Washington Brick, Lime & Sewer Pipe Co. v. Anderson

29 P.2d 690, 176 Wash. 416, 1934 Wash. LEXIS 475
CourtWashington Supreme Court
DecidedFebruary 15, 1934
DocketNo. 24866. Department One.
StatusPublished
Cited by5 cases

This text of 29 P.2d 690 (Washington Brick, Lime & Sewer Pipe Co. v. Anderson) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Brick, Lime & Sewer Pipe Co. v. Anderson, 29 P.2d 690, 176 Wash. 416, 1934 Wash. LEXIS 475 (Wash. 1934).

Opinion

Steinert, J.

— In its complaint containing three causes of action, plaintiff sought to recover for quantities of building material furnished and delivered by it to defendant. The answer of the defendant contained certain denials; then, by way of an affirmative defense, pleaded an offset and counterclaim, and concluded with a cross-complaint setting forth a series of *417 five separate causes of action against the plaintiff. Trial was had before a jury. A verdict having been returned in favor of defendant, judgment was entered thereon, from which plaintiff has appealed.

The respondent, in 1930, entered into a contract with the Federal government for the construction of the United States immigration and assay office at Seattle. The construction necessitated the use of certain architectural terra cotta, interior tile and brick. Appellant, a manufacturer of such materials, entered into a series of contracts with respondent for the manufacture and delivery to the latter of certain specified supplies for use on the job. A statement of the issues, as made by the pleadings, will contribute toward a better understanding of the questions presented by this appeal.

First, with reference to the complaint: The first cause of action was for the recovery of a balance of $401.50 for architectural terra cotta delivered under a written contract. The second cause of action was for the recovery of $2,719.05, the balance claimed to be owing for salt-glazed tile and slip-glazed tile furnished under two written contracts, and for the further sum of $816.70, the reasonable value of additional salt-glazed tile which was necessary on account of certain breakage attributable to respondent’s negligence. The third cause of action was to recover a balance of $1,917.45 for a quantity of brick sold and delivered to respondent at his special instance and request. The total of appellant’s claims amounted to $5,854.70.

Respondent admitted the execution of the various written contracts referred to in the first and second causes of action of the complaint, but denied that the material had been delivered according to specifications. He further denied the delivery of the additional salt-glazed tile for which a recovery of $816.70 was sought. *418 •As to the third cause of action, respondent admitted receiving a portion of the brick, but denied in its entirety any valid claim therefor. Then followed, in the answer, a series of six affirmative defenses, the first being in the nature of an offset and counterclaim, and the others being pleaded by way of cross-complaint.

In the first affirmative defense, respondent demanded that he be allowed an offset of $401.50 against appellant’s first cause of action, because the material therein described did not comply with the specifications of the contract, but were of defective quality. In the second affirmative defense, made a cross-complaint, respondent demanded $850 for expense incurred by reason of delay in delivery and for rehandling the material. In the third affirmative defense, pleaded as a cross-complaint, respondent sought to recover an aggregate sum of $3,154.60 for faulty material, irregular deliveries, expense of recutting a portion of the tile and loss of time. In the fourth affirmative defense, incorporated in a cross-complaint, respondent sought to recover the sum of $480 for other expenses incurred by reason of delay in delivery of a portion of the material.

The fifth affirmative defense and cross-complaint has a very important bearing upon the main question presented here. Respondent sought therein to recover the sum of $2,324.75, which he claimed represented the impaired efficiency of the crew in the performance of their work, occasioned (1) by the delivery of irregular-shaped and faulty material, (2) by delay and irregularity in deliveries of material, and (3) by the failure of appellant to furnish setting or construction plans showing where the various pieces of tile were to be placed in the progress of construction. Whether appellant was obligated to furnish such plans, was a vital *419 question in the case, and underlay the scope and validity of the verdict.

The sixth and final affirmative defense, also characterized as a cross-complaint, claimed a loss of $600, interest upon a stagnated investment because of delay in the completion of construction. The total of respondent’s claims amounted to $7,810.85. In its reply, appellant denied the various claims of respondent.

The jury returned a verdict for respondent in a lump sum of $453.50. The form of the verdict affords no clue as to how the jury arrived at the final result, nor does it indicate how the jury disposed of the respective contentions with respect to the specific claims. We have simply a single, comprehensive result, without mathematical segregation.

The ramified questions of fact suggested by the foregoing outline of the issues furnished a lengthy trial and an extensive record, the result of which is now before us. The assignments of error, however, present but three questions, which we now proceed to examine.

The trial court gave instruction No. 10%, as follows:

Defendant claims that plaintiff should have furnished what is known as a setting or construction plan with the tile to aid in the proper laying of the tile and particularly the special pieces thereof. While the tile contract in question between the parties does not specifically require the furnishing of any such plan, yet if you find from the evidence that the custom and practice of the trade required that a setting or construction plan be furnished with such tile then I instruct you that such plan should have been furnished by the plaintiff.” (Italics ours.)

The giving of this instruction is assigned as the first and principal error.

A setting or construction plan consists of a drawing or plan showing the location for each piece of tile in *420 the building’, according to corresponding numbers. To have prepared such a plan would have cost, as the evidence discloses, approximately eight thousand dollars. As the instruction itself indicates, the contract did not specifically require the appellant to furnish such plan. Further, the contract contained an express provision to the effect that it was complete in itself, and that the obligations incurred therein by the parties should not be added to or modified by any other provision, in writing or otherwise.

The respondent sought to establish a usage or custom of trade requiring the manufacturer to accompany the delivery of such material with a setting plan. Bespondent’s evidence, however, did not meet the requirements of the pertinent rules upon the subject. Several witnesses, testifying from the standpoint of contractors, stated that such plans would have very practical value and would greatly assist the contractor in expediting the work of construction; that, under ordinary and reasonably good practice, the material should be accompanied by a setting plan. Other witnesses, testifying as experts, stated that they would, in their own cases, have required such plans, and that they believed that the manufacturer should supply them, because of their assistance to the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglass v. Stachecki
537 P.2d 1044 (Court of Appeals of Washington, 1975)
Dingler v. Simpson
364 P.2d 181 (Idaho Supreme Court, 1961)
Seattle Flower & Bulb Co. v. E. S. Burgan & Sons, Inc.
271 P.2d 704 (Washington Supreme Court, 1954)
Barbee Mill Co. v. State
261 P.2d 418 (Washington Supreme Court, 1953)
Dant & Russell, Inc. v. Grays Harbor Exportation Co.
26 F. Supp. 784 (W.D. Washington, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
29 P.2d 690, 176 Wash. 416, 1934 Wash. LEXIS 475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-brick-lime-sewer-pipe-co-v-anderson-wash-1934.