Washington Sand & Gravel Co. v. Brann & Stuart Co.

162 F.2d 826, 1947 U.S. App. LEXIS 2198
CourtCourt of Appeals for the Third Circuit
DecidedJuly 14, 1947
DocketNo. 9344
StatusPublished
Cited by1 cases

This text of 162 F.2d 826 (Washington Sand & Gravel Co. v. Brann & Stuart Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Sand & Gravel Co. v. Brann & Stuart Co., 162 F.2d 826, 1947 U.S. App. LEXIS 2198 (3d Cir. 1947).

Opinion

McLAUGHLIN, Circuit Judge.

This is a contract action which was dismissed at the end of appellant’s case for failure-of proof as to damages. Appellant’s-motion to set aside the resultant judgment and to allow it a new trial was denied and this appeal followed.

It is a diversity suit. Performance of the contract was in Maryland, which brings the measure of the damages under the law of that state with the specific question of the sufficiency of the evidence, a matter of Pennsylvania law. As said in the leading case of Scudder v. Union National Bank, 91 U.S. 406 at pages 412, 413, 23 L.Ed. 245: “Matters bearing upon the execution, the interpretation, and the validity of a contract are determined by the law of the place where the contract is made. Matters connected with its performance are regulated by the law prevailing at the place of performance. Matters respecting the remedy, such as the bringing of suits, ad[827]*827missibility oí evidence, statutes of limitation, depend upon the law of the place where the suit is brought.”

And see Restatement, Conflict of Laws, Section 358 and Section 585 et seq. Appellant while urging that Maryland law governs the situation concedes that in the pertinent particulars the law of that state and of Pennsylvania is the same, and both sides accept the fundamental proposition that the damages claimed must rest upon a definite basis and not upon speculation and conjecture. The dispute arises over the application of the principle to the existing facts.

Appellant is in the sand and gravel business with an office and plant at Prince Georges County, Maryland, and another office in Washington, D. C. Appellee is a contractor who in 1943 was constructing an air field at Camp Springs, Meadows, Maryland, for the Government. On January 13, 1943, appellee issued its written purchase order addressed to the appellant at “Box 611, Bennings, D.C.” for 10,000 tons of washed gravel at $1.20 a ton and 10,000 of concrete sand at 7Op a ton. The order by its terms was subject to increase or decrease to the extent of 25'% without any change in unit prices or liability to appellee. Shipments were to start as called for and be completed as called for. Delivery was to be F.O.B. appellee’s truck at appellant’s bins. Paragraph 1 of the Instructions on the order provides: “Acknowledge receipt of this Purchase Order. Unless acknowledged immediately we reserve the right to cancel.” By on or about June 7, 1943, there had been delivered under the contract and paid for, 1,627.35 tons of concrete sand and 1,684.-745 tons of washed gravel. Oil that date appellant received a change in purchase order from appellee which was addressed to “Bennings, D.C.” This change decreased the original order by all remaining undelivered sand and gravel and in effect can-celled the balance of the purchase order. Thereafter appellant brought the present action for its alleged losses flowing from the cancelled contract.

The president of the appellant company, George Zouras, was the only witness in its behalf. He testified that at the time the purchase order was signed he was told that the sand and gravel was for the airport and “to keep on stock piling material because they would need it very soon.” By the time the decrease change had been received, appellant had stock piled the total sand and gravel called for by the contract. There was no complaint about the sand and gravel which was actually delivered under the order. The balance of the material “stayed in our yard” until the change of purchase order was received in June, 1943, six months after the original order. This was sold later on, but prior to that “most of the material had to be rewashed over again.” (Emphasis added.) The expense of this amounted to 85’% of the original cost of mining and washing. The total original cost per ton for producing both the sand and gravel was 35^ which gave appellant under the agreement 35^ a ton profit on the sand and 85^ a ton on the gravel.1 The undelivered balance of the sand and gravel was sold by appellant to other purchasers for 10?! a ton over the contract prices with appellee. The witness further generally stated that because of the contract appellant had refused definite orders at 85^ a ton for sand and $1.30 for gravel but he made no elaboration of that statement.

At the conclusion of the above testimony the defense moved “to dismiss on the ground that the evidence of the damages is too speculative to justify its submission to the jury.” The Court in dismissing the suit concluded that the testimony that “most of the material had to be rewashed over again” gave the jury no basis on which to figure damages regarding that item and that “the other proof about loss of orders was similarly indefinite.” He, therefore, found “that there is no proof sufficient in the case to establish any damages for the breach of contract.” Regarding the sole witness for the appellant he said:

“He testified that he reprocessed this gravel and sold it for $.10 more, both sand [828]*828and gravel, for $.10 more than the original purchase price. That first instance would indicate that there was no damage. In the second place, he didn’t show where any damage could arise. He talked about reprocessing the gravel, but he didn’t tell us how much gravel he reprocessed, and there is 25% of this upon which no claim can arise under the terms of the contract in any event.

* * * * * *

“As a matter of fact, he may have made money.”

Following the dismissal of the action on the application to set aside the judgment and grant a new trial, the Court “felt that it would be fair perhaps to let the plaintiff come in and say what he thought he could prove” and informally, without regard to evidential rules, permitted appellant to make an offer of proof. All of the further testimony that appellant “would have additional to what is'already in the record * * *” consisted of further testimony by Zouras. He, under the guidance of his attorney, was more specific this time in his figures. He said that the undelivered sand under the contract amounted to 8,372.65 tons and that all of that amount, with the exception of 150 tons in a bin, had to be reprocessed. Regarding the gravel, he stated that 8,315.25 tons were undelivered and that this too, less 150 tons in a bin, was reprocessed. Cross-examined as to how he knew that the material had been rewashed he said, “Because I went there to instruct after we had a talk to see what they need there. We have given instructions for the shovel operation and for the plant to carry on and rewash this material.” He had no-records of this, saying, “We don’t keep records as far as rewashing in concerned.”' As to seeing the sand rewashed he was asked, “You instructed them to do it .but you weren’t there to see them do it were you?” And he answered, “I can’t stay all day long there. I did stay there as long as I needed to be there and then I come back again to my place.” Asked how he knew material was not sold directly from the stock pile he said, “Because I was there. I knew it was-n’t done. I can see from the orders coming in, the contracts we have, and it was nothing of the kind for me not to know it." He said that his manager Griggs did all of appellant’s business with appellee and that most of his information came through Griggs. On redirect examination he said he visted the plant on occasion in the three months following June 1, 1943 and had given the men instructions regarding the reprocessing of the material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dell v. American Export Lines, Inc.
142 F. Supp. 511 (S.D. New York, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
162 F.2d 826, 1947 U.S. App. LEXIS 2198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-sand-gravel-co-v-brann-stuart-co-ca3-1947.