Wells, J.

The agreement set np in the third plea amounted to an undertaking by the plaintiff, that during the reasonable time allowed for the completion of the house, he would not bring his action for the moneys then due from the defendant, or for what might in the meantime accrue. It was of no greater effect certainly, than a covenant not to sue during the same time. But a covenant not to sue for a limited time was never held to bar an action brought in the meantime. The reason is, that if the defendant plead such covenant in bar and succeed upon his plea, the plaintiff will be precluded from bringing his second action after the time limited has expired. Guard v. Whiteside, 13 Ill. 7. To give the agreement set up its fullest effect, therefore, it could not be pleaded in bar. The demurrer was for this reason properly sustained. The plaintiff upon his examination went out of his way to assert that, of certain moneys received by the defendant'to his use, no part had been repaid to him. The defendant was therefore entitled to cross-examine to the question of payment, but in the opening of his cross-examination, the plaintiff had stated that he had received money from the defendant at different times ; and the question afterward propounded, and for the exclusion of which error is assigned, called for no more than this. It was, therefore, entirely proper to exclude it. If the question propounded had been directed to whether particular sums had not been paid, or whether payments had not been made at particular times, or the like, it must have been allowed. But the court was under no requirement to permit counsel to renew a question already propounded and answered.

The instruction prayed by the defendant below upon the [438]*438question of interest was substantially given by the court, though in other language; in'this, as has been repeatedly decided, there was no error. There was evidence tending to show, that at sometime during, or prior to the summer of 1870, the defendant had entered into an agreement to erect for plaintiff, who was then in his employment, the dwelling-house alluded to in the second instruction given, upon the promise of plaintiff, that if, when it should be completed, the demand of the defendant therefor should amount to more than the indebtedness of the defendant to him, he would pay the difference. The defendant himself was the only witness examined as to this, and the only inference that can fairly be drawn from his testimony is, that he was tó build and complete the structure. It was an entire contract. So far as appears, nothing was said as to the time within which it was to be completed. But this omission the law supplies by the presumption that a reasonable time was contemplated and no action would lie at the suit of defendant upon the contract, unless he had fully performed it, as well in point of time as in other particulars, or unless he had been prevented from performing it by the act or default of the plaintiff, or unless the time of performance having been subsequently enlarged by agreement of the parties, he had performed the contract as so modified. Nothing of this sort was pretended. Neither, if the contract were not fully performed, would indebitatus assumpsit lie upon the quantum meruit for what had been done, except under special circumstances, e. g., such action would not lie if the defendant had willfully, and without excuse, abandoned his undertaking. Dermott v. Jones, 2 Wall. 1. Neither, in the like case, could defendant have advantage of what he had expended by way of set-off, in an action brought by the plaintiff. But while it sufficiently appeared that a time reasonably sufficient for the completion of such a structure had, long before the bringing of this action, elapsed, and that the house was still incomplete even down to the date of the trial, no circumstance excusing this delay was anywhere shown ; for any thing that appears, the defendant refused or [439]*439omitted to perform his undertaking, without any reason or excuse for his omission. The burden of accounting for his defalcation on this behalf was, of course, upon the defendant, and he having failed to explain it, it was not improper for the court to charge the jury, that the evidence was not sufficient to warrant them in allowing the set-off claimed. This was the effect of the instruction now under consideration. The question of reasonable time, reasonable diligence and the like, is, it is true,'ordinarily for the jury, under proper instructions, and perhaps it would have been proper to have submitted it in this case ; the final proposition asserted in the instruction given as to this point, being made dependent upon how the jury should find as to whether time, reasonably sufficient for the completion of the house, had or had not elapsed before plaintiff brought hi& action. If the court had so charged, it would have been necessary to further charge, that if the contract contemplated the erection of a house such as spoken of in testimony, of the reasonable value of $1,200 or thereabouts, and if the period of one year and over had elapsed between the date of the contract and the bringing of the plaintiff's action, the defendant had not proceeded with reasonable diligence. But, upon the evidence heard, the jury would not have been warranted in resolving either of these questions of fact in the negative, so that the defendant cannot be said to have been prejudiced by the omission of the court in this respect, even if the omission were erroneous, which is not admitted. N either is it material that the instruction is predicated upon the supposition of a price agreed upon, for whether the price, which should be paid by plaintiff for the erection of the house, was fixed and agreed upon, or left to be supplied by the legal presumption that a reasonable price was intended, is not in any manner material to the residue of the proposition, which the instruction asserts ; and however the jury may have found upon the question of price the defendant cannot have been prejudiced. Evidence was given in the court below, touching certain material, amounting in all to the value of $600, or there[440]*440abouts, which was said to have been delivered by the defendant to the use of the plaintiff, at certain localities in ^Nevada street and Eureka street. The defendant in error, in his examination, denied that he gave authority for such delivery, and the jury seem to have given him credit. It cannot be said that we are entitled to review their action in this. As we understand the testimony, no other witness was examined as to this matter. Other witnesses declare, in general terms, that the defendant delivered lumber for the plaintiff at these places ; but none of .them speak to any express direction given by the defendant, authorizing such delivery. The jury seem to have regarded these witnesses as speaking to their understanding of the purpose for which the lumber was delivered, and not as declaring that of their own knowledge the delivery was by authority. It is true that a portion of this lumber was afterward removed by the plaintiff and appropriated, but neither this nor plaintiff’s declaration to Walters, when informed that the lumber in question was being carried away, can be regarded as conclusive, that plaintiff had, in truth, authorized the lumber to be placed where it was found. The jury must be supposed to have given to these circumstances their due weight; and considering the whole evidence, we cannot say that they have erred in rejecting these items of the defendant’s demand. Rejecting these items, and those as to disbursements, for which no authority from the plaintiff is shown, e. g.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Distributing Co. v. Diodosio
841 P.2d 1053 (Supreme Court of Colorado, 1992)
Rider v. Rider
493 P.2d 679 (Colorado Court of Appeals, 1972)
Price v. Baker
352 P.2d 90 (Supreme Court of Colorado, 1960)
Boggs v. McMickle
206 P.2d 824 (Supreme Court of Colorado, 1949)
State ex rel. Stock Inspection Commissioners v. Nelson
223 P. 1086 (Supreme Court of Colorado, 1924)
Cocquyt v. Shower
68 Colo. 89 (Supreme Court of Colorado, 1920)
Trimble v. Collins
172 P. 421 (Supreme Court of Colorado, 1918)
Morris v. Hokosona
26 Colo. App. 251 (Colorado Court of Appeals, 1914)
Lombard v. Overland Ditch & Reservoir Co.
41 Colo. 253 (Supreme Court of Colorado, 1907)
Cochran v. Balfe
12 Colo. App. 75 (Colorado Court of Appeals, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
2 Colo. 434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walling-v-warren-colo-1874.