Walters v. Kellam & Foley, Mussett, Nicholas & Stevenson, Inc.

360 N.E.2d 199, 172 Ind. App. 207, 1977 Ind. App. LEXIS 750
CourtIndiana Court of Appeals
DecidedFebruary 17, 1977
Docket2-373A64
StatusPublished
Cited by70 cases

This text of 360 N.E.2d 199 (Walters v. Kellam & Foley, Mussett, Nicholas & Stevenson, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walters v. Kellam & Foley, Mussett, Nicholas & Stevenson, Inc., 360 N.E.2d 199, 172 Ind. App. 207, 1977 Ind. App. LEXIS 750 (Ind. Ct. App. 1977).

Opinion

Sullivan, J.

Donald Walters, a sheetmetal worker, was injured on May 28, 1969, while he was installing certain duct work above a heating and ventilating unit in a gymnasium building. He was positioned on top of the unit and, in the course of his work, dropped a tool, which fell into the unit, coming to rest on the bottom panel. To retrieve the tool, *209 Walters lowered himself into the unit, placing his feet on the same bottom panel. The panel broke loose, and he fell some thirty feet to the concrete floor below. As a result, he sustained serious injuries.

Walters and his wife, Jessie (Walters) 1 filed suit for damages.

Walters appeals from a summary judgment in favor of Glenroy Construction Co., Inc. (Glenroy), the general construction contractor. Walters also appeals from judgments on the evidence in favor of the other defendant-appellees, Kellam & Foley, the architect; Mussett, Nicholas & Stevenson, Inc. (Mussett), the mechanical engineer; Burton Plumbing-Heating Co., Inc. (Burton), the mechanical contractor; Modine Manufacturing Co. (Modine), the heating and ventilating unit manufacturer; and Fink and Kress, the supplier of the Modine equipment.

Facts which are important pertain to the manner in which Walters’ work was conducted. Scaffolding was available in the immediate area where he worked. However, it was used by the sheetmetal workers on this job, not as a protective device to prevent or obstruct falls, nor as a stable work location, but as a ladder to reach the top of the unit. Because the work took place at a height exceeding thirty feet, statutory provisions requiring scaffolding or staging are relevant and are hereinafter discussed. (See footnote 2, infra). In addition, testimony revealed that Walters and at least one other sheetmetal worker on this job had previously stepped down into the unit onto the bottom panel in the course of accomplishing their work. Whether such conduct was the customary practice in the sheetmetal trade and the admissibility of such evidence were points of controversy during trial and are at issue here.

The contractual arrangements by which the various defendants undertook the project are as follows: The Fayette *210 County School Corporation (Owner) and the Fayette County School Building Corporation contracted with architect, Kellam & Foley, to provide planning and architectural services for the development of a new high school complex. Kellam & Foley, in turn, subcontracted with Mussett for the engineering and design of the mechanical phases of the construction. The Owner contracted separately with Glenroy for general construction services and with Burton for mechanical construction services. Walters’ employer, Brad Snodgrass, Inc. (third party defendant impleaded by Burton and severed from this litigation pursuant to a motion for separate trial), was engaged by Burton to install duct work and to assist in the installation of the Modine manufactured heating and ventilating units, supplied by Fink & Kress.

Walters and his wife brought suit alleging common law negligence against all defendants; strict tort liability against the manufacturer, Modine, and the supplier, Fink & Kress; and statutory negligence 2 against the contractors, Glenroy and Burton; the architect, Kellam & Foley, and the engineer, Mussett.

Prior to trial, the trial court granted Glenroy’s motion for summary judgment pursuant to Ind. Rules of Procedure, Trial Rule 56. During the jury trial, after presentation of plaintiff’s case, all remaining defendants moved for judgment on the evidence pursuant to Ind. Rules of Procedure, Trial *211 Rule 50, and the trial court sustained all such motions. Walters asserts that these rulings are erroneous, and, in addition, challenges the exclusion of several offers of testimony from various witnesses. 3

We affirm the summary judgment for Glenroy and affirm the judgment on the evidence as to Kellam & Foley and as to Mussett. We reverse the judgments on the evidence as to all remaining defendants.

Our attention is directed first to the allegation that the trial court erred in granting summary judgment in favor of Glenroy, the construction contractor.

I.

SUMMARY JUDGMENT FOR GLENROY WAS NOT ERRONEOUSLY GRANTED

The question before us is whether there existed any genuine issue of material fact as to Glenroy.

