Walker v. Railroad

49 S.E. 84, 137 N.C. 163
CourtSupreme Court of North Carolina
DecidedDecember 13, 1904
StatusPublished
Cited by14 cases

This text of 49 S.E. 84 (Walker v. Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. Railroad, 49 S.E. 84, 137 N.C. 163 (N.C. 1904).

Opinions

CLARK, C. J., and DOUGLAS, J., dissenting. This action was brought to recover the penalty for failure to transport freight, given by chapter 590, section 3, Laws 1903. Plaintiffs alleged that there had been a delay of four days and demanded judgment for $40, that is, $25 for the first day and $5 per day for the next three days of delay. The material portion of the evidence was as follows:

(1) Bill of lading issued by the defendant bearing date Cumnock, N.C. 27 May, 1903, for a car-load of lumber, to be transported to the plaintiffs at Graham, N.C. J. R. Burns was the shipper.

(2) The receipt of the plaintiff for the said freight, bearing date Graham, N.C. 4 June, 1903.

D. M. Walker, one of the plaintiffs, testified: That he and J. C. (164) Walker constitute the firm of Walker Bros. The witness identified the bill of lading and freight bill hereinbefore referred to and said the dates as therein stated were correct. The plaintiffs operated a saw-mill situated about 160 feet from the main line of the North Carolina Railroad Company, some 300 or 400 yards east of the station at Graham in Alamance County, and were accommodated by what is ordinarily known as an industrial or spur track, running from the main line into their yards, which are inclosed. When they receive freight by the carload the car is placed by the defendant on this spur track and unloaded in the mill-yard of the plaintiffs. The car in question was delivered to them in their yards on 4 June, 1903. The bill of lading was received by the plaintiffs through the mails about May, 1903. Plaintiffs made demand upon the agent of defendant at Graham. The spur or industrial track was put in at the instance of the plaintiffs, and operated, as witness supposed, for the accommodation of both the plaintiffs and defendant, as the cars could be unloaded sooner. No extra charge was demanded or made against the plaintiffs for shifting and carrying cars from the main track of the defendant into the yard of the plaintiffs by means of the spur track. The cars containing freight for other parties were not put upon the spur track of plaintiffs without their permission, nor carried inside the gate of plaintiff's yard. The witness did not know of his own knowledge when the car in question arrived at Graham station. The train passed, but he did not see it come.

The freight in question was brought in the car from Cumnock by way of Greensboro and from the latter place to Graham. There are four stations or stops between Greensboro and Graham, and ten stations between Greensboro and Cumnock. 31 May, 1903, was Sunday. Witness made demand on the railroad company for the car of freight in question, and at that time the car had not arrived in Graham. (165)

It was admitted by the parties that the defendant transported freight and passengers through several states, including this State, and *Page 138 is engaged in interstate commerce, and it was admitted that Cumnock and Graham are stations on different roads, both of which are operated by defendant within this State.

Plaintiffs here rested their case. The defendant thereupon moved to nonsuit the plaintiffs under the statute, which motion was allowed and judgment was rendered accordingly. Plaintiffs excepted and appealed. After stating the facts: It is provided by Laws 1903, ch. 590, sec. 3, that any railroad company failing to transport goods received by it for shipment and billed to any place in this State for a longer period than 4 days after the receipt of the same, unless otherwise agreed between the parties, or allowing such goods to remain at any intermediate point more than 48 hours, shall pay to the party aggrieved a penalty of $25 for the first day and $5 for each succeeding day of unlawful delay or detention, if the shipment is in car-load lots, and if in smaller quantities, then a less sum, which is prescribed by the act. The plaintiffs claim that by the statute the defendant is allowed only 4 days to make the shipment, and any delay beyond that time subjects it to the penalty. We do not think that is the proper construction of the law. The word "transport" does mean to carry or convey from one place to another, but it also means to "remove," and this is one of its primary significations, according to the lexicographers. (166) Whatever may be the precise meaning of the word when considered by itself and apart from the special connection in which it is used, the context of the act under review clearly shows that the Legislature did not intend to be understood as requiring the entire transit to be made within four days from the receipt of the goods. Such a construction might produce serious results and impose upon transportation companies not only a very onerous duty, but one which, in some cases, it would be difficult, if not impossible, to perform. It has been said that in regard to laws, as in other cases, difficulties will arise, in the first place, from the disputed meaning of individual words, or, as it is usually expressed, of the language employed, and, in the second place, assuming the sense of each separate word to be clear, doubt will result from the whole context. This is due in large measure to the imperfection of language and its inadequacy in conveying our meaning. We must, therefore, regard the context and the general scope of the law as well as the mischief to be suppressed and the remedy provided for that purpose so as to arrive at the intention of the Legislature. "When we see what is the sense that agrees with the intention of *Page 139 the instrument (or statute), it is not allowable to wrest the words to a contrary meaning. No text imposing obligations is understood to demand impossible things." Sedgwick Stat. and Const. Law (1857), ch. 6. pp. 225-235. Whenever the intention can be discovered it ought to be followed with reason and discretion in construing the statute, although it may not seem to conform to the letter. Sedgwick, supra. We have no doubt as to the true intention of the Legislature in passing this act. The very phraseology of the statute indicates clearly the purpose that the penalty shall be incurred if the company delays to begin the transportation or to start the goods on their journey within four days after they are received for shipment. The fact that the law provides against unreasonable delay during the course of the transportation at any intermediate station is conclusive evidence that the (167) neglect or omission to transport for a longer period than four days refers to a delay at the initial point or the place of departure. To hold it to have been contemplated that four days only from the time of receipt should be allowed for the shipment of the goods and their delivery at the place of final destination would impute to the Legislature an intention to adopt a harsh and impracticable rule, and therefore an unreasonable one, as the time allowed might not be sufficient in many cases for the transportation as thus understood. Having concluded that the four days must apply to the time of shipment, we find no evidence as to when the goods left Cumnock nor as to when they reached Graham; and even if there had been such evidence, we have failed to discover any proof as to the distance between Cumnock and Graham, or as to the time reasonably required to carry the goods from one place to the other. The burden was on the plaintiff to bring forward the proof necessary to establish his allegations and to make out his case, and in the absence of evidence we can raise no presumption in his favor. If the defendant has violated the law and incurred its penalty, the plaintiff must show it affirmatively. There is not in this case the slightest evidence as to the essential fact to be proved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. Pittman-Harrison Co.
249 S.W. 889 (Court of Appeals of Texas, 1923)
Garrison v. Southern Railway Co.
64 S.E. 578 (Supreme Court of North Carolina, 1909)
Davis v. Southern Railway Co.
60 S.E. 722 (Supreme Court of North Carolina, 1908)
Jenkins v. Southern Railway Co.
59 S.E. 663 (Supreme Court of North Carolina, 1907)
Cardwell v. Southern Railway Co.
59 S.E. 673 (Supreme Court of North Carolina, 1907)
Watson v. Atlantic Coast Line Railroad
59 S.E. 55 (Supreme Court of North Carolina, 1907)
Harper Furniture Co. v. Southern Express Co.
57 S.E. 458 (Supreme Court of North Carolina, 1907)
Stone & Co. v. Atlantic Coast Line Railroad
56 S.E. 932 (Supreme Court of North Carolina, 1907)
Alexander v. Atlantic Coast Line Railroad
56 S.E. 697 (Supreme Court of North Carolina, 1907)
Summers v. Railroad
50 S.E. 714 (Supreme Court of North Carolina, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
49 S.E. 84, 137 N.C. 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-railroad-nc-1904.