Walton v. Smulcer

222 S.W.2d 918, 1949 Tex. App. LEXIS 2071
CourtCourt of Appeals of Texas
DecidedJune 24, 1949
DocketNo. 15057
StatusPublished
Cited by3 cases

This text of 222 S.W.2d 918 (Walton v. Smulcer) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walton v. Smulcer, 222 S.W.2d 918, 1949 Tex. App. LEXIS 2071 (Tex. Ct. App. 1949).

Opinion

HALL, Justice.

Appellees, Howard and Jimmy Smulcer, •oil .well drilling contractors, sued appellant, S. H. Walton, in a district court of Wichita •County, Texas for the amount alleged due ■them for drilling appellant an oil well 2127 feet at $1.75 per.foot, based upon an oral contract. •

Appellant answered' by way ■ of general ■denial and cross action. He admits in his answer that the contract ^ plead and proved by appellees was substantially Correct, and plead the following: “ * - * * that they were to drill such well with due and reasonable diligence, using that degree of care which an ordinary drilling contractor in this locality would use in drilling the well, in setting the casing, in testing the casing, and in- cementing; that such well in the event- that a formation was discovered at the depth of approximately 2100 feet was to have casing set therein,' and that after the setting of casing, the Plaintiffs were to pump into the casing cement, or to cement thf well and the casing, 'and were to cement the well leaving the cement in the casing and in the hole to a depth of 20 feet from the bottom of the hole * * * ”

By way of cross action appellant sought damagés against - appellees in the sum of $2,656.81, alleged due him because appellees Jailed (1) to' set the casing firmly in the hole; (2) to spud or jog the casing; (3) in working the men overtime which prevented them from properly performing their duties in an efficient manner; (4) to use a test plug so as to test the casing to see whether or not the joints had become loose; (5) in leaving 577 feet of cement in the hole so as to prevent proper testing of the sands in the well below 1,600 feet; (6) to use any circulating pump; -and (7) to apply sufficient pressure on the pump which would force the cement down to a depth of within 20 feet of the bottom of 'the hole.

The case was tried to a jury, which answered the court’s submitted -special issues in favor of appellees. Judgment was rendered accordingly for the sum of $3,722.25, full amount appellees sued for.

Appellant submits this appeal assigning five'-points of error. Points 1 and 2 relate to' error of the court an permitting proof of custom and practice without any pleading of such custom and practice and without pleading that appellant, - who is not a drilling contractor, knew of such custom and practice, or had any knowledge of such custom and practice. Points 3, 4 and 5 are as follows:

. “3. The Qo-urt erred in submitting Special Issue Number One of the Court’s charge, inquiring'as to whether the Plaintiffs, Ploward Smulcer and Jimmie A. Smulcer, fully complied with the terms of their agreement with defendant, S. H. Walton, in the drilling of the well in question.”
“4. The Court erred in submitting to the jury its Special Issue Number Three, inquiring as to whether'the defendant, S. H. Walton, ' agreed with the plaintiffs, Ploward Smulcer and Jimmie A. Smulcer, that, on completing said well to a -depth of 2127 feet, the defendant, S. H. Walton, would have an independent cementing contractor -cement said well.”
“5. The Court erred in the submission of its Special Issue Number Six, inquiring as to whether the cementing contractor was solely responsible for the cementing of the well involved in this suit.”

The jury’s answers'to special issues involved in this appeal a-re substantially as follows: .

[920]*9201. That appellees fully complied with the terms-of their agreement with appellant.
2. Agreement 'between the parties was that the well should be drilled to a depth of 2127 feet.
3. Appellant agreed with appellees that on completion of said well appellant would have an independent cementing contractor to cement said well.
4. That appellees did not agree to assume responsibility for the cementing of said well.
5. But they did agree to furnish part of the labor in the cementing of said well.
6. The cementing contractor was solely responsible for the cementing of said well.
7. The parties did not agree appellees would complete the well by leaving approximately 20 feet of cement at the bottom of the casing in the well in question.
8. That appellees did not leave more than approximately 20 feet of cement in the casing in the well in question.

In discussing points 1 and 2 we find ap-pellees’ pleading with reference to custom is as follows:

“Defendant further agreed to pay plaintiffs the ¡sum of $1.75 per foot for the total depth to which said well was drilled and to compensate plaintiffs at the rate of $10.00 for each core head taken, and to compensate plaintiffs for Schlumberger time at the rate of $12.50 per hour, all shutdown time consumed to be paid at the rate of $12.50 per hour, plaintiffs agreeing to allow defendant a reasonable time within which to examiner electric log prior to the time of setting casing, the reasonable time so allowed to be at the expense of plaintiffs,
“That plaintiffs exercised -reasonable diligence and performed said contract in a careful and prudent manner and in conformity with the prevailing custom, usage, and practice of drilling contractors in .the immediate area of the drilling of said well.”

In connection therewith appellees specifically plead the following:

'* * * That after said well had been so drilled with said rotary drilling rig to the depth desired by the defendant, plaintiffs were to set in said hole casing to be selected by and furnished at the expense of defendant, and after said casing wa-s so set in said well, plaintiffs were to furnish a part of the labor to the cement contractor selected by the defendant to enable the cement the well, at which time plaintiffs’1 contract with defendant was to be considered completely performed.”

We have read the testimony of appellant. He did not testify, in substance, that his contract with appellees included pushing the cement down with sufficient force by their pressure pump so that all of it would be on the outside of the casing except 20 feet at -the bottom of the hole, -but his testimony along such line relates to the conversations he had with appellees at the -time the cementing was taking place. His testimony pertaining to the contract is as follows :

“Q. * * *. I asked you if you and Mr. Smulcer and J. B. Price were present in the White Rose Cafe at Electra and made this contract, the provisions of — all-—all the provisions of this contract? A. There wasn’t no — there wasn’t any provisions on it; just like the other wells was, and they' moved out there on it.
“Q. Who was present when you did make a contract? A. Price and this, Smulcer and myself.
- “Q. All sitting in the White Rose Cafe ? A: At the White Rose Cafe.
“Q. At Electra? A. Yes, sir.
“Q. You did not make the contract with Mr. Price; you made the contract with Mr. Smulcer? A. I talked to Price out on the highway several days -. before and told him what I’d do; give him my note for six months to go' over there and drill this well to 2100 feet.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. Turner
472 S.W.2d 831 (Court of Appeals of Texas, 1971)
Minneapolis-Moline Company v. Purser
361 S.W.2d 239 (Court of Appeals of Texas, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
222 S.W.2d 918, 1949 Tex. App. LEXIS 2071, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walton-v-smulcer-texapp-1949.