Washington Monumental & Cut Stone Co. v. Murphy

142 P. 665, 81 Wash. 266, 1914 Wash. LEXIS 1607
CourtWashington Supreme Court
DecidedAugust 14, 1914
DocketNo. 11612
StatusPublished
Cited by6 cases

This text of 142 P. 665 (Washington Monumental & Cut Stone Co. v. Murphy) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Monumental & Cut Stone Co. v. Murphy, 142 P. 665, 81 Wash. 266, 1914 Wash. LEXIS 1607 (Wash. 1914).

Opinion

Ellis, J.

— Action by a subcontractor against the principal contractor and his statutory bondsman, for work done by plaintiff upon a public building under its subcontract. On January 5, 1911, the defendant Murphy entered into a written contract with the city of Spokane School District No. 1, to erect a high school building in that city and furnish all the materials and labor therefor. An old school building on the same site had been destroyed by fire. It seems to be conceded that the general contractor had the right to use uninjured granite remaining on the ground in the construction of the new building. Pursuant to the statute, Rem. & Bal. Code, § 1159 et seq. (P. C. 309 § 93), the general contractor executed a bond, with the defendant Pacific Coast Casualty Company as surety, in an amount equal to the full contract price, conditioned, among other things, that the defendants would pay all laborers, mechanics, subcontractors and materialmen, and all just debts, dues and demands incurred in the performance of the work. The bond was delivered to the school board and filed with the auditor of Spokane county as [268]*268required by statute. On January 23, 1911, the plaintiff submitted to the defendant Murphy a bid for a subcontract for certain granite work, as follows:

On February 7, 1911, pursuant to this bid, Murphy and the plaintiff entered into a written contract, the portions of which material here are as follows:

“The party of the first part, [the plaintiff] agrees to recut all granite now on the building grounds that can be possibly used and to furnish, cut and deliver on said building grounds all new Spokane Granite that may be necessary to complete all granite steps, platforms, and the two granite courses as shown, as per plans and specifications of the New Central High School, of Spokane, for the sum of forty-eight hundred dollars ($4800).
“In consideration of the fulfillment of the above the party of the second part [defendant Murphy] agrees to pay the party of the first part the above named sum of forty-eight hundred dollars — paying 85 % on the tenth of each month, of the amount then cut and delivered on building grounds, and the final payment to be made in full within thirty days after the last stone has been delivered on the building grounds and accepted by the architect.
“Party of the second part also agrees to take down granite from the old walls and pile it in a suitable place so the granite cutters of the party of the first part can do the necessary cutting.”

The plaintiff entered upon the work and completed cutting the granite for the two granite courses, the steps and platforms, in accordance with the terms of its contract. The plaintiff claims that this was all that its contract called for. The defendant Murphy claims that the contract included the [269]*269cutting of granite for the buttresses as well. The school board, at a meeting held March 30, 1912, passed a resolution as follows:

“On motion of Mr. Long, it was voted to allow Mr. Murphy the balance on general contract on the Lewis & Clark High School up to 95% of the total amount, amounting to $12,-270. And it was further voted to accept the building, as far as interior construction, as per recommendation of Architect Rand. . .

It is admitted that no further action was taken by the board, except that, on May 13, 1912, the board paid the defendant Murphy the balance due on his general contract. On June 10, 1912, the plaintiff filed with the school board his claim in statutory form against the bond for the unpaid balance of the contract price stated in his contract for cutting granite. The plaintiff also claimed a small item for extra work in recutting some of the granite, necessitated by an error of the defendant Murphy, and $411 for cutting gi'anite used in the buttresses flanking the steps.

At the conclusion of the evidence, the court made findings of fact and conclusions of law, which, in effect, sustained the plaintiff’s contention that its contract did not contemplate buttresses as a part of the work; that it had substantially performed its contract, and was entitled to the balance of the contract price, and to pay for the additional work except that done on granite for the buttresses. Judgment was entered against the defendants in the sum of $1,251.03, and costs, from which they prosecute this appeal.

Both of the appellants insist that the judgment should be reversed because the evidence failed to show that the respondent had fully performed its contract. The casualty company insists, that, in any event, the action should be dismissed as to it, because there had been no formal acceptance of the exterior work on the school building by the school boax’d at the time the respondent filed its claim against the bond.

[270]*270I. The appellants’ argument under the first head is twofold. It is first asserted that, by the terms of its contract, the respondent agreed “to recut all granite now on the building grounds that can possibly be used.” It is said that it has not done this, hence has not completed its contract. This fragment is lifted bodily from the sentence of which it forms a part, without even so much as a separation by comma, much less by period. Taken in context, this language was clearly intended to evidence an agreement to recut only such granite then on the grounds as could be used for the purposes set out in the remainder of the same sentence with which it is used in the conjunctive, “and to furnish, cut -and deliver on said building grounds all new Spokane granite that may be necessary to complete all granite steps, platforms and the two granite courses as shown, as per plans and specifications,” etc. The obvious purpose of requiring the use of all old granite possible was to minimize the cost to the subcontractor. This phase of the argument hardly merits further notice.

It is next urged that, inasmuch as the plans and specifications referred to in the contract provided for buttresses flanking the steps and platforms, the buttresses are a part of the steps and therefore the contract included the cutting of the granite for these as well as for the “granite steps, platforms and the two granite courses.” Here again the conclusion comes perilously near being abortive for lack of sufficient premises. The contract itself would hardly seem ambiguous, since, by particularizing the things included: steps, platforms, and courses, it excluded all things not enumerated. If the word “steps” was used in some broad generic sense, as including everything in any way related to the steps proper, so as to include the buttresses, why use the word “platforms” at all? They, at least, are in a sense steps, while the buttresses are not. It is a matter of common knowledge that a platform in a stairway is, both in use and position, but a broader step or tread. A buttress, though sometimes employed as a balustrade, would hardly perform the office of a step in any connec[271]*271tion. Nor is it clear that any ambiguity was imported into the contract by its reference to the plans :and specifications. An examination of the plans of the school building shows the words “granite steps” with an arrow pointing to the steps alone, i. e., the treads.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ralph K. Simmons, V. Dept Of Labor & Industries
Court of Appeals of Washington, 2023
City Of Edmonds, V. The Edmonds Ebb Tide Assoc.
Court of Appeals of Washington, 2023
C-Star Concrete Corp. v. Hawaiian Insurance & Guaranty Co.
509 P.2d 758 (Court of Appeals of Washington, 1973)
Puget Sound Bridge & Dredging Co. v. Jahn & Bressi
268 P. 169 (Washington Supreme Court, 1928)
Denny-Renton Clay & Coal Co. v. National Surety Co.
160 P. 1 (Washington Supreme Court, 1916)
Union Iron Works v. Strauser
143 P. 446 (Washington Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
142 P. 665, 81 Wash. 266, 1914 Wash. LEXIS 1607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-monumental-cut-stone-co-v-murphy-wash-1914.