Waseca County v. Minnesota Department of Transportation
Opinion
This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).
STATE OF MINNESOTA
IN COURT OF APPEALS
A15-1850
Waseca County, et al.,
Appellants,
vs.
Minnesota Department of Transportation, Respondent.
Filed June 27, 2016
Affirmed
Schellhas, Judge
Steele County District Court File No. 74-CV-15-991
Justin P. Weinberg, Jonathan P. Schmidt, W. Knapp Fitzsimmons, Briggs and Morgan, P.A., Minneapolis, Minnesota (for appellants)
Lori Swanson, Attorney General, Stephen D. Melchionne, Assistant Attorney General, St. Paul, Minnesota (for respondent)
Considered and decided by Schellhas, Presiding Judge; Peterson, Judge; and Reyes, Judge.
UNPUBLISHED OPINION
SCHELLHAS, Judge Appellants challenge the district court’s rule-12.02(e) dismissal of their complaint.
We affirm.
FACTS
We set forth the facts as alleged in the complaint and its exhibits. See Walsh v. U.S.
Bank, N.A., 851 N.W.2d 598, 601, 606 (Minn. 2014) (stating that, when reviewing the rule- 12.02(e) dismissal of a complaint, “[appellate courts] accept the facts alleged in the complaint as true and construe all reasonable inferences in favor of the nonmoving party”). In December 2012, respondent Minnesota Department of Transportation (MnDOT) released to appellants Waseca County and Steele County (the counties) portions of Old Trunk Highway No. 14 (Old Highway 14) that were located in the counties. The counties initiated separate lawsuits, which were later consolidated, alleging, among other things, that MnDOT was not permitted to “revert [Old Highway 14] to the Counties without an agreement in place at the time of the reversion.”
In January 2014, the counties and MnDOT executed a settlement agreement and release. The settlement agreement requires MnDOT to perform certain work at its expense on several segments of Old Highway 14. As to Waseca County Segments 1, 3, and 5 and Steele County Segment 2 (subject highway segments), which are at issue in this case, MnDOT agreed to “reclaim to aggregate the existing shoulders.”1 And MnDOT agreed that all of its work would “be completed in accordance with applicable Minnesota Statutes, MnDOT Rules, and MnDOT [T]echnical Design Standards.”
1 “[A]ggregate” means “[t]he mineral materials, such as sand or stone, used in making concrete.” The American Heritage Dictionary of the English Language 33 (4th ed. 2006) [hereinafter American Heritage Dictionary].
In April 2015, the counties sued MnDOT, claiming that MnDOT-issued Technical Memorandum No. 12-12-TS-06 (technical memorandum) requires, “at least in part, paved shoulders” for the subject highway segments and alleging that MnDOT ignored the technical memorandum’s design requirements by instructing a third-party design engineer that the shoulders of the subject highway segments should be aggregate. The counties sought a declaratory judgment that the shoulders of the subject highway segments must be paved in accordance with the technical memorandum. MnDOT moved to dismiss the counties’ complaint for failure to state a claim on which relief can be granted. The district court granted MnDOT’s motion.
This appeal follows.
DECISION
“When reviewing a case dismissed pursuant to Minn. R. Civ. P. 12.02(e) for failure to state a claim on which relief can be granted, the question before [an appellate] court is whether the complaint sets forth a legally sufficient claim for relief.” Hebert v. City of Fifty Lakes, 744 N.W.2d 226, 229 (Minn. 2008). “[Appellate courts] review de novo whether a complaint sets forth a legally sufficient claim for relief.” Walsh, 851 N.W.2d at 606. Although “[appellate courts] accept the facts alleged in the complaint as true and construe all reasonable inferences in favor of the nonmoving party,” id., “a legal conclusion in the complaint is not binding on [an appellate court],” Bahr v. Capella Univ., 788 N.W.2d 76, 80 (Minn. 2010).
