Warnard Constructors, Inc. v. Narragansett Brewing Co.

18 A.2d 390, 66 R.I. 182, 1941 R.I. LEXIS 22
CourtSupreme Court of Rhode Island
DecidedFebruary 24, 1941
StatusPublished

This text of 18 A.2d 390 (Warnard Constructors, Inc. v. Narragansett Brewing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warnard Constructors, Inc. v. Narragansett Brewing Co., 18 A.2d 390, 66 R.I. 182, 1941 R.I. LEXIS 22 (R.I. 1941).

Opinion

Capotosto, J.

This action in contract was heard by a justice of the superior court, sitting without a jury, who gave a decision for the plaintiff in the sum of $1158.07, which, with interest from the date of the writ, May 24, 1939, mounted to $1227.55. The case is before us on defendant’s bill of exceptions under which it presses two exceptions: First, to the denial of its request to file a plea of set-off during the course of the trial; and second, to the decision for the plaintiff in the amount above stated.

Omitting all incidental issues concerning a commission for adjusting loss covered by insurance and compensation for *183 extra work, which were not proved by the plaintiff or admitted by the defendant, the principal question in this case is the application of an overpayment on one contract in the total amount of $697.24, which the defendant claims should have been credited on another contract between the parties.

On September 21, 1938, a hurricane did great damage to many buildings in this state, creating a situation of emergency. By an undated contract in writing, which was admittedly entered into on or about October 13, 1938, the plaintiff agreed to repair and paint, where necessary, the roofs, skylights, doors and windows, including the replacing of all broken glass, on twelve buildings of the defendant damaged by the hurricane, on the basis of cost plus 10% for overhead, plus 10% for profit, the entire cost not to exceed $3000. This contract is referred to as the “hurricane contract” in the evidence and we will so identify it hereafter. Payments under this contract were to be made on invoices submitted directly by the plaintiff to the defendant. The plaintiff began work under this contract the day following its execution.

While work was going on under the hurricane contract, the parties, on October 27, 1938, entered into another written contract by which the plaintiff agreed to build a concrete floor in the defendant’s brewhouse for $3500. This contract is identified by the parties in the testimony as the “brewhouse contract”, and we shall continue to so identify it in this opinion. Payments under this contract were to be made on requisitions signed by the defendant’s architect. The parties agreed that two payments were made on this contract, one on December 3, 1938 for $1000; and the other on December 17, 1938 for $1500.

The plaintiff claims that the defendant still owes $1000 on the brewhouse contract, and this sum, added to admittedly proper allowances for extras in the amount of $158.07 on the hurricane contract, represents the $1158.07 of the trial justice’s decision. The'defendant, on the other hand, *184 claims that by mistake it paid $697.24 over and above the $3000 that the plaintiff should have received under the hurricane contract; and that in the circumstances it is entitled to credit this sum on whatever amount is due to the plaintiff under the brewhouse contract and for extras.

According to a statement dated January 24, 1939, sent by the defendant to the plaintiff before the instant action was commenced, in which statement the payments on the two contracts are combined without specifying on which contract the payments therein mentioned apply, the defendant strikes a balance due from it to the plaintiff of $433.58. This statement was accompanied by defendant’s check of January 25, 1939 for that amount, such check bearing on its face the notation: “In full payment to date.” The plaintiff did not cash this' check and later returned it to the defendant.

The plaintiff contends that the defendant has no right to treat the two contracts as practically one transaction; that the payments on each contract should be applied to the specific contract on which they were made; and that the alleged overpayment of $697.24 on the hurricane contract, which the defendant now seeks to apply to the brewhouse contract on the ground of mistake, was in fact a voluntary payment by the defendant of that amount on the hurricane contract in the course of negotiations for a modification of that contract. The conflicting contentions of the parties require a review of the testimony on this point. Unless otherwise indicated, all dates hereafter mentioned refer to the year 1938.

It appears in evidence that the cost of performance of the hurricane contract did, in fact, greatly exceed $3000, and that the defendant paid the plaintiff $697.24 in excess of the $3000 limit of that contract. The first three of plaintiff’s invoices, in the total amount of $2347.20, were duly paid by the defendant. It is important to keep in mind the last one of these three invoices in the sum of $792.92, dated November 5, and paid by defendant’s check of November 10, *185 as it is the basis for the defendant’s claim of over-payment by mistake of the sum of $697.24 on the hurricane contract.

The testimony as to how the account under this contract was carried in the defendant’s system of bookkeeping is very indefinite. Confining our attention for the present to the above-mentioned invoice of November 5, we find that the plaintiff’s invoice contains a detailed statement of the items that make up the invoice. Excepting in one instance, there is a check-mark opposite each item, the exception being a cross opposite and a correction of the amount of one item. At the bottom of the page, in a bold hand, are the figures “1.86 — #195”. These figures, check-marks and cross are all in red pencil.

After checking such invoice, the defendant apparently filled in a bill form of its own with such information from the invoice as it deemed necessary. Under the printed heading “Distribution” on this form, we find the typewritten figures “1.86 — #195”, the same as those that appear in red pencil on the invoice. There is no explanation in the testimony of the meaning of these figures. In the lower left-hand corner of the defendant’s form and under the printed words “Approved for Payment” are the initials “A. MeC.” and “H 3rd.”, written in ink and in different handwriting above the word “Treasurer” in each instance. This form and the invoice are firmly fastened together with staples.

The defendant’s check of November 10, in payment of this invoice, was signed by “Arthur McCartney — Assistant Treasurer” and “Countersigned — E. Haffenreffer 3rd — Treasurer.” The handwriting and the initials of these names are the same as the handwriting and the initials on the defendant’s form approving payment of that invoice. This check, which according to the perforations thereon was paid November 15, is also firmly attached with a staple to the defendant’s form and invoice.

*186 It is clear to us from our examination of the above-mentioned instruments that the defendant carefully checked the plaintiff’s invoice before payment; that it made an independent record of its own of such invoice for bookkeeping purposes; that such record, with the invoice firmly attached thereto, was submitted for approval to the defendant’s treasurer and assistant treasurer before any check was issued; and that the defendant had occasion and did refer to such form and invoice when it attached the cancelled check thereto on its return after payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
18 A.2d 390, 66 R.I. 182, 1941 R.I. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warnard-constructors-inc-v-narragansett-brewing-co-ri-1941.