Wash. Gas Light Co. v. Md. Pub. Serv. Comm'n

191 A.3d 460, 460 Md. 667
Court of Appeals of Maryland·Decided August 14, 2018·No. 81/17·Published·Cited by 21 cases

Opinion

Getty, J.

Legislative intent
(b) It is the intent of the General Assembly that the purpose of this section is to accelerate gas infrastructure improvements in the State by establishing a mechanism for gas companies to promptly recover reasonable and prudent costs of investments in eligible infrastructure replacement projects separate from base rate proceedings.
-Statement of "Legislative Intent," Senate Bill 8, 2013 Md. Laws, ch. 161, § 1.

In this appeal, we are asked to interpret Public Utility Article ("PU") § 4-210 of the Maryland Code, known also as the STRIDE statute. 1 In short, the STRIDE statute allows Maryland gas companies more timely cost recovery if they submit plans that increase the pace of natural gas infrastructure improvements.

The General Assembly passed the STRIDE statute (Senate Bill 8) in response to increasing concerns about threats to public safety posed by aging and deteriorating gas infrastructure throughout the state. 2 The Fiscal and Policy Note for Senate Bill 8 highlighted the occurrence of "30 'significant [pipeline] incidents' in Maryland from 2002 through 2011, totaling $12 million in property damage and causing one fatality and 16 injuries." Dep't Leg. Servs., Fiscal and Policy Note, Senate Bill 8 , at 6 (2013 Session) (hereinafter cited as "Senate Bill 8 Fiscal Note"). To underscore the importance of providing Maryland residents with a safe and reliable gas distribution infrastructure throughout the State, the legislature codified a rarely used express statement of legislative intent. See PU § 4-210(b).

Petitioner Washington Gas Light Company ("Washington Gas") asserts that the Maryland Public Service Commission ("the Commission"), the Circuit Court for Montgomery County, and the Court of Special Appeals each erred in their statutory analysis, from which they ultimately concluded that the STRIDE statute provides accelerated cost recovery only for gas infrastructure projects located in the State of Maryland. Respondents Maryland Office of People's Counsel ("OPC") 3 and the Commission argue that the prior tribunals' interpretation of PU § 4-210 was correct. We are therefore called upon to conduct statutory interpretation, analyzing both the plain language and the legislative history of PU § 4-210.

For the following reasons, we conclude that PU § 4-210 is unambiguous and requires that "gas infrastructure improvements" be located "in the State" in order to promptly recover investment costs separate from base rate proceedings. We also hold that the STRIDE statute's legislative history supports this interpretation. Accordingly, we affirm the judgment of the Court of Special Appeals.

BACKGROUND

A. The Parties

Washington Gas is a public service company that provides natural gas and delivery services to customers in the Maryland counties of Montgomery, Prince George's, Charles, Calvert, St. Mary's, and Frederick, as well as customers in Washington, D.C. and jurisdictions in Virginia. To transport natural gas to its customers, Washington Gas operates a system of distribution pipelines spanning its geographic service area throughout Maryland, Virginia, and Washington, D.C.

The Commission is tasked with regulating Maryland public service companies, including Washington Gas, and its duties are summarized in Maryland Off. of People's Counsel v. Md. Pub. Serv. Comm'n :

The Maryland Public Service Commission is an independent unit in the executive branch of State government (PU[ ] § 2-101(b) ), with jurisdiction over public service companies that operate utility businesses within the State. PU[ ] § 2-112(a). The Commission's primary duties are to "supervise and regulate" the companies subject to its jurisdiction[,] to "ensure their operation in the interest of the public[,]" and to "promote adequate, economical, and efficient delivery of utility services in the State without unjust discrimination [.]" PU[ ] § 2-113(a)(1)(i).

226 Md.App. at 488, 130 A.3d 1061 . The statutory authority for the Commission's regulation of public service companies is provided in Title Four of the Public Utilities Article.

Washington Gas has a duty to "charge just and reasonable rates for the regulated services that it renders," PU § 4-201, and the Commission retains "the power to set a just and reasonable rate of a public service company[.]" PU § 4-102(b). Generally, the Commission determines just and reasonable rates for a public service company by accounting for the company's "income and expenses during a test year, calculating the rate base (the fair value of the property used and useful in rendering service) during that year, determining the utility's cost of capital (its required rate of return), and then multiplying that rate of return against the rate base." Bldg. Owners & Managers Ass'n of Metro. Baltimore, Inc. v. Pub. Serv. Comm'n of Maryland , 93 Md.App. 741 , 753, 614 A.2d 1006 (1992). The Commission may order an adjustment in the company's rates if the utility's level of income deviates significantly from the test year's net income. See id. Importantly, prior to the enactment of the STRIDE statute, a public service company would recover the costs of investment in infrastructure improvements through distribution rates, determined with the Commission, after the work was completed . PU § 4-101(3) (defining "just and reasonable rate" as "a reasonable rate on the fair value of the public service company's property used and useful in providing service to the public ." (Emphasis added) ).

B. The STRIDE statute - PU § 4-210

Beginning in 2011, the General Assembly considered legislation to accelerate replacement of aging gas infrastructure and allow cost recovery separate from base rate proceedings. See S.B. 8, 2013 Reg. Sess. (cross-filed as H.B. 89); S.B. 541, 2012 Reg. Sess. (cross-filed as H.B. 662); S.B. 332, 2011 Reg. Sess. (cross-filed as H.B. 856). On February 22, 2013, the General Assembly enacted a bill titled "An Act Concerning Gas Companies-Rate Regulation-Infrastructure Replacement Surcharge," the STRIDE statute, creating an exception to the normal ratemaking process. The law took effect on June 1, 2013. 2013 Md. Laws, ch. 161, § 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Wash. Gas Light Co. v. Md. Pub. Serv. Comm'n, 191 A.3d 460, 460 Md. 667 (Md. 2018).

191 A.3d 460 (Wash. Gas Light Co. v. Md. Pub. Serv. Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bailey v. Happer
Court of Special Appeals of Maryland, 2026
Cerrato v. Garner
Court of Special Appeals of Maryland, 2023
107oag093
Maryland Attorney General Reports, 2022
Maryland Attorney General Opinion 107OAG093
Maryland Attorney General Reports, 2022
Lawrence v. State
257 A.3d 588 (Court of Appeals of Maryland, 2021)
Wheeling v. Selene Finance
250 A.3d 197 (Court of Appeals of Maryland, 2021)
Maryland Attorney General Opinion 106OAG067
Maryland Attorney General Reports, 2021
United Bank v. Buckingham
247 A.3d 336 (Court of Appeals of Maryland, 2021)
Winner, LTD v. Pabst Brewing
245 A.3d 242 (Court of Special Appeals of Maryland, 2021)
Kemp v. Nationstar Mortgage
239 A.3d 798 (Court of Special Appeals of Maryland, 2020)
Berry & State Farm v. Queen
233 A.3d 42 (Court of Appeals of Maryland, 2020)
Neal v. Balt. City Brd. of School Commissioners
225 A.3d 66 (Court of Appeals of Maryland, 2020)
Johnson v. State
225 A.3d 44 (Court of Appeals of Maryland, 2020)
Andrews & Lawrence v. Mills
223 A.3d 947 (Court of Appeals of Maryland, 2020)
David A. v. Karen S.
213 A.3d 685 (Court of Special Appeals of Maryland, 2019)
Town of Forest Heights v. M-NCPPC
463 Md. 469 (Court of Appeals of Maryland, 2019)
In re: O.P.
205 A.3d 129 (Court of Special Appeals of Maryland, 2019)
Johnson v. Francis