Washington Hotel Realty Co. v. Bedford Stone & Construction Co.

143 N.E. 156, 195 Ind. 128, 1924 Ind. LEXIS 114
CourtIndiana Supreme Court
DecidedMarch 20, 1924
DocketNo. 23,516.
StatusPublished
Cited by21 cases

This text of 143 N.E. 156 (Washington Hotel Realty Co. v. Bedford Stone & Construction Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Hotel Realty Co. v. Bedford Stone & Construction Co., 143 N.E. 156, 195 Ind. 128, 1924 Ind. LEXIS 114 (Ind. 1924).

Opinion

*131 Willoughby, J.

J.—This was an action by the Bedford Stone and Construction Company, appellee, against the Washington Hotel Realty Company, and J. Edward Krause, for an alleged balance due upon a contract between the appellant and appellee for the construction of the Washington Hotel in Indianapolis, and also for the recovery of alleged extras in connection therewith.

The complaint is in five paragraphs. The first paragraph seeks to recover from the appellant a balance alleged to have been due from the hotel company under the terms of plaintiff’s contract for construction of the hotel. In addition to said amount, it charges that the plaintiff, at the special instance and request of the hotel company and Krause procured the plaintiff to furnish extras in the sum of about $25,000 for which it seeks recovery, against both defendants. The second paragraph of complaint, omitting any alleged balance as against the hotel company on the construction contract, alleges that the defendants, the hotel company and Krause, specially requested the plaintiff to install certain extras in said hotel in the sum of about $25,000.

The third paragraph alleges an unpaid balance of $13,000 on the construction contract as against the hotel company and further alleges that both defendants were indebted $25,000 for alleged extras furnished at their request.

The fourth paragraph of complaint seeks to recover as against both defendants the sum of $25,000 on account of extras furnished at their special instance and request.

The fifth paragraph is against the hotel company alone and is upon the quantum meruit, for the alleged cost of the hotel.

To the .first, second, third, fourth and fifth paragraphs of complaint, the Washington Hotel Realty Company answered as follows: First: General denial. Sec *132 ond: Payment. Third: Failure to perform the contract and damages therefor, setting out the items thereof. Fourth: Liquidated damages by virtue of the contract. Fifth: Defective performance of the contract, setting out the defects and asking for judgment over against the plaintiff.

The defendant, Krause, answered all paragraphs by general denial. Plaintiff then filed a reply in three paragraphs to the hotel realty company’s second, third, fourth, and fifth paragraphs of answer. It further filed an answer in three paragraphs to the defendant’s third, fourth and fifth paragraphs' of answer, described as counterclaims. A trial was had and judgment rendered against both of the defendants—against the hotel company for $16,313.14 and against defendant Krause for $2,710.80. Krause satisfied the judgment against him and a new trial was granted to the hotel company on its motion therefor.

The answers theretofore filed by defendant hotel company were withdrawn and the hotel company filed its answer in six paragraphs, as follows: First: General denial. Second: Payment. Third: Payment of certain specified items. Fourth: Counterclaim. Liquidated damages for failure to deliver hotel on contract time. Fifth: Counterclaim. Liquidated damages. Sixth: Counterclaim for certain specified defects in the construction of said building, and demanding judgment for $25,000.

Said hotel company filed its answer in two paragraphs to the fifth paragraph of complaint as follows: Tenth: General denial. Eleventh: That said hotel was constructed under and by virtue of a contract and setting out wherein the plaintiff failed to perform said contract, and demanding judgment on account of said failure to perform.

Plaintiff replied in four paragraphs to the second, *133 third, fourth, fifth and sixth paragraphs of answer as follows: First: General denial. Second: That certain parts of said building were not completed upon contract time but that the fault was with the defendant hotel company. Third: That the delay in completion was caused by extrae and changes in plans and that the contract in reference thereto was mutually waived. Fourth: That failure to install certain specified items was caused by the directions of defendant hotel company.

The plaintiff further filed, an answer in four paragraphs to the fourth, fifth and sixth paragraphs of answer and counterclaim of the hotel company as follows: First: General denial. Second: Failure to complete building was caused by changes ordered and extras ordered by the defendant. Third: Negligence of hotel company caused delays complained of in defendant’s answer. Fourth: Failure to install certain fixtures caused by failure of detailed plans to include same.

