Water Lot Co. v. Leonard

30 Ga. 560
CourtSupreme Court of Georgia
DecidedJune 15, 1860
StatusPublished
Cited by10 cases

This text of 30 Ga. 560 (Water Lot Co. v. Leonard) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Water Lot Co. v. Leonard, 30 Ga. 560 (Ga. 1860).

Opinion

By the Court.

Lyon, J.,

delivering the opinion.

1. There is nothing in the first and second grounds of demurrer; because, if the declaration was defective — and we do not think it was — the objections could ha^e been cured by amendment.

The 3d, 4th, 5th and 6th grounds of demurrer are involved in the charge of the Court as given, and in the refusals to charge on the request of counsel.

2. The witness, Parr, was competent. The fact that he owned an interest in the property did not affect him with interest. The property had been sold at sheriff’s sale, as the property of the Howard Manufacturing Company, and Parr [571]*571held an interest under the purchaser at that sale. That sale carried with it the covenant of the Water Lot Company to the Howard Manufacturing Company, and would enable the purchaser at such sale to recover for all injuries resulting from a breach after the sale, but the damages resulting to the Howard Manufacturing Company for breaches prior to the sale, did not pass to the purchaser by the sale; therefore the purchaser at sheriff’s sale, nor any one holding under him, could have any interest in the recovery in this suit, for this action is for damages resulting from a breach of covenant prior to the sheriff’s sale.

3. Tiie objection to the introduction of the deeds of 9th July, 1857, on the ground of discrepancy, was not well considered by couñsel. Van Leonard is called in the first, in one place, trustee of the Howard Manufacturing Company, and in the same deed, in another place, trustee of the stockholders of the Howard Manufacturing Company, which shows that the same company was referred to and intended in both cases, and if there was an apparent discrepancy, it explains itself; it certainly did not vitiate the deed. Besides, Van Leonard held the legal title in any event.

We understood the counsel for plaintiff in error, as not insisting upon the objection to these deeds for the want of an order to show that the persons who signed the deeds were authorized to make them, as no plea of non est factum had been filed, putting that fact in issue.

The remaining objections to the evidence — and they are numerous, for I believe everything was objected to by defendant’s counsel, even to testimony offered by themselves — are involved in the rulings of the Court in his charge to thejury, and may be all considered together. The same may be said of the points of error complained of by the Howard Manufacturing Company in the cross-bill of exceptions brought up by them.

The breaches assigned by the plaintiff in the Court below, in his declarations, were—

1st. That the Water Lot Company did not blast and blow out the race, or waste-way, opposite to lots 13, 14 and 15, to the width of sixty feet, and to the then depth of the raceway opposite to each or any of the other lots, as by the covenants they -were bound to do.

2d. That the said company did not finish all the eyes in [572]*572said canal or reservoir, in such manner as to furnish and contain in said canal water in sufficient quantity to propel the machinery placed and erected on said lot 11 by the plaintiff, by reason whereof damage resulted.

There was much discussion as to what was the true construction of the covenant in that part on which the second breach is assigned.

4. We think the true interpretation is, that if the canal was completed, and the eyes or gates, at the mouth of the canal were so finished or constructed as to permit the water from the river to flow freely and without interruption into the canal, and the balance of the eyes so finished as to prevent the escape of the water from the canal, except as intended it should, and the race or waste-way, was blasted out— all of which the Water Lot Company covenanted they would do — except as to blasting out the race or waste-way, opposite to lots 11 and 12, which the Howard Manufacturing Company covenanted they would do, that, then, the canal would furnish and contain sufficient water to propel the machinery, etc. There was no covenant against general drought or unusual and excessive low stages of the water in the river.

The whole'of the questions made upon the pleading, other than what I have disposed of, the evidence and the charge and refusal to charge by the Court, may be reduced to two, for to that were they narrowed in the argument, and they are—

1st. Was it necessary for the plaintiff to aver and prove that they had performed their part of the covenants; that is, to blast ancl blow out the race or waste-way, opposite to lots 11 and 12 before they could recover against the defendants for their breaches of the covenants by them ?

2d. What is the measure of damages for the injuries sustained by plaintiff in consequence of the breaches ?

5. Upon the first question we had great difficulty; in fact, were so unfortunate as at last not to be able to agree upon it. The whole difficulty lies in that knotty question, whether the covenants are dependent or independent? If they are dependent; that is, if each depends on the other, the failure of the one annuls and destroys the other. Now, the proof here is, that it would not benefit the plaintiff to blast out the race-way opposite lots 13, 14 and 15, unless the race-way opposite lot 12 was also blasted out, for their machinery is [573]*573on lot 11, which is above all of them, and the waste water would be equally poured on their wheel from the obstruction opposite lot 12, as that of 13, 14 or 15, or vice versa. If there was nothing between these parties; that is, if there was nothing in the agreement or deed but this part of the covenant, I should say the covenants were concurrent. To determine what is a proper construction, has always been an extremely vexed question with the Courts. I will, as briefly as possible, state some of the rules that bear on the point, that Courts have laid down to determine whether the covenants are dependent or independent:

“ When the agreements go to the whole of the consideration, on both sides, the conditions are dependent, and one of them is a condition precedent to the other. If the agreements go to a part only of the consideration on both sides, and a breach may be paid for in damages, the promises are so far independent.” Par. on Con., 2 vol., 189. “Or if this dependence is not mutual, but one of them rests upon the other by a dependence which is not equally shared .by the other; if that contract upon which this dependence rests, is broken .and defeated, the other, by reason of its dependence, is annulled and destroyed also.” “But they may be wholly independent, although relating to the same subject, and made by the same parties, and included in the same instrument. In that case, they are two separate contracts. Each party must, then, perform what he undertakes, without reference to the discharge of his obligation by the other party. And each party may have his action against the other for the non-performance of his agreement, whether he has performed his own or not.” The mutual covenants must go to the whole consideration on both sides, when the one is precedent to the other, but when they go to a part only, and a breach may be paid for in damages, the covenants are independent. The leading case on this point, is of Boon vs Eyrie, 1 H. Blk., 273. The plaintiff in that case conveyed to the defendant the equity of redemption

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Complete Trucklease, Inc. v. Auto Rental & Leasing, Inc.
288 S.E.2d 75 (Court of Appeals of Georgia, 1981)
Jordan Realty Co. v. Chambers Lumber Co.
168 S.E. 601 (Supreme Court of Georgia, 1933)
Williams Manufacturing Co. v. Schofield's Sons Co.
93 S.E. 527 (Court of Appeals of Georgia, 1917)
Baker v. Smith
70 S.E. 239 (Supreme Court of Georgia, 1911)
Clark v. West
137 A.D. 23 (Appellate Division of the Supreme Court of New York, 1910)
Muscogee Manufacturing Co. v. Eagle & Phenix Mills
54 S.E. 1028 (Supreme Court of Georgia, 1906)
McConnell v. Stubbs
53 S.E. 698 (Supreme Court of Georgia, 1906)
Williams v. Island City Milling Co.
37 P. 49 (Oregon Supreme Court, 1894)
Taylor Manuf'g Co. v. Hatcher Manuf'g Co.
39 F. 440 (U.S. Circuit Court for the Southern District of Georgia, 1889)
Anderson v. Sloane
40 N.W. 214 (Wisconsin Supreme Court, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
30 Ga. 560, Counsel Stack Legal Research, https://law.counselstack.com/opinion/water-lot-co-v-leonard-ga-1860.