In his complaint, Walters alleged negligence against Glenroy for failure (1) to supply or cause to be supplied a unit which would safely hold Walters’ body weight; (2) to inspect and reject any faulty units, or alternatively, to warn of hidden dangers; and (3) to construct safety scaffolding, required by the Dangerous Occupation Act, supra.

Glenroy, in moving for summary judgment, asserted that no genuine issue of material fact existed because the school construction was done in accordance with three prime contracts: a construction contract with Glenroy; a mechanical contract with Burton; and an electrical contract with B & B Electric Company. Glenroy further asserted that each prime contractor was fully responsible for the conduct of the work to be performed under its individual contract with the Owner, and that therefore, Glenroy had no responsibility or authority with respect to the mechanical installation of the heating *212 units or any work performed relative thereto. On the other hand, plaintiff had asserted in his complaint that Glenroy, being the “general construction contractor,” was the “supervising” or “general” contractor. Plaintiff later argued in his brief in opposition to the summary judgment and in his appeal brief that although Glenroy was one of three prime contractors, Glenroy should be held liable because it was somehow co-operating with, acquiescing in, or mutually interested in the overall construction project and therefore had a right to control the conduct of the duct work installation.

The contract between Glenroy and the Owner is not of record, nor did either party to this motion for summary judgment attempt to make it a part of the record. Consequently, the duties assigned to Glenroy by the Owner were then and are now a matter of pure conjecture. However, Walters would urge that the contract between Burton, the mechanical contractor, and the Owner permits the inference that Glenroy had on-site inspection duties as well as the responsibility for overseeing all construction work. The Burton contract, however, contains no mention of Glenroy. Its terms are largely those of the American Institute of Architect’s standard form contract. The overriding emphases go to the duties of that “contractor,” i.e. Burton. The only references made to “general contractor” must be construed in context with the substance and purpose of the Burton contract. In that light, the “general contractor” references undoubtedly pertain to Burton itself and are interchangeable with the use of the term “contractor” to describe Burton.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JENNIFER PENNINGTON v. Spear Corporation
Indiana Court of Appeals, 2023
Mayberry Café, Inc. v. Glenmark Construction Co.
879 N.E.2d 1162 (Indiana Court of Appeals, 2008)
Hammock v. Red Gold, Inc.
784 N.E.2d 495 (Indiana Court of Appeals, 2003)
Wal-Mart Stores, Inc. v. Wright
754 N.E.2d 1013 (Indiana Court of Appeals, 2001)
Estate of Heck Ex Rel. Heck v. Stoffer
752 N.E.2d 192 (Indiana Court of Appeals, 2001)
Ousley v. BOARD OF COMMISSIONERS OF FULTON CTY.
734 N.E.2d 290 (Indiana Court of Appeals, 2000)
Hagerman Construction, Inc. v. Copeland
697 N.E.2d 948 (Indiana Court of Appeals, 1998)
Creasy v. Rusk
696 N.E.2d 442 (Indiana Court of Appeals, 1998)
Herb v. State Board of Tax Commissioners
656 N.E.2d 890 (Indiana Tax Court, 1995)
Bloemker v. Detroit Diesel Corp.
655 N.E.2d 117 (Indiana Court of Appeals, 1995)
G.M. Meredith & Associates v. Blue Pacific Management Corp.
28 Am. Samoa 2d 60 (High Court of American Samoa, 1995)
Rickels v. Herr
638 N.E.2d 1280 (Indiana Court of Appeals, 1994)
N. Ind. Pub. Serv. v. E. CHICAGO SAN. D.
590 N.E.2d 1067 (Indiana Court of Appeals, 1992)
Northern Indiana Public Service Co. v. East Chicago Sanitary District
590 N.E.2d 1067 (Indiana Court of Appeals, 1992)
Moore Heating & Plumbing, Inc. v. Huber
583 N.E.2d 142 (Indiana Court of Appeals, 1991)
Alexander v. City of Shelbyville
575 N.E.2d 1058 (Indiana Court of Appeals, 1991)
McLaughlin v. Michelin Tire Corp.
778 P.2d 59 (Wyoming Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
360 N.E.2d 199, 172 Ind. App. 207, 1977 Ind. App. LEXIS 750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walters-v-kellam-foley-mussett-nicholas-stevenson-inc-indctapp-1977.