A pleading must “contain a short and plain statement of the claim showing that the pleader is entitled to relief and a demand for judgment for the relief sought.” Minn. R. Civ.
P. 8.01. “A claim is sufficient against a motion to dismiss for failure to state a claim if it is possible on any evidence which might be produced, consistent with the pleader’s theory, to grant the relief demanded.” Walsh, 851 N.W.2d at 603.
In this case, the district court dismissed the counties’ complaint, concluding that “the plain and unambiguous language of the [settlement agreement] requires only that [MnDOT] reclaim the shoulder of the [subject highway segments] to aggregate.” The counties argue that the district court erred in its interpretation of the settlement agreement because the agreement incorporates MnDOT’s technical design standards and those standards require paved shoulders on the subject highway segments. “In deciding a motion to dismiss, [a] court ‘may consider the entire written contract when the complaint refers to the contract and the contract is central to the claims alleged.’” Baker v. Best Buy Stores, LP, 812 N.W.2d 177, 180 (Minn. App. 2012) (quoting In re Hennepin Cty. 1986 Recycling Bond Litig., 540 N.W.2d 494, 497 (Minn. 1995)), review denied (Minn. Apr. 25, 2012).
A settlement agreement is a contract, and [appellate courts]
review the language of the contract to determine the intent of the parties. When the language is clear and unambiguous, [appellate courts] enforce the agreement of the parties as expressed in the language of the contract. But if the language is ambiguous, parol evidence may be considered to determine intent. Whether a contract is ambiguous is a question of law that [appellate courts] review de novo. The language of a contract is ambiguous if it is susceptible to two or more reasonable interpretations.
Dykes v. Sukup Mfg. Co., 781 N.W.2d 578, 581–82 (Minn. 2010) (citations omitted).
Paragraph 2 of the settlement agreement describes the “Work” or “Project” that MnDOT agreed to complete, at its expense, on several segments of Old Highway 14. As to the subject highway segments, paragraph 2A provides:
MnDOT agrees to complete highway preservation work as follows: mill of up to 4[ inches] (including appropriate patching), and pave a 5[-inch] unbonded concrete overlay with a width of 24[ feet] consistent with MnDOT Rules and Technical Design Specifications (construction means and methods will, at a minimum, satisfy the requirements of MnDOT’s State-Aid Rules), in the above-referenced sections, as shown in attached Exhibit D. MnDOT will reclaim to aggregate the existing shoulders.
(Emphasis added.) Exhibit D to the settlement agreement contains five diagrams of the four subject highway segments; each diagram shows a point at which to “RECLAIM TO AGG SHOULDER.” And the notes to Exhibit D state, “NEW CLASS 2 SHOULDER AGGREGATE BASE WHICH WILL CONSIST OF RECLAIMED BITUMINOUS SHOULDERS TO BE UTILIZED TO BRING NEW SHOULDERS FLUSH WITH NEW CONCRETE SURFACE.”2 Paragraph 9 of the settlement agreement provides that “[a]ll of MnDOT’s Work will be completed in accordance with applicable Minnesota Statutes, MnDOT Rules, and MnDOT [T]echnical Design Standards.” The counties argue that paragraph 2A requires, “at a minimum,” that MnDOT restore the shoulders of the subject highway segments to
2 “[B]ituminous” means “[l]ike or containing bitumen,” which is “[a]ny of various flammable mixtures of hydrocarbons and other substances, occurring naturally or obtained by distillation from coal or petroleum, that are a component of asphalt and tar and are used for surfacing roads and for waterproofing.” American Heritage Dictionary, supra, at 189.
aggregate but that paragraph 9 incorporates the technical memorandum and requires MnDOT to pave the shoulders on the subject highway segments. We are not persuaded.
Free access — add to your briefcase to read the full text and ask questions with AI
Waseca County v. Minnesota Department of Transportation (Waseca County v. Minnesota Department of Transportation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.