Walling v. Hardy Construction

807 P.2d 1335, 247 Mont. 441, 48 State Rptr. 250, 1991 Mont. LEXIS 63
CourtMontana Supreme Court
DecidedMarch 19, 1991
Docket90-345
StatusPublished
Cited by13 cases

This text of 807 P.2d 1335 (Walling v. Hardy Construction) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walling v. Hardy Construction, 807 P.2d 1335, 247 Mont. 441, 48 State Rptr. 250, 1991 Mont. LEXIS 63 (Mo. 1991).

Opinion

JUSTICE HARRISON

delivered the Opinion of the Court.

On June 6, 1990, the Montana Workers’ Compensation Court determined that claimant Jess K. Walling, as an independent contractor, could not recover workers’ compensation benefits from Hardy Construction, the general contractor. From this decision, Wailing appeals. We affirm.

The following issues are presented:

1. Was the evidence sufficient for the Workers’ Compensation Court to find that Walling was an independent contractor, rather than an employee of Hardy Construction?

2. In concluding that Walling was an independent contractor, did the Workers’ Compensation Court err in its analysis of the control factor of § 39-71-120, MCA?

3. Did the Workers’ Compensation Court err by applying § 39-71-401, MCA, as a basis for denying Hardy Construction’s liability under the Workers’ Compensation Act?

*445 Summary of Facts

In September 1984 Hardy Construction, a general contractor, was awarded a $6.5 million contract for construction of a new Fergus County high school. Hardy Construction negotiated a subcontract, signed on January 10,1985, with Jess Walling, proprietor of Walling Construction, a business in operation from 1976 to 1985. In submitting his bid for the concrete flatwork, Walling advised Hardy Construction that Walling did not want to set the forms, but only wanted to do the pouring and finishing. Walling agreed to pour and finish concrete slabs on the school construction project for 28 cents per square foot.

Paragraph VII of the subcontract provided that Walling was to “obtain, maintain and pay for such workmen’s compensation insurance as may be required by the General Contract or by law ... .” Walling complied with this requirement of the subcontract by providing workers’ compensation insurance through the State Fund for his employees. As allowed by law, Walling elected not to pay for workers’ compensation insurance for himself.

The agreement specified that the subcontractor was to “proceed with the work in the sequence directed by the Contractor and to abide by the Contractor’s decision as to the allotment of all storage and working space on the Project.”

The subcontract required Walling to provide “[ljabor and equipment to place and finish concrete.” Equipment provided by Walling included shovels, rakes, wheelbarrows, cement finishing machines worth $200 to $350, and hand tools. Under the terms of the subcontract, Hardy Construction provided concrete, cure, sealer, hardener, concrete saw worth $1,000, installation of forms, reinforcing steel, and visqueen.

On one occasion Hardy Construction allowed Walling to use a forklift, operated by a Hardy Construction employee, for lifting concrete to mezzanine level. On three occasions, in order to speed up the work, Hardy Construction made available to Walling a Bobcat tractor driven by a Hardy Construction employee.

Under the terms of the subcontract, Hardy Construction had the authority, which it never exercised, to fire any Walling employee Hardy Construction considered objectionable. If the subcontract were terminated, the subcontractor retained the right to withhold service and to extend the time for completion of the work if delay were the fault of Hardy Construction.

*446 On the job Hardy Construction’s superintendent, Norm Bjorndal, pursuant to the subcontract, controlled the sequence of work by subcontractors. Walling checked with Bjorndal daily to find out when and where concrete was to be poured. Bjorndal told Walling and his employees where they had to work and how much concrete to pour each day. At times, Bjorndal ordered Walling to pour concrete over Walling’s objections that rain would min the concrete. By altering the method of setting the screed, Bjorndal changed Walling’s procedure for making the concrete surface flat. Bjorndal also determined whether to “burn the floor,” giving the concrete a high gloss finish, or whether to leave the concrete with a rough finish. Walling worked along with his employees.

On the other hand, Walling or one of his foremen, Jim Plovanich or Dan Oblander, supervised the Walling employees. Bjorndal did not instruct Walling on which employees or how many employees to have on the constmction site. Bjorndal did not tell Walling which Walling employees were to perform certain tasks or what tools to use. Walling, rather than Bjorndal, controlled when the Walling employees would take lunch and coffee breaks or could leave the job site.

Walling employees did not make out time cards as did Hardy Construction employees. Rather, Walling paid his own employees. According to the subcontract, Walling was paid within sixty days of submittal of a certified monthly estimate to Hardy Construction, provided that the architect had certified the monthly estimate, that Walling was not in default, and that Hardy Construction had been paid by the project owner. Payment to Walling was usually made monthly. In contrast, Hardy Construction employees were paid weekly whether or not Hardy was paid by the owner of the project.

Each month Hardy Constmction obtained lien waivers from Walling and its other subcontractors.

On May 28,1985, Walling, while working, severely injured his back when he slipped on some wet forms at the construction site. Due to his injuries, Walling underwent surgery on June 27, 1985. About 90 per cent of Walling’s work had been completed at that point. After Walling’s injury, Bjorndal took over Walling’s crew until the work was finished in July, 1985.

Walling claimed that he was eligible for workers’ compensation benefits as an employee of Hardy Constmction, rather than an independent contractor. On December 6,1989, a trial was held before the Workers’ Compensation Court on the issue of liability, which was *447 bifurcated from the question of the nature and extent of Walling’s injury. From the court’s decision in favor of Hardy Construction, Walling appeals.

I.

Was the evidence sufficient for the Workers’ Compensation Court to find that Walling was an independent contractor, rather than an employee of Hardy Construction?

Walling claims that he was an employee of Hardy Construction, not an independent contractor. See § 39-71-118(l)(a), MCA. An “independent contractor” is defined as follows:

“[0]ne who renders service in the course of an occupation and:
“(a) has been and will continue to be free from control or direction over the performance of the services, both under his contract and in fact; and
“(b) is engaged in an independently established trade, occupation, profession, or business.”

Section 39-71-120, MCA.

The parties agree that Walling Construction, as an independently established trade or business, satisfies subsection (2) of § 39-71-120, MCA. However, Walling alleges that when working for Hardy Construction, he was not “free of direction or control over the performance of services,” as required by subsection (1).

In Sharp v. Hoerner Waldorf Corp. (1978), 178 Mont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Fedex Ground Package System, Inc.
273 F.R.D. 424 (N.D. Indiana, 2008)
Wild v. Fregein Construction
2003 MT 115 (Montana Supreme Court, 2003)
Mathews v. BJS Construction, Inc.
2003 MT 116 (Montana Supreme Court, 2003)
Spain v. Montana Department of Revenue
2002 MT 146 (Montana Supreme Court, 2002)
Potter v. Montana Department of Labor & Industry
853 P.2d 1207 (Montana Supreme Court, 1993)
Potter v. DEPT. OF LABOR AND INDUST.
853 P.2d 1207 (Montana Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
807 P.2d 1335, 247 Mont. 441, 48 State Rptr. 250, 1991 Mont. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walling-v-hardy-construction-mont-1991.