Walton Brick Co. v. Anderson Foundry & Machine Works

134 S.W. 136, 142 Ky. 274, 1911 Ky. LEXIS 153
CourtCourt of Appeals of Kentucky
DecidedFebruary 15, 1911
StatusPublished
Cited by2 cases

This text of 134 S.W. 136 (Walton Brick Co. v. Anderson Foundry & Machine Works) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walton Brick Co. v. Anderson Foundry & Machine Works, 134 S.W. 136, 142 Ky. 274, 1911 Ky. LEXIS 153 (Ky. Ct. App. 1911).

Opinion

Opinion of the Court by

Wm. Rogers Clay, Commissioner

Affirming.

Appellee. Anderson Foundry & Machine Works, on February 24th, 1908, sold to appellant, Walton Brick Company, certain machinery for making brick. For this machinery the Walton Brick Company agreed to pay $4,063.50. Of this sum $2,133.50 was to he paid upon the arrival of the machinery at Walton, Kentucky, and the balance when said machinery was in proper working order and making at the rate of 2,000 perfectly formed brick per hour. The machinery arrived at Walton in March, 1908. Thereupon appellant paid to appellee $2,031.75. On June 29, 1908, after the machinery had been installed and had been making brick for several weeks, it paid the additional sum of $1,000. The balance, 1,031.75, was not paid, and appellee brought this action against appellant for the purpose of enforcing a mechanic and materialman’s lien. During the trial it was admitted that appellant, at the request of appellee, had furnished certain small articles of the value of $68.20. Upon final submission of the case, the chancellor gave judgment in favor of appellee for the sum of $1,031.75, subject to a credit of $68.20, and also adjudged appellee a lien upon certain real property, ma[275]*275chinery, etc., constituting the brick manufacturing plant owned by appellant. From that judgment this appeal is prosecuted.

Briefly stated, the facts are as follows: About ten days before the contract of purchase was entered into, appellee submitted to appellant a proposition, in writing, hy which it agreed to furnish certain machinery designated therein. This proposition contained certain guaranties. Those that are material to this case are as follows :

“Our proposition also contemplates that in event you favor us with order that we will send a competent engineer to your plant free of cost to yourself, who will make a lay-out for your buildings, show you what changes are necessary in order to install the above named machinery, and he will then make a detailed drawing and furnish you with blue prints so that any carpenter or millwright can install the machinery such as we would send you, and when you are ready to operate same we will also agree to furnish you a first-class man both as an engineer and as a brickmaker for the starting up of your plant to see that the machinery fulfills the guarantee that we will give with same, however, the expense of the man sent will be $5 per day and his car fare to and from Anderson, and wish to state you can use him as few or as many as you desire.

“Our guarantee contemplates that if for any reason the machinery furnished should not do what we claim for it, all we ask will be the return of same to cars and we will refund any and all money that had been paid upon same.

“The terms of the sale would be one-half cash when all the machinery has arrived upon car in your city, balance after machinery is started and guarantee, fulfilled in accordance with contract that we would enter into.

“Also wish to state that we will guarantee your material to make brick equal to the samples that we have submitted made from the same material, provided, of course, that it is burned in a manner and with the equipment necessary for burning dry press brick. "What we wish to convey is, that we guarantee that your clay properly burned will make brick similar to the samples that we have submitted, referring to the same clay that you shipped us for making up the samples.”

The contract of sale was on one of the ordinary forms employed by appellee. Appellant being in doubt as to [276]*276whether the foregoing guaranties were contained- in the contract, declined to take the machinery. Appellee, upon being informed of the ground of objection, telegraphed to appellant directing it to make appellee’s letter of February 14th a part of the contract.

Appellant defended on the ground that there was an absolute failure all along the line of the guaranties made by appellee; it also sought to recover damages by way of counterclaim and set-off.

Upon the completion of the pleadings and the calling of the case for trial, appellant moved to have certain issues out of chancery submitted to the jury. This motion the court granted. Of the issues submitted, Nos, 1, 2, 3 and 5 were prepared by counsel for appellant; No. '4, involving the item of $68.20 which was submitted by appellee, was not submitted to the jury. The following are the questions submitted, and the finding of the jury thereon:

“To question 1. Will the clay upon the land of the .defendant Walton Brick Company, at Walton, Ky., when properly burned, make brick equal to the samples furnished by plaintiff to defendant?

“Answer. Yes. By eleven.

“To question 2. Was the brick press, or any part thereof, furnished by plaintiff to the defendant, a new or second-hand press, and if second-hand how much less was it worth than if it had been new?

“Answer. Yes, but worth as much as one mentioned in contract.

“To question 3. Were the brick that were made by the plaintiff for the defendant in its yards at Walton, Ky., made in such a manner that they could be burned into dry pressed brick equal to samples furnished by plaintiff to defendant?

“Answer. Can’t agree.

“To question 5. Was, or not, the man furnished by plaintiff to defendant to operate said machinery, a competent man to properly adjust and operate the said machinery?

“Answer. Yes. By ten.

“To question 6. Was, or not, said machinery furnished defendant by plaintiff at the yard of the Walton Brick Company, at Walton, Ky., sufficient and proper machinery, when properly adjusted and operated, to [277]*277make, when properly bnrned, brick, equal to the sample furnished by plaintiff to defendant?

“Answer. Yes.”

It is conceded by counsel for appellant that the evidence on the trial tending to prove the quality of the machinery and the qualifications of appellee’s expert were sufficient for that purpose. These matters embraced three of the questions submitted. That being true, the only questions left for consideration are Nos. 1 and 3, which we again state in full:

“To question 1. Will the clay upon the land of the defendant Walton Brick Company, at Walton, Ky., when properly burned, make brick equal to the samples furnished by plaintiff to defendant?

“Answer. Yes. ' By eleven.

‘ ‘ To question 3. Were the brick that were made by the plaintiff for the defendant in its yards at Walton, Ky., made in such a manner that they could be burned into dry pressed brick equal to samples furnished by plaintiff to defendant ?

“Answer. Can’t agree.”

As to question No. 1, the finding of the jury was in favor of appellee. The jury could not agree upon an answer to question No. 3. Upon these questions the evidence, in brief, is as follows: Some time prior to the purchase of the machinery J. D. Mayhugh, appellant’s president, sent some of the clay owned by appellant to Chisholm, Boyd & White Company, of Chicago, one of appellee’s competitors. There a test was made, which showed that the clay would make good pressed brick. Appellant also sent some of the clay to appellee. Appellee sent it to a brick concern in Chicago. Its test also showed that good brick could be made out of appellant’s clay. Aside from this testimony, appellee’s manager and Messrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marr v. Lawson
161 S.W.2d 42 (Court of Appeals of Kentucky (pre-1976), 1942)
Kainea v. Kreuger
30 Haw. 860 (Hawaii Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
134 S.W. 136, 142 Ky. 274, 1911 Ky. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walton-brick-co-v-anderson-foundry-machine-works-kyctapp-1911.