Wartsila Finland OY v. Duke Capital LLC

518 F.3d 287, 2008 WL 444561
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 22, 2008
Docket07-20012
StatusPublished
Cited by7 cases

This text of 518 F.3d 287 (Wartsila Finland OY v. Duke Capital LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wartsila Finland OY v. Duke Capital LLC, 518 F.3d 287, 2008 WL 444561 (5th Cir. 2008).

Opinion

EMILIO M. GARZA, Circuit Judge:

Duke Energy International (“DEI”) appeals the district court’s judgment confirming an arbitration award and denying DEI’s request for a stay of enforcement. The district court entered a judgment ordering DEI to pay Wartsila Finland OY and Wartsila Guatemala, SA, (collectively “Wartsila”) $13,677,951.64 plus pre- and post-judgment interest. The district court enforced the arbitrator’s award despite the presence of separate, pending arbitration claims brought by DEI, against Wartsila. For the following reasons, we affirm the judgment of the district court.

I

In 2002, Wartsila contracted with DEI to construct a power plant near Puerto Quetzal, Guatemala. The contract provided for Wartsila to complete construction of the power plant in four phases. Pertinent to this case, the agreement gave DEI certain rights to withhold payment on invoices. Specifically, Sections 6.9 and 6.10 of the contract provide that:

Any amount of an Invoice which is disputed by [DEI] as provided in this section 6 shall be resolved in accordance with Section 21. Once the dispute is resolved in accordance with Section 21, [DEI] shall pay any amount owing within five (5) Business Days after the date of the final resolution.
[DEI] may withhold payment on an invoice or a portion thereof in an amount and to such an extent as may be reasonably necessary, subject to the dispute resolution provisions of Section 21, to protect [DEI] from loss because [of] ... work that has not been remedied.

The agreement also gave DEI certain rights to setoff amounts owed to DEI against amounts DEI owed Wartsila. Specifically, Section 6.13 states:

Notwithstanding any other provision in this Agreement, and in addition to its other rights and remedies, [DEI] shall be entitled to setoff against any amount *290 it owes [Wartsila], or that will become owed to [Wartsila], under this Agreement, any amount that [Wartsila] owes [DEI] under this Agreement.

In Section 21, the contract included an arbitration provision which provided that if disputes could not be resolved by Senior Officers of each party, then the disputes were to be submitted to arbitration held pursuant to International Chamber of Commerce (“ICC”) rules. Section 21 states that “any decision rendered by the arbitrators in any arbitration shall be final and binding upon the Parties, and judgment may be entered on the award in any court of competent jurisdiction.”

In April 2003, prior to completion of phase four of the power plant, Wartsila sought payment for disputed invoices and filed a demand for arbitration with the ICC to resolve disputes that had arisen with respect to the first three phases. The arbitral tribunal conducted a hearing as to these claims in September 2004. In January 2005, the tribunal instructed Wartsila and DEI to raise any further claims and counterclaims to be resolved in the arbitration proceeding. Both parties served memoranda containing their remaining claims for relief related to phase four. In February, DEI requested more time from the tribunal, stating that it needed the time to comprehensively address all of its counterclaims. The tribunal refused the request, but stated that it would allow DEI to withdraw any claims that it felt should be reserved for a later proceeding. A second hearing was held in June 2005 to consider all claims and counterclaims that had not been withdrawn. The tribunal then issued a partial award, reserving its decision on all undecided claims for further partial awards or a final award. Because some construction on the project was still ongoing, the parties asked the tribunal to consider a third set of hearings. The tribunal noted that a third set of hearings may be necessary but did not set a date for those hearings.

In September 2005, the tribunal chairman informed the parties that he had been appointed as a High Court Judge in England and that he would therefore be unable to continue as an arbitrator. Wartsila and DEI disputed whether the tribunal should be reconstituted to consider further claims. The tribunal determined that it would not reconstitute itself for another round of hearings, but instead would issue a final award as to the claims then before it. The tribunal allowed DEI to withdraw certain of its claims according to Article 30(4) of the ICC Rules so that DEI might present the claims in a later arbitration proceeding. 1

In April 2006, the tribunal issued a “Final Award” which dealt with “all remaining claims and counterclaims, including .the remaining claims in Phase III and those arising in Phase IV.” After correcting computational errors in its award, the tribunal ordered DEI to pay Wartsila €11,-315,385 and Wartsila to pay DEI $757,085.

Wartsila sought payment in accordance with the final award. DEI refused to pay, *291 claiming that it was entitled to withhold payment to protect itself from loss due to defective or unfinished work. DEI also contended that it could set off the amounts it sought in its withdrawn claims against the amount ordered to be paid in the tribunal’s final award. In October 2006, DEI made a request to the ICC for arbitration in order to bring the claims withdrawn from the previous arbitration. Three days after DEI made this request, Wartsila filed a motion in federal court to have the tribunal’s award confirmed and enforced under The Convention on the Recognition and Enforcement of Foreign Arbitral Awards (hereinafter “New York Convention”), see 9 U.S.C. § 207 (providing courts with jurisdiction to confirm and enforce arbitration awards arising under the New York Convention). 2 DEI filed a cross-motion for confirmation as well as a stay of the proceedings pending completion of its newly filed arbitration claims. Because neither party objected to confirmation, the district court confirmed the award. The district court then rejected DEI’s arguments for a stay and enforced the award by reducing it to judgment — the judgment required DEI to pay Wartsila $13,677,951.64.

DEI appeals, contending that the district court erred in refusing to stay the entry of judgment. DEI presents two arguments in support of a stay. First DEI argues that the award itself, when properly interpreted, required the district court to stay enforcement of the award. Second, DEI argues in the alternative that, even if the award contemplates immediate enforcement, the district court should have exercised its discretion to stay enforcement of the award.

II

“This court reviews a district court’s confirmation of an arbitration award de novo, using the same standards as the district court.” American Laser Vision, PA. v. Laser Vision Inst., L.L.C., 487 F.3d 255, 258 (5th Cir.2007). As to DEI’s claim seeking a stay of enforcement in spite of the arbitration award, we review the district court’s decision denying a stay for an abuse of discretion. See Sutter Corp. v. P & P Industries, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
518 F.3d 287, 2008 WL 444561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wartsila-finland-oy-v-duke-capital-llc-ca5-2008.