the Water Pollution Control Authority of the City of Norwalk (“WPCA”)

embarked upon a four-year project to upgrade its wastewater plant (“the Project”). WPCA hired Gilbane Building Company (“Gilbane”) to manage the Project. Gilbane’s duties included, among other things, soliciting and evaluating equipment bids and recommending winning bids to WPCA. In its role as manager, Gilbane conducted a public bid process for six “vertical non-clog dry pit submersible pumps” and associated control systems, ultimately awarding the contract to Flowserve US, Inc. (“Flowserve”), the low bidder. JA-207. Flowserve delivered the pumps to the wastewater plant in August 2011, where they were installed and put into operation by March 2012. At that point, WPCA’s plant operator, OMI, Inc. (“OMI”), assumed responsibility for operation and maintenance of the pumps. OMI kept daily handwritten logs of plant equipment operation, including (1) daily operator checklists (which operators marked and recorded during their rounds); (2) work orders for routine and preventative maintenance; and (3) spot maintenance for specific issues that arose.

After the Flowserve pumps were put into operation, some of them began malfunctioning.

Most significantly, in late July and early August 2013, OMI noted in its logs that Pumps 1 and 5 were running without pumping any liquid or were “airbound,” meaning that air had entered the system and needed to be bled out. This is also known as “running dry.” JA-1446–47. Running pumps dry can damage the seals and lead to “catastrophic seal failure.” JA-1447. On August 12, 2013, OMI again noted in its logs that Pump 1 was airbound; the next day, Pump 1’s primary mechanical seal failed. Pumps 1 and 5 were repaired by Associated Electro Mechanics, Inc. (“AEM”), a Flowserve-approved repair company. Upon inspection, AEM concluded that the mechanical seals in Pumps 1 and 5 had failed due to thermal shock from running dry. Flowserve denied WPCA’s warranty claims for the seal inspections and repairs of Pumps 1 and 5, stating that AEM’s inspection had revealed that the pumps had failed because of improper maintenance and use.

Following the denial of its warranty claims for Pumps 1 and 5, WPCA sued Flowserve in Connecticut state court. The action was removed to the United States District Court for the District of Connecticut (Bryant, J.) in April 2014. Flowserve then filed a third-party complaint against Gilbane.

While this litigation was ongoing, WPCA asked the company that had designed the project, Camp, Dresser & McKee (“CDM”), to investigate the pumps and determine whether they should be replaced. CDM concluded that it was not necessary to replace the pumps. Likewise, OMI never recommended that the pumps be replaced. Nevertheless, in January 2015, WPCA decided to redesign the pumping system and install new pumps, entering into a contract with Arcadis U.S., Inc.

WPCA filed its Third Amended Complaint (“TAC”) on February 1, 2017. The TAC alleges seven causes of action against Flowserve: (1) strict products liability; (2) negligent products liability; (3) breach of express warranty; (4) breach of implied warranty of merchantability; (5) breach of implied warranty for a particular purpose; (6) third-party breach of contract; and (7) violation of the Connecticut Unfair Trade Practices Act (“CUTPA”). The TAC also alleged a single breach of contract claim against Gilbane. All three parties moved for summary judgment. In addition, Flowserve moved to exclude two experts that WPCA had disclosed for trial.

On March 28, 2018, the district court granted Flowserve’s motions to exclude WPCA’s experts, granted Flowserve’s and Gilbane’s motions for summary judgment against WPCA, and denied as moot Flowserve’s and Gilbane’s motions for summary judgment against each other. As to the experts, the district court determined that (1) WPCA’s expert Judith Hodgson (“Hodgson”) had relied on inadequate surveys, failed to consider relevant evidence, and failed to disclose calculations; and (2) WPCA’s expert Bonneau Dickson (“Dickson”), in his expert report, lacked a sufficient explanation of reliable methodology. As to the motions for summary judgment, the district court determined that (1) WPCA’s products liability claims against Flowserve failed because they were not supported by admissible expert testimony, and in any event the pumps complied with Project specifications; (2) WPCA’s express and implied warranty claims against Flowserve failed because the final agreement either did not contain the cited warranties or expressly excluded any implied warranties; (3) WPCA’s CUTPA claim against Flowserve failed because it is barred by the Connecticut Product Liability Act’s (“CTPLA”) exclusivity provision; and (4) WPCA’s breach of contract claim against Gilbane failed because WPCA had offered no evidence that Gilbane advanced its own interests in breach of its fiduciary duty.

WPCA timely appealed.

II. Analysis A. The District Court’s Exclusion of Hodgson1 Hodgson is an engineer, hired by WPCA, who submitted a 108-page expert report to the district court explaining her conclusion that the Flowserve pumps had nine design defects that “were the cause of the pump failures and operational problems that plagued WPCA’s operation of its treatment plant.” SPA-15. The district court excluded Hodgson because, in part, she had reached her conclusion without considering evidence relevant to the possibility that the pumps had failed due to operator error in running the pumps dry, rather than because of design defects. In particular, Hodgson failed to review evidence regarding how the Flowserve pumps were maintained and operated, including “the deposition transcripts of most witnesses in this case, the daily log books recording Pump operation, the preventative maintenance records, or OMI’s daily round checklists.” SPA-35. As a result, the district court deemed Hodgson’s conclusions unreliable.

Free access — add to your briefcase to read the full text and ask questions with AI

Water Pollution Control Authority of the City of Norwalk v. Flowserve US, (2d Cir. 2019).

Water Pollution Control Authority of the City of Norwalk v. Flowserve US (Water Pollution Control Authority of the City of Norwalk v. Flowserve US) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
In Re Paoli Railroad Yard PCB Litigation
35 F.3d 717 (Third Circuit, 1994)
Wills v. Amerada Hess Corp.
379 F.3d 32 (Second Circuit, 2004)
United States v. Williams
506 F.3d 151 (Second Circuit, 2007)
Ackerman v. Sobol Family Partnership, LLP
4 A.3d 288 (Supreme Court of Connecticut, 2010)
Godina v. Resinall International, Inc.
677 F. Supp. 2d 560 (D. Connecticut, 2009)
Gerrity v. R.J. Reynolds Tobacco Co.
818 A.2d 769 (Supreme Court of Connecticut, 2003)
Sanders v. Fireline, Inc.
295 F. App'x 373 (Second Circuit, 2008)