Walter Cain v. Consumers Energy

CourtMichigan Court of Appeals
DecidedJuly 18, 2024
Docket366448
StatusUnpublished

This text of Walter Cain v. Consumers Energy (Walter Cain v. Consumers Energy) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walter Cain v. Consumers Energy, (Mich. Ct. App. 2024).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

WALTER CAIN and MAVIS R. CAIN, UNPUBLISHED July 18, 2024 Plaintiffs/Counterdefendants- Appellants,

V No. 366448 Mecosta Circuit Court CONSUMERS ENERGY, LC No. 19-024820-CZ

Defendant/Counterplaintiff-Appellee.

Before: CAMERON, P.J., and M. J. KELLY and YATES, JJ.

PER CURIAM.

Plaintiffs, Walter and Mavis Cain, appeal of right the trial court’s order directing a verdict for defendant, Consumers Energy, with regard to plaintiffs’ claims of nuisance and trespass. After plaintiffs finished presenting proofs at trial, the trial court ruled that plaintiffs’ trespass claim was barred by res judicata and that plaintiffs had not properly followed the procedure for pursuing their public nuisance claim. We reverse those rulings and remand the case for further proceedings.

I. FACTUAL BACKGROUND

Plaintiffs own a parcel of property in Mecosta County on which they operate a public-use airport and mine gravel for sale. In 2017, defendant, which had an easement on plaintiffs’ property, replaced utility poles on the easement. The new poles placed on the side of the runway were taller than the old poles, prompting plaintiffs’ concern that the higher poles and wires might present a danger to aircraft. Plaintiffs first contacted defendant, the Michigan Department of Transportation, and the Federal Aviation Administration, and then plaintiffs filed this lawsuit on February 4, 2019. In their complaint, plaintiffs asserted that defendants’ construction constituted a trespass because the height and different locations of the new poles and anchor wires that extended onto plaintiffs’ property exceeded the rights granted in the original easement. Plaintiffs also claimed that the new poles and anchor wires interfered with the operation of plaintiffs’ gravel pit, endangered aircraft, and forced plaintiffs to erect a new fence for their cattle. Plaintiffs later summarized their trespass claim by explaining that they wanted to be paid for the gravel surrounding their property that was taken by condemnation. Additionally, plaintiffs alleged that the higher poles and wires constituted

-1- both a public nuisance and a private nuisance because of the danger to aircraft that used the airport and the interference with plaintiffs’ use of their gravel pit. Plaintiffs asked the trial court to award monetary damages and order the abatement of the nuisance by restricting new poles to the original sizes and locations of the original poles.

While this case was pending, defendant filed a separate condemnation suit against plaintiffs concerning a small area on which some of the newly installed equipment was placed. That action was the subject of case evaluation, which resulted in a resolution when the parties agreed to accept the case-evaluation award in September 2022. The stipulated dismissal filed by the parties stated in sweeping terms that “[t]he case evaluation award is a complete compromise and settlement of all asserted and unasserted claims pertaining to necessity and for just compensation . . . .” But it also specified that it did “not affect or alter any claims or defenses of any party” in the instant case.

This case, which remained unresolved despite the case-evaluation process, went to trial on November 15, 16, and 17, 2022. After plaintiffs rested their case-in-chief, defendant made an oral motion for a directed verdict on plaintiff’s claims pursuant to MCR 2.516. Defendant asserted that it was entitled to a directed verdict on the trespass claim because plaintiffs should not be allowed to pursue any claim for damages related to sand and gravel. Defendant insisted that those damages either were, or could have been, addressed in the condemnation case, and therefore plaintiffs were barred from pursuing those damages in this case under res judicata. Addressing the factors relevant to res judicata, defendant argued that (1) the condemnation case was decided on the merits because it was resolved via acceptance of the case-evaluation award, (2) the parties in this case were also parties to the condemnation case, and (3) plaintiffs had the opportunity to pursue damages for sand and gravel that was underneath the utility poles and guy wires and outside of the easement in the condemnation case, but plaintiffs did not pursue those damages in that case.

Plaintiffs responded that they were not compensated for the land surrounding the easement and they had no opportunity to pursue damages for the land adjacent to the condemned land in the condemnation case. Plaintiffs explained that their unsuccessful attempt to bring a similar claim in the condemnation case did not bar their trespass claim in this case because that claim was legally prohibited in the condemnation case. However, the trial court agreed with defendant and held that plaintiffs’ trespass claim was barred by res judicata because the condemnation case was resolved on the merits, it involved the same parties, and the trespass issue was, or could have been, decided in the condemnation case.

Defendant further claimed an entitlement to a directed verdict on plaintiffs’ nuisance claim. First, defendant asserted that, as a matter of law, the larger poles did not overburden the easement. But plaintiffs clarified that the claim focused on the hazard created by the larger poles as a nuisance and insisted that whether the easement was overburdened was of little importance compared to the hazard the poles posed. The trial court agreed that plaintiffs could not argue that the easement was overburdened, but that did not foreclose plaintiffs’ claim that the poles were a nuisance.

-2- Defendant then argued that it was entitled to a directed verdict on plaintiffs’ nuisance claim because this was not an issue for a jury to decide under MCR 3.601.1 Defendant asserted that the jury did not have the authority to order an abatement of a nuisance. The trial court initially agreed, but noted that the jury could still decide whether it was a nuisance, and then the court could decide how to abate the nuisance. Defendant insisted that the entire nuisance issue was not triable by the jury and told the court that it was not prepared to argue about appropriate abatement at that time.

The trial court also observed that MCR 3.601 only dealt with public nuisances. Defendant agreed that that court rule was not applicable to private nuisance claims. Plaintiffs responded that, for the public nuisance claim, the jury could determine whether the new poles were a nuisance as an advisory opinion for the trial court, citing MCR 2.509(D). Defendant stated that it would have litigated the case differently if it had known that plaintiffs were seeking equitable relief, so it was inappropriate at that late stage for the trial court to rule on an equitable remedy.

The trial court ultimately agreed with defendant that the nuisance claim must be dismissed. The trial court determined that, pursuant to MCR 3.601, “the procedure to abate public nuisances is through a nonjury action not a jury trial and that issue was not appropriate for the jury to make a determination on [a]nd it has not been presented as a nonjury issue.” Accordingly, the trial court discharged the jury and entered a written order dismissing plaintiffs’ claims. Plaintiffs moved for reconsideration, but the trial court denied that motion in a written order issued on March 7, 2023. This appeal followed.

II. LEGAL ANALYSIS

On appeal, plaintiffs contend that the trial court erred in granting defendant’s motion for a directed verdict and dismissing their claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington v. Sinai Hosp. of Greater Detroit
733 N.W.2d 755 (Michigan Supreme Court, 2007)
Adair v. State
680 N.W.2d 386 (Michigan Supreme Court, 2004)
Cavaliere v. Adults for Kids
386 N.W.2d 667 (Michigan Court of Appeals, 1986)
Jones v. State Farm Mutual Automobile Insurance
509 N.W.2d 829 (Michigan Court of Appeals, 1993)
Cloverleaf Car Co. v. Phillips Petroleum Co.
540 N.W.2d 297 (Michigan Court of Appeals, 1995)
Garrett v. Washington
886 N.W.2d 762 (Michigan Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Walter Cain v. Consumers Energy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walter-cain-v-consumers-energy-michctapp-2024.