Washington Gas Light Co. v. Leo Construction Co.

48 Va. Cir. 237, 1999 Va. Cir. LEXIS 64
CourtLoudoun County Circuit Court
DecidedFebruary 26, 1999
DocketCase No. (Law) 20715
StatusPublished

This text of 48 Va. Cir. 237 (Washington Gas Light Co. v. Leo Construction Co.) is published on Counsel Stack Legal Research, covering Loudoun County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Gas Light Co. v. Leo Construction Co., 48 Va. Cir. 237, 1999 Va. Cir. LEXIS 64 (Va. Super. Ct. 1999).

Opinion

By judge Jean Harrison Clements

This case came before the Court on February 18 and 19, 1999, for trial without a jury upon Plaintiff Washington Gas Light Company’s Amended Motion for Judgment against Leo Construction Company, Defendant, and its Answer and Grounds of Defense thereto. Evidence was presented; the case was argued by counsel, and taken under advisement by the Court.

Plaintiff is a corporation organized under the laws of Virginia and is a natural gas distribution company which provides public utility service in northern Virginia, including Loudoun County. Its gas distribution system includes underground utility lines. Defendant, a corporation organized under the laws of the Commonwealth of Virginia, engages in excavation which includes excavation around underground utility lines.

Plaintiff alleged Defendant was negligent and caused damage to its lines in twelve separate counts and seeks recovery for actual/compensatoiy damages with pre-judgment and post-judgment interest and costs. Plaintiff further seeks triple damages plus pre-judgment and post-judgment interest and costs. The dates and places of damage are as follows:

Count I Lot 14, Peregrine Court Montclair, Virginia November 19,1996

[238]*238Count n Lot 21, Rhode Island Avenue Dale City, Virginia November 23,1996

Count in 4741 Thombury Drive Fairfax County, Virginia January 22,1997

Count IV 406 North Street Leesburg, Virginia February 17,1997

CountV Lot 52, Foal Court Gainesville, Virginia April 4,1997

Count VI Lot 62, Hyde Paik Drive Sterling, Virginia April 30,1997

Count VII Lot 3, Estate Place Ashbum, Virginia May 22,1997

Count VIH Lots 223 and 229, Michael Court July 16,1997 Manassas, Virginia

Count IX Lot 56, Medix Run Place Ashbum, Virginia August 6,1997

Count X Lot 193, Covent Garden Way Ashbum, Virginia August 11,1997

Count XI Lot 821, Crowning Place Gainesville, Virginia September 19,1997

Count XII 11334 Kessler Place Manassas, Virginia October 9,1997

hi its Answer and Grounds of Defense and in its opening statement, counsel for Defendant admitted negligence and liability to the allegations in Counts 3,6,7,9,10, and 11. Negligence and liability is denied as to Counts 1,2,4,5,8, and 12. Although Defendant acknowledges that its actions in fact damaged Plaintiff’s utility lines as alleged, compensatoiy damages as to all Counts, except in Count 11, are in dispute, hi its closing argument, defendant, [239]*239by counsel, agreed to Plaintiffs compensatory damages in the amount of $974.73, for Count 11. Defendant denies any liability for triple damages sought by Plaintiff pursuant to § 56-5, Code of Virginia.

The Court will address the evidence of Counts 1,2,4,5,8, and 12 first. This case involves several sections of the Underground Utility Damage Prevention Act, specifically § 56-265.17, § 56-265.18, § 56-265.19, § 56-265.24, and § 56-265.25. On the issue of triple damages, § 56-5 is applicable.

Defendant, as an excavator, was required to notify “Miss Utility” (the notification center) before beginning excavation. The requirements of a Notice are designated in § 56-265.18. Plaintiff, as operator, was then assigned duties pursuant to § 56-265.19. In each instance of this case, those duties were carried out by Byers Locate Service. If there was an underground line that could be damaged, then Byers was to “mark” the line on the ground to within two feet of either side by stakes, by high visibility safety yellow paint (for gas), or by flags no later than 48 hours after receiving Defendant’s Notice through “Miss Utility.” Byers then had to report to “Miss Utility” no later than 48 hours that the location had been marked or that there were no utility lines within such proximity of the excavation or demolition that may be damaged by the excavator.

Defendant was required to wait at least 48 hours after Notice before commencing work. If “Miss Utility” felled to respond to Defendant within 48 hours, then Defendant was required to wait an additional 24 hours before commencing work.

Defendant’s notification to “Miss Utility,” called a “Ticket,” was valid for fifteen working days from the date Defendant gave Notice, and two days before the end of the period, or at any time the “marks” became illegible, Defendant was to call “Miss Utility” and request a “remark.”

If the Defendant was excavating within two feet of either side of a staked or marked line, it was required to take all reasonable steps necessary to properly protect, support, and backfill the lines, including but not limited to “hand digging.” Upon arrival at the site, and, if the Defendant observed clear evidence of the presence of an unmarked line in the area of the proposed excavation, it was not to begin until three hours after an additional call to “Miss Utility.” Defendant was required at all times to exercise due care to protect Plaintiff’s underground lines.

In the event of damage to an underground line, Defendant was required to immediately notify Plaintiff. Plaintiff was to repair the damage. Defendant, however, was responsible to take immediate steps reasonably calculated to safeguard life, health, and property if the damages created an emergency.

[240]*240Count I. Defendant notified “Miss Utility” on November 13,1996, of intent to excavate, and Byers accurately marked the lines on November 14, 1996. Defendant cut the stub off of a “dry cross” below ground when it trenched behind the location of the marker. The “Ticket” clearly showed lines marked and stubs. Defendant’s operator testified he saw no marks. Defendant was negligent in Ming to observe the marks or call for three hours’ Notice or “remark” in view of the information on the “Ticket.”

Count n. On November 13, 1996, Defendant notified “Mss Utility” of intent to excavate, and Byers was given the Notice. However, on November 14,1996, Defendant’s employee “Kevin” “waived Byers off,” and no locate was done. Eight feet from the lot was a visible gas line stake. Defendant was excavating on a site without a valid “Ticket.” Defendant “hung a crossing” with a backhoe. Defendant “crimped” over the broken line with electrical tape. Defendant was negligent in excavating without a valid “Ticket,” in failing to call for “marks,” and failing to observe clear evidence of the presence of an unmarked gas line. Although Plaintiff testified that “crimping” a gas line emitting escaping gas was illegal and dangerous, the Court has no evidence as to the other circumstances at the time of the break. The Court construes Plaintiffs evidence to be a situation in which Defendant could perceive an emergency but cannot conclude that the steps taken were unreasonable when Defendant took them.

Count IV. On February 7, 1997, Defendant notified “Mss Utility” of intent to excavate, and Byers accurately marked the lines on February 10, 1997. Defendant’s Supervisor testified there were no marks on site on February 17, 1997. A 3/4 inch gas service line was cut. There was considerable evidence and argument over gas lines and service to other lots in the area and a riser/meter that was or should have been visible on the side of an adjacent house. The Court finds that the Defendant was negligent in failing to observe the marks or, if they were obliterated after marking, in Ming to call for three hours’ Notice or “re-mark” in view of the information on the “Ticket.”

Count V.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
48 Va. Cir. 237, 1999 Va. Cir. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-gas-light-co-v-leo-construction-co-vaccloudoun-1999.