Wannacomet Water Co. v. Department of Public Utilities

194 N.E.2d 109, 346 Mass. 453, 1963 Mass. LEXIS 630
CourtMassachusetts Supreme Judicial Court
DecidedNovember 20, 1963
StatusPublished
Cited by15 cases

This text of 194 N.E.2d 109 (Wannacomet Water Co. v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wannacomet Water Co. v. Department of Public Utilities, 194 N.E.2d 109, 346 Mass. 453, 1963 Mass. LEXIS 630 (Mass. 1963).

Opinion

Cutter, J.

Wannacomet Water Company (see St. 1880, c. 27; St. 1908, c. 548; St. 1928, c. 197) serves over 1,800 customers in Nantucket, of whom about 600 are seasonal. Its common stock is owned by Greenwich Water System, Inc.

Wannacomet filed new rate schedules to become effective July 1, 1961. The Department of Public Utilities suspended their operation and initiated an investigation as to their propriety. After hearings in April and May, 1961, interim rates were put into effect to afford Wannacomet some relief, pending experience with the use of recently installed meters. Wannacomet introduced further evidence at resumed hearings in 1962.

On June 29, 1962, the department disallowed the rate schedule. The department stated that Wannacomet’s depreciation reserve was inadequate by $76,000 and directed the transfer of this amount from earned surplus, thereby reducing Wannacomet’s rate base. The department also found “that a rate of return of 6.5 per cent will be adequate” to meet expenses and interest charges, and to provide a return “calculated to allow ... in excess of 8 per [455]*455cent on the equity portion of the rate base.” Wannacomet had sought a higher return. The department’s order was designed to produce net operating income of $45,185 rather than of $55,932, as sought by Wannacomet.

Wannacomet appealed (G. L. c. 25, § 5, as amended through St. 1956, c. 190), among other matters, objecting on the grounds of alleged confiscation and lack of substantial supporting evidence to the 6.5% rate of return allowed, as well as to the downward adjustment of rate base because of the increase in the depreciation reserve. The town appealed principally on the ground that the investment by Wannacomet in installing meters was imprudent to the extent of $117,000. The single justice, at the request of the parties, reserved the appeals upon a consolidated record for the determination of the full court.

The Town’s Appeal.

In 1958, the department ordered Wannacomet to install meters for not less than seven per cent of its customers each year. Wannacomet, with the department’s prior informal approval, decided (for reasons of economy as well as of public relations and because costs were constantly rising) to do this work at once, rather than over several years. The installation was completed in the summer of 1961, for $184,764,2 and was paid for by short term borrowing, without interest, from a parent company.

The town contends that the meters were placed in concrete vaults under the public way or sidewalk area at an unnecessary installation cost of $73 each, instead of a cost of about $8 each for installation inside the houses served. On this issue, the department’s decision points out that installation of the “meters outside of buildings was made after careful consideration of the particular problems” on the island; that the program represented a “considered judgment by men of long experience ’ ’; and that, although [456]*456“inside installation in some instances would have been feasible,” in the light of “the high proportion of seasonal” customers and houses “without basements, the record does not disclose that these instances are substantial.” The department concluded “that the long run advantages of efficiency of meter reading and of safety of the meter . . . will outweigh . . . [the] added investment cost.”

Wannacomet’s president gave testimony about the considerations that led to the outside meter installations. In Nantucket there are numerous seasonal customers. In houses closed during the winter, water left in an inside meter will freeze and break the meter chamber. To protect such a meter, it is necessary to take the meter out and blow out the water. Wannacomet is unwilling to leave this work to the owner’s plumber, because it wishes to take care of its own property. Leakage from a frozen meter is less likely to cause damage if the meter is outside the house rather than inside. Sixty-five per cent of Nantucket houses have no basements. In such houses, in order to obtain a fair measurement, the meter must be installed at a point outside the first take-off of the main service line. The meter must be at an accessible point where it can be read. Outside meters can be read more rapidly and inexpensively than those installed inside buildings.

