Washington State Department Of Transportation v. Washington Natural Gas Company

59 F.3d 793
Court of Appeals for the Third Circuit·Decided July 13, 1995·No. 93-35130·Published·Cited by 9 cases

Opinion

59 F.3d 793

41 ERC 1678, 95 Cal. Daily Op. Serv. 5436,
95 Daily Journal D.A.R. 9272

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION,
Plaintiff-Appellant-Cross-Appellee,
v.
WASHINGTON NATURAL GAS COMPANY, PACIFICORP,
Defendants-Appellees-Cross-Appellants,
Advance Ross Corporation,
Third-Party-Defendant-Appellee-Cross-Appellant.

Nos. 93-35088, 93-35130, 93-35137, 93-35289, 93-35292 and 93-35330.

United States Court of Appeals,
Ninth Circuit.

Argued and Submitted April 7, 1994.
Decided April 14, 1995.
As Amended July 13, 1995.

Deborah L. Cade, Olympia, WA, for plaintiff-appellant-cross-appellee.

Gregory Costello, Riddell, Williams, Bullitt & Walkinshaw, Seattle, WA, for defendant-appellee-cross-appellant, Washington Natural Gas.

Louis A. Ferreira, Stoel, Rives, Boley, Jones & Grey, Portland, OR, for defendant-appellee-cross-appellant, Pacificorp.

Peter Petrakis, Katten, Muchin & Zavis, Chicago, IL, for third-party-defendant-appellee-cross-appellant.

Dennis J. Dunphy, Schwabe, Williamson, Ferguson & Burdell, Seattle, WA, for third-party-defendant-appellee-cross-appellant.

Appeals from the United States District Court for the Western District of Washington.

Before: TANG, BOOCHEVER, and REINHARDT, Circuit Judges.

OPINION

TANG, Senior Circuit Judge:

This is a review of several judgments of the United States district court, western district of Washington. The Washington State Department of Transportation (WSDOT) initiated this action against Washington Natural Gas Company (WNG), Pacificorp, and Advance Ross Corporation seeking recovery costs due under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. Sec. 9601, et seq. On cross-motions for partial summary judgment, the district court concluded that the defendants were responsible parties under CERCLA Sec. 107, 42 U.S.C. Sec. 9607. The district court conducted a bench trial to determine damages and entered a judgment in favor of WNG et al. The district court concluded that WSDOT was not entitled to recover its response costs because WSDOT did not comply with the National Contingency Plan ("NCP") promulgated by the Environmental Protection Agency ("EPA") pursuant to CERCLA.1

The overarching issue on this appeal is whether WSDOT can recover its response costs. To answer this question, we must address several related issues. First, under 42 U.S.C. Sec. 9607(a), is a state entitled to a presumption that its actions are consistent with the NCP? The effect of this presumption is to shift the burden of proving inconsistency with the NCP. We conclude that states are entitled to the presumption of consistency. Second, is WSDOT the "State" under 42 U.S.C. Sec. 9607(a)? We conclude that WSDOT is the "State," but further conclude that erroneously placing the burden of proof on WSDOT was harmless error. Third, were WSDOT's actions consistent with the relevant NCP, thereby entitling WSDOT to recovery of its response costs? We conclude that WSDOT's actions were inconsistent with the NCP and thus WSDOT is not entitled to recover its costs.2

BACKGROUND

In 1982, WSDOT began construction of the Tacoma Spur, an interstate highway project designed to connect Interstate 5 to Schuster Parkway and downtown Tacoma, Washington. In late 1983 and early 1984, WSDOT's geotechnical consultant, the firm of Hart Crowser, discovered tar-like material in soil borings taken to gain information on the material that would support planned highway structures. WSDOT reported the contamination to the Washington State Department of Ecology ("WSDOE"). WSDOE tested soil samples using the persistence testing method, which tests for PAH compounds. Because these soil samples came from the geotechnical borings, they were not obtained utilizing protocol typically followed to gather environmental samples. WSDOE reported that the tarry material was contaminated with polycyclic aromatic hydrocarbons ("PAHs") at a level of greater than one percent. Under WSDOE's regulations, material with a concentration of PAHs greater than one percent is considered "extremely hazardous waste."

WSDOE advised WSDOT that it might try to get the site listed on the CERCLA National Priority List, to obtain funding through the Superfund program. According to Hart Crowser, WSDOT did not want to pursue that option because it involved extra time and effort. Neither Hart Crowser nor WSDOT referred to the CERCLA National Contingency Plan to determine how to proceed.

WSDOT hired Hart Crowser as an environmental consultant to investigate the site and determine the type and extent of subsurface contamination. Hart Crowser began its investigation in July, 1984. The firm discovered from historical records that a coal gasification plant had operated on the construction site from 1884 until 1924. Sanborn maps indicated the location of the gas holders used to store the manufactured gas. Hart Crowser assumed that the plant, along with any gas holders, had been removed because the plant was not visible.

Hart Crowser also learned that tar was a likely by-product of the coal gasification process and may have accumulated in gas holders. However, Hart Crowser expected that the tar had been removed because it had some commercial value. The firm also assumed that any remaining tar waste had been dumped on the extremities of the plant grounds. To avoid running into the foundations of the gas holders, Hart Crowser did not put borings into the area where the gas holders had been located.

In addition to conducting historical research, Hart Crowser drilled twenty-six borings and obtained 359 soil samples. Upon testing these samples, Hart Crowser identified two types of contaminated material: tar-like material, and oily silt and sand. Hart Crowser's tests indicated a PAH concentration under one percent in the tar-like material. The highest concentration of PAHs in one sample of tar-like material was .5 percent and the second highest was .15 percent. The concentration of PAHs in the oily silt and sand did not exceed .02 percent. Hart Crowser did not use the test WSDOE had used to identify PAHs--Hart Crowser's method did not test for the total PAH level. Therefore Hart Crowser's report relied on WSDOE's original tests to conclude that the tar may be classified as a hazardous waste by WSDOE standards.

Hart Crowser estimated the volume of the sub-surface contaminants by interpolating between the borings. The calculations yielded estimates that the site contained 40 to 100 cubic yards, a maximum of 100 tons, of coal tar and 4,500 to 6,000 cubic yards of oily silt and sand, a maximum of 10,000 tons. Hart Crowser issued a report containing its findings in November, 1984.

Free access — add to your briefcase to read the full text and ask questions with AI

Washington State Department Of Transportation v. Washington Natural Gas Company, 59 F.3d 793 (3d Cir. 1995).

59 F.3d 793 (Washington State Department Of Transportation v. Washington Natural Gas Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related