Wastewater Plant Service Co. v. Harrison County Utility Authority

28 So. 3d 686, 2010 Miss. App. LEXIS 97, 2010 WL 610648
CourtCourt of Appeals of Mississippi
DecidedFebruary 23, 2010
Docket2008-CA-01815-COA
StatusPublished
Cited by3 cases

This text of 28 So. 3d 686 (Wastewater Plant Service Co. v. Harrison County Utility Authority) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wastewater Plant Service Co. v. Harrison County Utility Authority, 28 So. 3d 686, 2010 Miss. App. LEXIS 97, 2010 WL 610648 (Mich. Ct. App. 2010).

Opinion

GRIFFIS, J„

for the Court:

¶ 1. Wastewater Plant Service Co., Inc. (WPSCO) brought this action against Harrison County Utility Authority (HCUA) after HCUA chose another company’s proposal for the operation and management of HCUA’s wastewater facilities. On appeal by bill of exceptions, the circuit court affirmed HCUA’s decision. WPSCO now appeals, and the appeal has been deflected to this Court for consideration.

FACTS

¶ 2. HCUA governs Harrison County’s wastewater-treatment system, which includes wastewater-treatment plants and an interceptor system. HCUA is governed by a board of directors (Board), which is comprised of five mayors from cities located in Harrison County and two other representatives.

¶ 3. From 2000 through 2006, HCUA contracted with WPSCO to provide operation and maintenance services for HCUA’s interceptor system.

¶ 4. In August 2006, HCUA issued a Request for Proposals (“RFP”) which invited contractors to submit proposals for the operation and maintenance of its wastewater plants and interceptor lines. Proposals could be submitted for only one or for both systems.

¶ 5. According to the RFP, a mandatory pre-proposal meeting was held on August 16, 2006, at 9:00 a.m. In attendance were *689 representatives of WPSCO; Operation Technologies, Inc. (Optech); S.H. Anthony (SA); and Severn Trent.

¶ 6. The submission deadline for proposals was September 15, 2006. HCUA received three proposals. SA, together with Utility Partners (“UP”), submitted a proposal for the operation of both the waste-water system and interceptor system (the “SA/UP” proposal). WPSCO submitted a proposal for the operation of the interceptor system. Optech submitted proposals for the operation of the wastewater system.

¶ 7. SA’s proposed price was $299,862 per year. WPSCO’s proposed price was $273,843.96 per year. However, the SA/ UP’s proposal included services that were not covered in WPSCO’s proposed cost. The SA/UP proposal included the following services:

(1) infrared surveying of HCUA’s pump stations every three years (for preventative maintenance);
(2) draw[-]down testing of the pump stations (to determine their volume of wastewater flow) by an engineer; and
(3) boom[-]truck utilization.

On September 26, 2006, eleven days after the proposal due date, WPSCO contacted HCUA to state that it would also include the additional services that SA had included in its proposal at no additional cost.

¶ 8. Thereafter, Optech filed a complaint for a temporary restraining order and a motion for preliminary and/or permanent injunction and damages in the Harrison County Circuit Court. Optech’s suit sought to prevent SA and UP and their officers and employees from entering into negotiations with HCUA for the operation of HCUA facilities. Optech claimed that its former employees had violated the Mississippi Trade Secrets Act when the employees left Optech to work for UP and/or work with SA. WPSCO did not join in the action against SA and UP. On October 2, 2006, the circuit court granted Optech’s ex parte motion for a temporary restraining order.

¶ 9. Kamram Pahlavan was the Executive Director of HCUA. Pahlavan summarized the proposals to a technical committee of HCUA, which then reviewed the proposals. Pahlavan compared both Op-tech’s and SA/UP’s proposals for the wastewater plants, and WPSCO’s and SA/ UP’s proposals for the interceptor system.

¶ 10. According to Pahlavan’s summary, SA/UP’s base proposal price was $299,862 per year and included pricing for an infrared survey, draw-down tests, and boom-truck services. WPSCO’s base proposal price was $273,843.96 per year and did not include the infrared survey, draw-down tests, or boom-truck services. Pahlavan also placed a market value on the services which were offered by SA/UP and not by WPSCO:

(1) Every three years, SA/UP will use a third party to perform an infrared survey of all equipment and provide the Utility Authority with a written report of the findings. This service is valued [at] an estimated $10,000-$15,000.
(2) SA/UP includes all costs for draw[-]down testing, performed by a professional engineer, [sic] in the proposal. This service is valued [at] an estimated $8,000-$10,000.
(3) SA/UP will provide the use of a 10-15 ton boom truck with up to 55’ reach for removal of pumps and equipment, as well as said installation of such equipment is included. The Utility Authority spent approximately $10,000 for this service to be provided by vendors.

¶ 11. On October 5, 2006, the Board met and selected the SA/UP proposal. However, since the temporary restraining order was in effect, the Board mandated *690 that SA/UP provide evidence of its legal ability to enter into negotiations with HCUA.

¶ 12. On October 13, 2006, the circuit court dissolved the temporary restraining order and denied Optech’s request for a permanent injunction.

¶ 13. On October 19, 2006, the Board affirmed its acceptance of SA/UP’s proposal. Thereafter, WPSCO filed a bill of exceptions in the Harrison County Circuit Court to contest HCUA’s actions. In WPSCO’s bill of exceptions, WPSCO did not ask for nor establish “damages”; instead, it asked the court to overturn the HCUA’s decision and award it the contract. The circuit court ruled in favor of HCUA. From this judgment, WPSCO appeals.

STANDARD OF REVIEW

¶ 14. “When [the appellate Court] reviews a decision by a chancery or circuit court concerning an agency action, [it applies] the same standard of review that the lower courts are bound to follow.” Miss. Sierra Club, Inc. v. Miss. Dep’t of Envtl. Quality, 819 So.2d 515, 519 (¶ 15) (Miss.2002). Our standard of review from a finding of an administrative agency is limited. Uniform Rule of Circuit and County Court 5.03, entitled “Scope of appeals from administrative agencies,” provides:

On appeals from administrative agencies[,] the court will only entertain an appeal to determine if the order or judgment of the lower authority:
1. Was supported by substantial evidence; or
2. Was arbitrary or capricious; or
3. Was beyond the power of the lower authority to make; or
4. Violated some statutory or constitutional right of the complaining party.

Questions of law will be reviewed de novo. Smith v. Jackson Constr. Co., 607 So.2d 1119, 1125 (Miss.1992).

ANALYSIS

¶ 15. We begin our analysis with a brief explanation of two matters, which aid our review. First, Mississippi Rule of Appellate Procedure 28(a)(3) requires that there be a statement of the issues and “[e]ach issue presented for review shall be separately numbered in the statement.” Rule 28(a)(6) provides that “[t]he argument shall contain the contentions of [the] appellant with respect to the issues presented, and the reasons for those contentions. ...” M.R.A.P. 28(a)(6).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jean Bernard Gelin v. U.S. Attorney General
837 F.3d 1236 (Eleventh Circuit, 2016)
Ace Pipe Cleaning, Inc. v. Hemphill Construction Co.
134 So. 3d 799 (Court of Appeals of Mississippi, 2014)
Preferred Transport Co. v. Claiborne County Board of Supervisors
32 So. 3d 549 (Court of Appeals of Mississippi, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
28 So. 3d 686, 2010 Miss. App. LEXIS 97, 2010 WL 610648, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wastewater-plant-service-co-v-harrison-county-utility-authority-missctapp-2010.