Warshaw v. Pyms

266 So. 2d 355, 1972 Fla. App. LEXIS 6293
CourtDistrict Court of Appeal of Florida
DecidedSeptember 12, 1972
DocketNo. 71-523
StatusPublished
Cited by7 cases

This text of 266 So. 2d 355 (Warshaw v. Pyms) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warshaw v. Pyms, 266 So. 2d 355, 1972 Fla. App. LEXIS 6293 (Fla. Ct. App. 1972).

Opinions

CARROLL, Judge.

The appellant filed an action under the Mechanics’ Lien Law for enforcement of a lien for the value of engineering services alleged to have been performed by him in connection with certain described land owned by appellees, under contract with appellees. By answer the defendants denied the material allegations of the complaint, and averred that the plaintiff had not performed any services in connection with the property; that improvements on the property were not made; that no contract had been entered into between the parties; that the services alleged to have been performed by plaintiff were of no value; and that defendants were not indebted to plaintiff.

Section 713.03 Fla.Stat., F.S.A. entitled: “Liens for professional services,” in subsection (1) provides that an architect, landscape architect, engineer or land surveyor shall have a lien, on real property improved, for money owed him for his services in preparing plans, specifications or drawings used in connection with improving the real property or for services in supervising any portion of the work of im[356]*356proving the real property “rendered in accordance with his contract and with the direct contract” — that is, under a contract with the owner, or under a subcontract.

Subsection (2) of § 713.03, on which the plaintiff is proceeding in this case, is applicable where services are performed incident to certain property but where the intended improvement of the property is not made. Thereunder an engineer has a lien for such services (plans, etc.) for the amount due him therefor, notwithstanding the planned improvement is not made, when the services are rendered under a “direct” contract with the owner, as distinguished from a subcontract.1

Plaintiff moved for partial summary judgment on liability, and defendants moved for summary judgment. The plaintiffs motion was denied. Defendants’ motion was granted. Summary judgment was entered for the defendants, and the plaintiff appealed.

The evidence before the court at the hearing on the motions for summary judgment included an affidavit of the defendant Jack Pyms, a deposition of Mrs. Pyms, an affidavit and the deposition of the plaintiff engineer, a deposition of the owners’ architect Carson Bennett Wright and the written contract of September 30, 1969, between Pyms and the architect. The contract with the architect, in addition to providing for architectural services and for payment therefor, provided for engineering services and for payment thereof by the owner. In that connection Pyms’ contract with the architect contained the following:

“The working drawings prepared by the architect will be inclusive of all required engineering services, however, all engineering services and drawings required and corresponding fees for such services shall be at the direct expense of the owner, exclusive of the above quoted architectural fee.
“As mentioned before, the owner will be required to pay the direct expenses for all engineering services required for the project, however, it is herein agreed that the engineer so retained shall be at the approval of the architect and will perform under his direction in order to control the design of the project.”

In the judgment rendered the court stated :

“1. Defendant Jack Pyms engaged one Carson Bennett Wright to architecturally design a private residence to be constructed on unimproved real property owned by said defendant and his wife, which real property is the subject matter of this litigation.
“2. Following some preliminary services, Pyms and Wright entered into a Letter Agreement dated September 30, 1969, outlining the nature and extent of the architectural services and making provision for payment to the architect of an aggregate sum of Five Thousand Five Hundred ($5,500.00) Dollars. The Agreement further contained verbiage which made it clear that any engineering services were to be exclusive of the architect’s fee and would be paid by the owner to the engineer. Wright told the plaintiff (the engineer) that the plaintiff would have to do his own negotiating with the defendants with respect to his fee and that under Wright’s agreement with Pyms, he, the architect, was not to be responsible for engineering fees. Plaintiff, however, chose not to contact the owners with respect to his fee and instead began to perform the engineering [357]*357work without a direct contract or agreement with the owners as to the amount and manner of payment of his fee.
>}c % ‡»

In granting summary judgment for the defendant the trial court proceeded on three grounds. First upon the expressed conclusion of the court that the plaintiff was not entitled to a lien because he did not have a “direct contract” within the meaning of § 713.03(2), stating: “The phrase ‘direct contract’ connotes a face-to-face personal confrontation of the parties, which was wholly lacking in this case.” That holding of the trial court would deny the effectiveness of an owner’s contract with an engineer made by the owner through an agent (which the appellant contends was done here).

Secondly, the court found there was no evidence of authority of the architect “to bind the defendants to pay the plaintiff any sum whatsoever.” That does not appear to be a finding of absence of evidence that the architect had authority to act as agent for the owner to make a contract between the owner and the engineer for services, but appears to be a finding that the architect was without authority to fix any sum as compensation to be paid therefor. As revealed in the deposition testimony of the architect, he did not purport to do the latter.

Third, the court appeared to reject the theory of implied contract between the engineer and the owner, where the court stated (correctly) that “mere knowledge on the part of the owners that the plaintiff was the person doing the work with reference to their property is not in itself sufficient to establish a ‘direct contract’,” but did not comment on other facts shown, bearing on existence of an implied contract.

The initial question presented by this appeal is whether the trial court was correct in holding that in order for there to be a “direct contract” between an owner and an engineer (for services of the latter in connection with a given parcel of real estate), the contract must be one that is made by them in a “face-to-face personal confrontation of the parties,” as distinguished from a contract between them made through an agent, or a contract implied by law (upon facts sufficient therefor).

We find merit in the contention of the appellant that the trial court ruled incorrectly in holding that a “direct” contract between an owner and an engineer could be made only by “a face-to-face personal confrontation of the parties.”

An owner of real estate can become directly obligated to an engineer, for performance by the latter of services relating to his property, by a contract which is made with the engineer by the owner through an agent, as effectively as if the parties made such contract face-to-face. Citation of authority for that proposition appears unnecessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Christopher B. Burke Engineering, LTD. v. Heritage Bank of Central Illinois
2015 IL App (3d) 140064 (Appellate Court of Illinois, 2015)
Wilger Enterprises, Inc. v. Broadway Vista Partners
2005 NMCA 088 (New Mexico Court of Appeals, 2005)
Cabarrocas v. Resolution Trust Corp.
840 F. Supp. 888 (S.D. Florida, 1993)
Capital Const. Services, Inc. v. Rubinson
541 So. 2d 748 (District Court of Appeal of Florida, 1989)
O'Kon and Co., Inc. v. Riedel
540 So. 2d 836 (District Court of Appeal of Florida, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
266 So. 2d 355, 1972 Fla. App. LEXIS 6293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warshaw-v-pyms-fladistctapp-1972.