Wapping Community Church v. Kelly, No. Cv 02 0079428 S (Oct. 11, 2002)

2002 Conn. Super. Ct. 12832
CourtConnecticut Superior Court
DecidedOctober 11, 2002
DocketNo. CV 02 0079428 S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 12832 (Wapping Community Church v. Kelly, No. Cv 02 0079428 S (Oct. 11, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wapping Community Church v. Kelly, No. Cv 02 0079428 S (Oct. 11, 2002), 2002 Conn. Super. Ct. 12832 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The following decision was originally entered orally on the record on September 23, 2002. At that time, all counsel were present. A signed copy of the transcript is in the Court file. This Memorandum of Decision contains edits and citations which have been added.

Findings

The Court makes the following findings concerning this case:

The primary defendant is the Connecticut Light and Power Company, since it is the primary constructor and service provider for this project. The court has already granted a Motion to Dismiss filed by the defendant Northeast Utilities Service Company.

The plaintiff commenced this appeal from a decision of the Department of Public Utility Control (DPUC) by filing a request for an ex parte stay of the DPUC orders. The DPUC orders allowed the defendant, Connecticut Light and Power Company (CLP), to upgrade pole lines on the west side of Peterson Way, in South Windsor, to install taller poles and transmission lines for twenty-three KV circuits.

The land on the west side of Peterson Way is owned by the town of South Windsor, (the town hall and library property) in part, and in part by the plaintiff Wapping Community Church, Incorporated. The road is a public street maintained by the town of South Windsor.

The DPUC, at the administrative hearing level, denied CLP's motion to dismiss regarding the individual property owners on the east side of Peterson Way. The DPUC granted those property owners status as adjoining proprietors. That action required CLP to either receive consent from the homeowners to complete the project or, in the alternative, the DPUC must decide, after a hearing, if the project should continue, and if so, in CT Page 12833 what manner.

The plaintiffs, asked the DPUC for a permanent injunction. This meant that the DPUC had to examine the project and alternatives presented as if they were being asked to consider the feasibility of the entire project. The DPUC undertook that responsibility.

The plaintiff Wapping Community Church requested and was granted intervening party status on May 13th 2002.

The primary purpose of the project is to provide reliable electrical service to customers in the town of Manchester. The service, however, runs through the town of South Windsor.

The existing poles along Peterson Way will be removed and replaced by taller poles. Tree trimming will be required. The purpose of the taller poles is to comply with current standards of the National Electric Safety Code.

CLP received permission to trim and remove trees from the town of South Windsor, on a portion of the west side of Peterson Way. CLP also originally received permission from the Wapping Church to trim and remove trees. This was before the church intervened as a party to the action. The Church now opposes the project, according to the findings of the DPUC.

The town of South Windsor not only supports the proposed construction, the town strenuously opposes any alternative that would run the new wires and poles along Sullivan Avenue from Route 74 south to Oakland and Buckland Roads.

The plaintiffs appealed from the proposed draft decision of the DPUC. The plaintiffs amended their appeal and their petition on September 23, 2002, to serve as an appeal from the DPUC's final decision dated August 28, 2002.

The defendant CLP stipulated at the DPUC hearing and again at the court hearing that if the plaintiffs are ultimately successful in their appeal, CLP will restore the poles and wires on Peterson Way to their present condition.

Issue

The decisive question at this hearing is a limited one. That question is whether this Court should dissolve the ex parte stay granted by Judge CT Page 12834 Sullivan on August 27, 2002 which stayed the DPUC's proposed orders, (which later became the final orders of the DPUC). The effect of granting the stay would be to halt the construction until the appeal is decided or some other court takes action.

Law

"The principal purpose of a temporary injunction is to preserve the status quo until the rights of the parties can be finally determined after a hearing on the merits." Rustici v. Malloy, 60 Conn. App. 47, 56,758 A.2d 424, cert. denied, 254 Conn. 952, 762 A.2d 903 (2000). "The issuance of an injunction is the exercise of an extraordinary power which rests within the sound discretion of the court." (Internal quotation marks omitted.) Silitschanu v. Groesbeck, 208 Conn. 312. 318, 543 A.2d 737 (1988).

The party seeking an injunction or a stay must prove irreparable harm and that they have no adequate remedy at law. "A party seeking injunctive relief has the burden of alleging and proving irreparable harm and lack of an adequate remedy at law . . ." Tighe v. Town of Berlin, 259 Conn. 83,86 (2002). The plaintiff has the burden of proving that there is a substantial probability that irreparable harm will occur. "Although an absolute certainty is not required, it must appear that there is a substantial probability that but for the issuance of the injunction, the party seeking it will suffer irreparable harm." Id. At 87.

Our Supreme Court requires a trial judge to use the balancing of theequities test to determine if a stay should be granted pending an appeal from an administrative agency. The balancing of the equities test is defined as "a test which weighs the equities and balances the harm that may be suffered by the [a]ppellant as a result of the enforcement of the [algency order, or the decision, pending the appeal, against the public harm that may result from the delaying the effectiveness of the [o]rder or [d]ecision." Griffin Hospital v. Commission on Hospitals, 196 Conn. 451,455 (1985).

The trial court must consider the following: "[T]he likelihood the appellant will prevail [on the appeal] . . . the irreparability of the injury to be suffered from immediate implementation of the agency order . . . the effect of the stay upon other parties to the proceeding . . . and the public interest involved." Id. at 456.

[Note: The following was inadvertently left out of the oral opinion entered on the record. The Court includes it in this decision, because these issues were raised by the plaintiffs.] CT Page 12835

As grounds for appeal, the plaintiffs allege that the "administrative findings, inferences, conclusions and decisions as set forth in the [draft] DPUC decision are: (a) in violation of the Petitioners' constitutional and statutory rights; (b) in excess of the statutory authority of the DPUC; (c) made upon unlawful procedure; (d) arbitrary and capricious and . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Griffin Hospital v. Commission on Hospitals & Health Care
493 A.2d 229 (Supreme Court of Connecticut, 1985)
Griffin Hospital v. Commission on Hospitals & Health Care
512 A.2d 199 (Supreme Court of Connecticut, 1986)
Silitschanu v. Groesbeck
543 A.2d 737 (Supreme Court of Connecticut, 1988)
Pet v. Department of Health Services
638 A.2d 6 (Supreme Court of Connecticut, 1994)
State v. Marquis
668 A.2d 710 (Supreme Court of Connecticut, 1995)
Tighe v. Town of Berlin
788 A.2d 40 (Supreme Court of Connecticut, 2002)
Rustici v. Malloy
758 A.2d 424 (Connecticut Appellate Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 12832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wapping-community-church-v-kelly-no-cv-02-0079428-s-oct-11-2002-connsuperct-2002.