The plaintiff further replied in three paragraphs to the eleventh paragraph of answer of the hotel company as follows: First: General denial. Second: Waiver of provisions for delivery of building in that the hotel company was responsible for delay. Third: That plaintiff was not required to install certain fixtures by reason of omission from detailed plans.

Plaintiff further answered in three paragraphs to defendant’s answer by way of counterclaim, filed March 2, 1916, as follows: First: General denial. Second: Waiver of provisions requiring delivery of building on certain date on the ground that defendant was responsible for said delay. Third: Failure to install certain fixtures not required by detailed plans.

The hotel company filed its reply to the plaintiff’s second and third paragraphs of answer to its counterclaim by a general denial and also filed a general denial *134 to the seqond, third and fourth paragraphs of answer to its separate counterclaim filed February 17, 1916. The hotel company, by leave of court, filed its fourteenth and fifteenth paragraphs of separate answer, alleging that, since the beginning of this action, the judgment rendered in favor of the plaintiff as against the defendant Krause, for the alleged extras, had been satisfied and paid in full by defendant Krause.

The plaintiff filed separate demurrer to each the fourteenth and fifteenth paragraphs of answer of the defendant Washington Hotel Realty Company. The plaintiff’s demurrer as to the fourteenth paragraph of answer was sustained and it was overruled as to the fifteenth paragraph.

The cause was submitted to a jury for trial which resulted in a verdict for the plaintiff in the sum of $30,000.- A motion for a new trial was filed by appellant. The judge ordered a remittitur of $1,800 and thereupon overruled the motion for a new trial and rendered judgment for $28,200. From such judgment, this appeal is taken. The errors alleged and relied on for reversal are, sustaining appellee’s demurrer to the fourteenth paragraph of answer, and the overruling of appellant’s motion for a new trial.

The first question to be considered is the demurrer to the fourteenth paragraph of defendant’s answer. Appellant contends that in the first trial of the cause, the judgment against the defendant Krause having been fully paid and satisfied, was full defense to this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. State
309 N.E.2d 833 (Indiana Court of Appeals, 1974)
Robinson v. Priest
256 N.E.2d 582 (Indiana Court of Appeals, 1970)
Miller v. Deming Hotel Co.
213 N.E.2d 809 (Indiana Court of Appeals, 1966)
City of Shelbyville v. MORTON, ETC.
208 N.E.2d 705 (Indiana Court of Appeals, 1965)
Board of Commissioners v. Flowers
201 N.E.2d 571 (Indiana Court of Appeals, 1964)
Stahl v. Kincade
192 N.E.2d 493 (Indiana Court of Appeals, 1963)
New York Central Railroad v. Milhiser
106 N.E.2d 453 (Indiana Supreme Court, 1952)
Hayes Freight Lines, Inc. v. Wilson
77 N.E.2d 580 (Indiana Supreme Court, 1948)
Emge v. Sevedge
76 N.E.2d 687 (Indiana Court of Appeals, 1948)
Angola State Bank v. State Ex Rel. Sanders
52 N.E.2d 620 (Indiana Supreme Court, 1944)
Keesler, Admx. v. Loy
43 N.E.2d 615 (Indiana Supreme Court, 1942)
Finerty, Auditor v. State Ex Rel. Greenwald
19 N.E.2d 846 (Indiana Supreme Court, 1939)
Johann Realty Corp. v. Kirkpatrick, Admr.
189 N.E. 843 (Indiana Court of Appeals, 1932)
Rowley v. Pogue
178 N.E. 449 (Indiana Supreme Court, 1931)
Garman v. State Ex Rel. Sprang
173 N.E. 640 (Indiana Court of Appeals, 1930)
State, Ex Rel. v. Hinds, Trustee
165 N.E. 754 (Indiana Supreme Court, 1929)
Henderson v. State Ex Rel. Powers-Thompson Construction Co.
154 N.E. 378 (Indiana Supreme Court, 1926)
Washington Hotel Realty Co. v. Bedford Stone & Construction Co.
148 N.E. 405 (Indiana Supreme Court, 1925)
Martindale v. Corbin
145 N.E. 926 (Indiana Court of Appeals, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
143 N.E. 156, 195 Ind. 128, 1924 Ind. LEXIS 114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-hotel-realty-co-v-bedford-stone-construction-co-ind-1924.