WARREN G. KLEBAN ENGINEERING CORPORATION v. Caldwell

361 F. Supp. 805, 1973 U.S. Dist. LEXIS 12989
CourtDistrict Court, N.D. Mississippi
DecidedJune 26, 1973
DocketWC 70-71-K
StatusPublished

This text of 361 F. Supp. 805 (WARREN G. KLEBAN ENGINEERING CORPORATION v. Caldwell) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WARREN G. KLEBAN ENGINEERING CORPORATION v. Caldwell, 361 F. Supp. 805, 1973 U.S. Dist. LEXIS 12989 (N.D. Miss. 1973).

Opinion

MEMORANDUM OPINION

KEADY, Chief Judge.

In this case, the Pontotoc County Board of Education and its superintendent (Board) are sued by Warren G. Kleban Engineering Corporation (Kleban) of Starkville, Mississippi, for losses allegedly arising from its failure to obtain the mechanical engineering work on a contract awarded by the Board to Lee Watson and Sons (Watson), general contractors of Hamilton, Mississippi, to construct two Pontotoc County 12-grade schools, one located at Ecru and the oth *807 er at Springville. 1 Watson, the general contractor, was originally joined as a co-defendant. On February 22, 1971, Den-ton Roberts, d/b/a Roberts Electrical Company (Roberts) of Aberdeen, with leave of court, intervened to assert a claim against the Board and Watson for being denied an opportunity to perform the electrical work under Watson’s contract. By its answers, the Board denied any contractual relation with either Kleban or Roberts and asserted that its dealings were exclusively with Watson as general contractor. Watson answered, also denying liability and asserting that although Kleban did submit the low bid for mechanical engineering, that firm was not awarded the subcontract because Kleban was not acceptable to the Board; Watson denied liability to Roberts on the gound that although it had solicited a bid for the electrical work from Roberts after Hankins, the original low bidder, was found unqualified, it had the right, once Kleban was rejected as mechanical engineering subcontractor, to substitute still another subcontractor, Central Electrical and Machinery Company (Central) of Tupelo, who submitted a lower and combination bid for both mechanical engineering and electrical work.

The court on August 4, 1971, entered a pre-trial order agreed to by all parties looking to the trial of the case in November 1971. Because of valid reasons, several continuances were granted by the court, thus delaying trial. Watson in March 1972 moved for summary judgment and shortly thereafter the court was presented an order dismissing Watson with prejudice, and the consent order was entered pursuant to stipulation approved by counsel for Kleban and Roberts.

Full evidentiary trial was conducted March 14, 1973. After the parties submitted proposed findings of fact and memorandum briefs, the court, having been presented with post-trial evidentiary materials in conflict with the previous pre-trial order, reopened the case and received further evidence May 30, 1973.

Since the commencement of this litigation, the two 12-grade schools, scheduled for completion August 1, 1971, have been constructed and placed into active use by the Board. Injunctive relief first sought has been abandoned but Kleban seeks a recovery for loss of profits ($57,000) on the project, estimate expenses in bidding ($4,800), and substantial damages both compensatory and actual, for injury to its business reputation ; and Roberts seeks the recovery for loss of profits ($21,640) for not being the electrical subcontractor.

The Board hired William I. Rosamond and Associates (Rosamond), a well-known architectural firm of Columbus, to prepare plans and specifications on the two-schools project. On the basis of detailed plans and specifications, the Board invited sealed bids .by contractors to be opened and publicly read September 29, 1970, at 2 o’clock, p. m., in the Board’s office at the City of Pontotoc. Bidders were solicited to ‘bid for general construction, including plumbing construction, mechanical construction, electrical construction, and site improvements for two 12-grade schools, Project ‘A’ and Project ‘B’.” The bid invita *808 tion specifically recited that the proposed work would be awarded either as one lump-sum contract covering both schools or as two separate one-lump-sum contracts for each school. The Board reserved the right to reject all bids, also advising bidders “that any person, firm or other party to whom it is proposed to award a subcontract must be acceptable to the owner and the architect.” The form of bid proposal supplied by the Board’s architect provided that bidders should complete a separate form headed “Data on Specialty Items”, in which the bidder was instructed to list a breakdown of his general bid, together with the names, if any, of the subcontractors. 2 The bidder was advised that the amounts of any such subcontracts should not include any general contractor’s overhead and profit and that a separate sheet on these specialty items should be properly filled out and submitted with the bidder’s bid but in a sealed envelope separate from the envelope containing the general bid. Watson did not submit a bid for each of the schools (Projects A and B), but only a lump-sum proposal to construct both schools. 3 Watson testified that in preparing his firm’s bid he relied upon a mechanical engineering proposal of $347,500 submitted by a Mr. Lundy although he had also received from Kleban a higher proposal of $350,000, and for electrical construction upon a $152,000 proposal from Hankins Electric Company. Only several minutes before its bids were actually delivered, however, Watson conferred with Kleban, who reduced its mechanical proposal to $347,000; Watson then hurriedly filled out the specialty data sheet naming Kleban as the successful mechanical engineering contractor for $350,000 4 and Hankins as the successful electrical contractor for $152,000. The Board opened the various general contractor bids but no award was immediately made since all bids exceeded available funds. The sealed envelopes containing the data on specialty items, including those submitted by Watson, were not opened by the Board but were confidentially retained by Rosamond and later opened at his Columbus office. The next day, Rosamond contacted Watson and proceeded to negotiate a contract with that firm, by taking alternate deductions and issuing certain change-orders. Hankins, the low bidder for the electrical work, was determined to be unqualified, not having a certificate of responsibility, and Watson, with Rosamond’s concurrence, negotiated with Roberts, who submitted a bid of $165,915.87. Further negotiations for the mechanical engineering took place between Watson and Kleban, with Rosamond’s approval, and resulted in a new proposal by Kleban for $330,000. On October 23, Watson submitted Kleban and Roberts to Rosamond, the Board, and the State Educational Finance Commission for approval as the proposed mechanical engineering and electrical subcontractors. The Board, on October 28, acting through its Superintendent Richard C. Ball, disapproved Kleban as mechanical subcontractor without assigning reasons but relying upon references contained in the specifications. No mention of Roberts was made.

*809 Watson was notified to submit an alternate mechanical subcontractor for the Board’s approval. Watson subsequently submitted Central as the combined mechanical engineering and electrical subcontractor, and this firm was approved by the Board and Rosamond. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker Bros. v. Crawford
68 So. 2d 281 (Mississippi Supreme Court, 1953)
Southern California Acoustics Co. v. C. V. Holder, Inc.
456 P.2d 975 (California Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
361 F. Supp. 805, 1973 U.S. Dist. LEXIS 12989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warren-g-kleban-engineering-corporation-v-caldwell-msnd-1973.