Wakefield Construction Co. v. City of New York

157 A.D. 535, 142 N.Y.S. 743, 1913 N.Y. App. Div. LEXIS 6633
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 10, 1913
StatusPublished
Cited by1 cases

This text of 157 A.D. 535 (Wakefield Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wakefield Construction Co. v. City of New York, 157 A.D. 535, 142 N.Y.S. 743, 1913 N.Y. App. Div. LEXIS 6633 (N.Y. Ct. App. 1913).

Opinion

McLaughlin, J.:

In October, 1909, the plaintiff entered into a contract with the city of New York for the construction of a sewer in the borough of the Bronx. The work was commenced in November of that year and in May, 1910, the plaintiff was notified [536]*536that the contract was canceled, and it was prevented from further performance. This action was brought to recover the damages sustained. Upon the trial the plaintiff had a verdict and from the judgment entered thereon and an order denying a motion for a new trial defendant appeals.

Substantially the only question presented by the appeal is whether the contract was canceled in accordance with its terms. It was to be completed within 600 working days, Sundays, holidays upon which no work was done, and the time during which work was delayed through, the fault of the city, being excepted. The chief engineer of the borough of the Bronx was made the arbiter in case of disputes, and it was further provided that if the contractor should abandon or sublet the work, or “if at any time the Chief Engineer shall be of the opinion and shall so certify in writing to the President, that the performance of the contract is unnecessarily or unreasonably delayed, or that the contractor is willfully violating any of the conditions or covenants of this contract, or is executing same in bad faith, or not in accordance with the terms hereof * * * the President may notify the contractor to discontinue all work, or any part thereof, under this contract, * * * and thereupon the contractor shall discontinue said work or such part thereof, and the President shall thereupon have the power to contract for the performance and completion of the work in the manner prescribed by law. ” The president referred to was the president of the borough of the Bronx.

The appellant’s claim is that the contract was duly canceled in accordance with the clause quoted. In this connection it appeared at the trial that on May 14, 1910, the chief engineer of sewers and highways of the borough of the Bronx wrote a letter addressed to the commissioner of public works of that borough with reference to the contract, stating that the plaintiff had been ordered to commence work on November 15, 1909; that 126% working days had been consumed and only $15,861.60 of work completed, the estimated cost being $671,725.50; that during the month of April only about forty men a day had been employed and $1,800 of work done; and that the plant installed was worth only about $20,000, whereas a sufficient plant would require an expenditure of at least [537]*537$60,000. The letter also stated the quantity of materials delivered on the work, and concluded: “There is nothing to indicate that the contractor has even a fair conception of the magnitude of work he has in hand. There seems to be no well-defined idea of carrying the same out. His forces are now, and have been in the past, entirely inadequate, and urging by the engineers seems to have no effect whatever. * * * In view of the foregoing, I would recommend that under covenant AA of the specifications that the contract be declared abandoned.” The covenant referred to is the clause above quoted.

Upon the strength of this letter, the borough president, on May 16, 1910, wrote to the plaintiff notifying it, “ I am of the opinion and do so certify in writing that the work on the contract * * * is not being prosecuted in a manner satisfactory to this department, but is unnecessarily and unreasonably delayed in violation of the terms and conditions of the contract and the work is not progressing according to the terms of the contract. In view of the above reasons I hereby declare your contract abandoned and you are hereby notified to discontinue all work under said contract. * * * ” After the receipt of this letter, the plaintiff, against its protest, was forced to abandon the work and the question presented is whether the contract was legally canceled according to its terms.

It is claimed by the respondent that neither of these letters complies with the requirements of the contract authorizing its termination. So far as the notice given by the borough president is concerned, this claim is entirely without foundation, for while it purports to state his own opinion, and does not show clearly upon which of the grounds stated in the contract his action was based, nevertheless, it was an unequivocal notice to discontinue the work and that is all the contract required. As a matter of fact the only ground upon which the city seeks to justify the action taken is that the performance of the contract had been unnecessarily delayed and it is a much more serious question whether the letter of the chief engineer of sewers and highways were sufficient to warrant the action of the president.' He was empowered to cancel the contract for that reason, only in case “the Chief Engineer shall be of the [538]*538opinion and shall so certify in writing to the President, that the performance of the' contract is unnecessarily or unreasonably delayed.”

It seems that after the contract was made, the office of the chief engineer of the borough of the Bronx was abolished and his duties in part assumed by the chief engineer of sewers and highways. There can be little doubt, under the contract, the latter officer had the powers and duties of the former chief engineer of the borough. The difficulty is that the letter in question is not addressed to the president, but to the commissioner of public works, and it nowhere states that in the opinion of the chief engineer the performance of the contract had been unnecessarily or unreasonably delayed; on the contrary, the letter is to the effect, not that the plaintiff had unreasonably or unnecessarily delayed the work in the past, but that it then seemed unlikely that it would be able to proceed with due diligence in the future. Assuming, however, that the statements in the letter sufficiently indicated that it was the chief engineer’s opinion that the work had been unnecessarily delayed and that the letter was intended to reach the borough president through the proper channels, as it obviously did, I am, nevertheless, of the opinion the judgment should be affirmed. Under the terms of the contract it was for the chief engineer to determine whether the performance of the contract was unreasonably or unnecessarily delayed, and in the absence of fraud or bad faith his certificate to this effect was conclusive. All that was necessary was that he should exercise his honest judgment upon the facts, which he knew or ought to have known. The question whether his certificate did represent such a determination was submitted to the jury under a charge which clearly brought out this point and to which no exception was taken by the appellant, the court saying: “In considering this question I must repeat to you and you must remember that the parties have made the chief engineer their arbiter and that his certificate cannot be impeached without proof of fraud or bad faith. It cannot be impeached as fraudulent, and you have no right to hold it fraudulent merely because you yourself may believe that the performance was not unreasonably delayed.”

[539]*539There seems to be no dispute between the parties as to the law, but there is some question between them as to its application, the appellant’s claim being, as I understand it, that the certificate could b© impeached only by showing conscious dishonesty on the part of the chief engineer, so that evidence of the actual facts relating to the performance of the work was inadmissible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F. V. Smith Contracting Co. v. City of New York
167 A.D. 253 (Appellate Division of the Supreme Court of New York, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
157 A.D. 535, 142 N.Y.S. 743, 1913 N.Y. App. Div. LEXIS 6633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wakefield-construction-co-v-city-of-new-york-nyappdiv-1913.