Washington Coho, Llc, V. Whatcom County

CourtCourt of Appeals of Washington
DecidedJanuary 6, 2025
Docket86498-0
StatusUnpublished

This text of Washington Coho, Llc, V. Whatcom County (Washington Coho, Llc, V. Whatcom County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Coho, Llc, V. Whatcom County, (Wash. Ct. App. 2025).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

WASHINGTON COHO, LLC, a No. 86498-0-I Washington limited liability company, DIVISION ONE Appellant,

v. UNPUBLISHED OPINION

WHATCOM COUNTY, a municipal corporation,

Respondent.

SMITH, C.J. — Washington Coho, LLC, sought a variance permit from

Whatcom County. The County approved the permit request more than two years

after Coho’s application was deemed complete. Less than a month after the

permit was approved, Coho requested a resolution under Whatcom County Code

(WCC) 22.05.130(2). When the County denied relief under WCC 22.05.130(2),

Coho brought an action for damages under RCW 64.40.020. The County moved

to dismiss, asserting Coho’s claim was barred by the statute of limitations. The

trial court found Coho’s action untimely because WCC 22.05.130(2) did not

create an administrative remedy that had to be exhausted under

RCW 64.40.030. Coho appeals. We affirm the dismissal of Coho’s complaint.

FACTS

Background

Washington Coho, LLC, owns real property in Whatcom County,

Washington. In May 2021, Coho submitted an application to the County for a No. 86498-0-I/2

shoreline variance to construct a single-family residence and relocate an existing

float plane hangar. The County e-mailed Coho’s legal counsel, informing them

Coho’s application would not be complete until Coho submitted a habitat and

critical areas report. Coho submitted the requested information and the County

deemed the application complete in October 2021. In April 2022, Coho received

a notice of additional requirements (NOAR) from the County requesting a

stormwater system design. Coho sent a preliminary stormwater report in August

2022. The County contacted Coho in October 2022 with concerns about the

stormwater report. A hearing on the variance was held in January 2023. The

hearing examiner approved the variance on January 30, 2023, which constituted

a final decision of approval for Coho’s application.

In March 2023, Coho e-mailed the County requesting a resolution under

RCW 22.05.130(2) concerning permit delays on the County’s review of the

application. In a meeting with the Director of Planning and Development

Services on March 24, 2023, Coho requested a “mutually acceptable resolution

as provided in WCC 22.05.130(2) subpart (c)” or, in the alternative, Coho would

bring a claim under RCW 64.40.020. Following the meeting, the County’s

prosecuting attorney e-mailed Coho and informed them that any claim under

RCW 64.40.020 is barred by the 30-day statute of limitations. The Director

followed up with an e-mail stating the meeting with Coho was a courtesy and any

remedy under WCC 22.05.130(2) is not applicable once a permit has been

issued.

2 No. 86498-0-I/3

On April 17, 2023, Coho initiated a complaint in Skagit County Superior

Court asserting two causes of action: (1) declaratory relief under RCW 7.24 and

(2) violation of RCW 64.04.20. The trial court dismissed both claims and found

WCC 22.05.130(2) did not create an administrative remedy that had to be

exhausted under RCW 64.40.030. Coho appeals.

ANALYSIS

Standard of Review

We review dismissal under CR 12(b)(6) de novo, considering the record

as a whole and taking all facts alleged in the complaint as true. Burton v.

Lehman, 153 Wn.2d 416, 422, 103 P.3d 1230 (2005); FutureSelect Portfolio

Mgmt., Inc. v. Tremont Grp. Holdings, Inc., 180 Wn.2d 954, 961, 331 P.3d 29

(2014). We may also “consider hypothetical facts not included in the record.”

Tenore v. AT&T Wireless Servs., 136 Wn.2d 322, 330, 962 P.2d 104 (1998).

Dismissal for failure to state a claim “is appropriate only if it appears beyond

doubt that the plaintiff cannot prove any set of facts which would justify recovery.”

Tenore, 136 Wn.2d at 330.

Administrative Remedy

Neither party contends WCC 22.05.130(2) is not an administrative

remedy. Rather, the parties dispute whether WCC 22.05.130(2) provides

adequate relief to require exhaustion and whether Coho timely initiated the

remedy. We conclude Coho failed to timely initiate the remedy.

When interpreting the meaning of an ordinance, courts rely on the same

principles that apply to statutory interpretation. Ellensburg Cement Prod., Inc. v.

3 No. 86498-0-I/4

Kittitas County, 179 Wn.2d 737, 743, 317 P.3d 1037 (2014). When the language

of an ordinance is ambiguous, “the section under construction should be read in

context with the entire act and a meaning ascribed to it that avoids strained or

absurd consequences.” Standing v. Dep't of Lab. & Indus., 92 Wn.2d 463, 474,

598 P.2d 725 (1979). When there appears to be a conflict between a local

ordinance and a state statute, if the ordinance can “be read in harmony” with the

statute, “no conflict will be found.” Watson v. City of Seattle, 189 Wn.2d 149,

171, 401 P.3d 1 (2017).

1. Timeliness of Action

Coho claims a remedy under WCC 22.05.130(2) can be pursued either

during or after the permitting process. The County contends WCC 22.05.130(2)

is only meant to provide relief for applicants who have not yet had a permit

issued and, therefore, Coho’s request was untimely. We agree Coho’s request

was untimely, but for reasons distinct from those put forth by the County.

The permit application process in Whatcom County is governed by

WCC 22.05. Whatcom County is required to “issue a notice of final decision for

all permit types . . . within 120 calendar days of the date the department

determined the application complete.” WCC 22.05.130(1). When an applicant

believes the department has not acted in a timely manner, the applicant “may

request a meeting with the director to resolve the issue.” WCC 22.05.130(2).

Within 14 days of the meeting, the director must take one of the following actions: (a) Approve the permit if it is within the director’s authority to do so, provided the approval would not violate state or county regulations; or

4 No. 86498-0-I/5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standing v. Department of Labor & Industries
598 P.2d 725 (Washington Supreme Court, 1979)
Tenore v. AT&T Wireless Services
962 P.2d 104 (Washington Supreme Court, 1998)
Burton v. Lehman
103 P.3d 1230 (Washington Supreme Court, 2005)
Ellensburg Cement Products, Inc. v. Kittitas County
317 P.3d 1037 (Washington Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Washington Coho, Llc, V. Whatcom County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-coho-llc-v-whatcom-county-washctapp-2025.