Even if total or partial inside installation of meters would have been practicable and cheaper than outside meters, the department could properly conclude that many such installations would be inconvenient to customers and to Wan-nacomet alike. Customers with no cellars could well regard the presence of a meter in their living quarters as unsuitable. The department could give weight to the difficulties which Wannacomet might encounter in reading inside meters, particularly in the closed houses of seasonal customers. Eemoval and blowing out of these meters would have involved some recurrent annual expense and nuisance to all concerned. The company reasonably was reluctant to entrust protection of its meters to its customers’ plumbers. Cheaper cellar installations of inside meters would have been possible only in those houses with cellars. The [457]*457department was warranted in relying upon the experience and judgment of Wannacomet’s management. We assume that the department would not have been bound to follow Wannacomet’s decision if that decision had been shown to be plainly unreasonable. See New England Tel. & Tel. Co. v. Department of Pub. Util. 327 Mass. 81, 90-92. See also New England Tel. & Tel. Co. v. Department of Pub. Util. 262 Mass. 137,146. The company seems to have proceeded cautiously and after consultation with the department and its own counsel. Substantial testimony justified the department’s conclusion.

Wannacomet’s Appeal.

The department correctly granted two of Wannacomet’s requests for rulings; viz. that it “is entitled to a fair return on its net investment in property used or useful ... to provide . . . adequate water service”; and that a “fair return is one . . . sufficient to insure confidence in the financial soundness of the utility, adequate to maintain ... its credit, sufficient to enable it to attract the capital required to meet its public obligations, and commensurate with that generally being earned on investments in business undertakings attended by corresponding risks.” See New England Tel. & Tel. Co. v. Department of Pub. Util. 331 Mass. 604, 617; Federal Power Commn. v. Hope Natural Gas Co. 320 U. S. 591, 603. We must examine whether the department’s decision on rate of return and rate base involves confiscation of Wannacomet’s property and whether there is substantial evidence to support the department’s conclusion that the rate base should not include the $76,000 to be transferred from earned surplus to the depreciation reserve.3

[458]*458The Rate Base as Affected by the Depreciation Reserve.

From 1915 through 1921, Wannaeomet, like certain other companies, provided for depreciation by charging income and making annual deductions from the plant account on the asset side of the balance sheet. Depreciation of $26,630 was thus accumulated. By St. 1921, c. 268, § 1 (now G. L. [Ter. Ed.] c. 155, § 5A), the department was given authority, when approving a rate schedule or security or debt issue proposed by a utility to ‘ ‘

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sturbridge Isle Realty Corp. v. Brown
13 Mass. L. Rptr. 607 (Massachusetts Superior Court, 2001)
Town of Hingham v. Department of Telecommunications & Energy
433 Mass. 198 (Massachusetts Supreme Judicial Court, 2001)
Massachusetts Electric Co. v. Department of Public Utilities
381 N.E.2d 325 (Massachusetts Supreme Judicial Court, 1978)
Boston Edison Co. v. Department of Public Utilities
375 N.E.2d 305 (Massachusetts Supreme Judicial Court, 1978)
Fitchburg Gas & Electric Light Co. v. Department of Public Utilities
359 N.E.2d 1294 (Massachusetts Supreme Judicial Court, 1977)
Boston Gas Co. v. Department of Public Utilities
324 N.E.2d 372 (Massachusetts Supreme Judicial Court, 1975)
New England Telephone & Telegraph Co. v. Department of Public Utilities
275 N.E.2d 493 (Massachusetts Supreme Judicial Court, 1971)
Mystic Valley Gas Co. v. Department of Public Utilities
269 N.E.2d 233 (Massachusetts Supreme Judicial Court, 1971)
Town of Westborough v. Department of Public Utilities
267 N.E.2d 110 (Massachusetts Supreme Judicial Court, 1971)
G & M Employment Service, Inc. v. Commonwealth
265 N.E.2d 476 (Massachusetts Supreme Judicial Court, 1970)
Metropolitan District Commission v. Department of Public Utilities
224 N.E.2d 502 (Massachusetts Supreme Judicial Court, 1967)
Strong v. Massachusetts Commission Against Discrimination
222 N.E.2d 885 (Massachusetts Supreme Judicial Court, 1967)
New York Central Railroad v. Department of Public Utilities
199 N.E.2d 319 (Massachusetts Supreme Judicial Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
194 N.E.2d 109, 346 Mass. 453, 1963 Mass. LEXIS 630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wannacomet-water-co-v-department-of-public-utilities-mass-1963.