Waits v. Orange Creek Turpentine Corp.

166 So. 449, 123 Fla. 31, 1936 Fla. LEXIS 934
CourtSupreme Court of Florida
DecidedFebruary 24, 1936
StatusPublished
Cited by10 cases

This text of 166 So. 449 (Waits v. Orange Creek Turpentine Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waits v. Orange Creek Turpentine Corp., 166 So. 449, 123 Fla. 31, 1936 Fla. LEXIS 934 (Fla. 1936).

Opinion

Terrell, J.

In December, 1932, Hayman’s Estate, Inc.; of Gainesville, Florida, leased to D. W. Matthews a large fract of land (about 16,000 acres) in Alachua and Putnam Counties. The lease was limited to the pine timber suitable for turpentine purposes and detailed the manner and specififications under, which it should be worked!. It ran for, ten years and Section 9 .provided for releasing any ,or all lands from its terms by giving sixty days notice and paying the amounts per cup face stated therein.

In March, 1933, appellee, Orange Creek Turpentine Corporation, by mfesnfe assignments came into possession of the lease. In September, 1933, Hayman’s Estate, Inc., executed. its deed of conveyance to appellant, W. Harvey Waits, describing.'the same lands as those described in- the lease to Matthews, said deed being subject to all, rights and privileges contained in the lease, o.f which -the vendee, Waits, had full knowledge.

On October 7, 1933, Waits and Hayman’s Estate, Inc., gave the lessee notice for release as required in Section 9, and 'on February 5, 1934, they gave it a. second notice requesting a release of the, lands described therein. Soon after the second notice and before the sixty, days expired Waits went into possession of the lands over the protest *33 of the lessee and proceeded to box, cup, and work for turpentine purposes a large part of the timber by placing about 23,000 cups on it and cutting some of it for cross ties, completely destroying it for turpentine purposes.

In August, 1934, Orange Creek Turpentine Corporation as plaintiff filed its bill of complaint in the Circuit Court of the Eighth Judicial Circuit praying that W. Harvey Waits as defendant be enjoined from trespassing upon the lands described in the lease and from cupping or otherwise working the timber on said lands for turpentine or other purposes. The bill also prayed that an account be stated between plaintiff and defendant and that defendant be required to pay plaintiff for all turpentine and gum he had gathered and removed from the leased premises contrary to the terms of the lease.

A temporary restraining order was granted, answer to the bill was filed, testimony was taken, and on final hearing the chancellor found the equities to be with the complainant and decreed the temporary restraining order to be permanent. He also found that Wait had unlawfully extracted from timber covered by the lease twenty-six units of Naval Stores products worth $36.00 per unit or $936.00, for which he entered judgment against Waits. On Petition for Rehearing the judgment was reduced to $795.60 and the final decree was reaffirmed. After the evidence was all in but before the final judgment was entered Waits petitioned to be permitted to file a supplemental answer but this request was denied.

From the final decree finding the equities to be with the complainant and from the decree refusing to permit defendant to file his amended or supplemental answer, and from the decree denying defendant’s Petition for Rehearing the present appeal was prosecuted.

*34 The primary questions brought here for determination turn on the interpretation of the lease, but the appellant and appellee are so widely at variance as to both the theory of the case and the questions presented we feel impelled to recant and treat such questions as we conceive to be immured in the belly of the pleadings and were adjudicated by the decrees of the chancellor.

Section 9 of the lease in question is as follows:

“It is further agreed between the parties hereto that should the Lessor, during the continuance of this lease, make a bona fide sale of any of the lands described above, or desire small tracts for colonization purposes or for agricultural purposes, and desire a release of the privileges herein granted to the timber thereon, then in that event and upon sixty (60) days’ written notice to the Lessee, specifying in particular the lands to be released, and upon payment to the Lessee of the amounts per cup face based upon the following schedule, the Lessee will, by appropriate instrument, release unto the Lessor the lands so specified:
“Faces which have been worked one year, or less, 10c per face;
“Faces which have been worked two years, 8c per face;
“Faces which have been worked three years, 6c per face;
“Faces which have been worked four years, 4c per face;
“Faces which have been worked five years, 2c per face;
“Faces which have been worked more than five years, and less than six years, 1c per face.”

As stated in a preceding paragraph, immediately - after conveying the title to Waits, Hayman’s Estate, Inc., gave the notice to Orange Creek Turpentine Corporation required in Section 9, demanding a release' of practically all the 16,000 acres described in the lease. On February 5, 1934, *35 a second notice was given the lessee demanding a release of the same lands described in the first notice, including with it a tender of $269.88 to cover the cost of cup faces under the schedule. The tender was refused. Imme-t diately after the second notice Waits entered and took possession of part of the lands and placed about 23,000 faces on the timber. August 8, 1934, appellee filed its bill of complaint, prayer to which and • relief granted have been previously detailed.

From this state of facts the first question may be posited as follows: Had Orange Creek Turpentine Corporation as holder of the lease from Waits’ grantor a right to restrain Waits from entering the lands described in the lease and working the timber for turpentine purposes before he (Waits) complied strictly with the terms of paragraph 9, it not being charged that appellee was in other respects in default?

Appellant in a very illuminating brief contends that the lease was one of mutual covenants, that it was the duty of appellee to disclose the amount due on cup faces under Section 9 when the notice was given, and failing to do so appellant had a right to enter and take possession of the premises.

The rule is' well settled that a landlord may under the terms of a lease or at its expiration re-enter and take possession of the leased premises and defend his possession against all persons but he is bound by the provisions of the lease for re-entry. The lease in this case was for ten years and prescribed the size and length of term trees might be worked. It also provided the manner in which they should be worked and allowed sixty days after its expiration for the lessee to remove tins, gutters, and cups placed on the trees. Section 9 provided how the lessor might re-enter *36 and take possession of the leased premises and whether or not he complied with that section is the very nub of this case.

It is shown that the timber constituted the main value of the land and the lessee, subject to the terms of the lease, had exclusive right to work it. Under Section 9 the lessor had a right to rescind the lease in case of a bona fide

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ENRIQUILLO EXPORT & IMPORT v. MBR Industries, Inc.
733 So. 2d 1124 (District Court of Appeal of Florida, 1999)
In re Sorrento's I, Inc.
195 B.R. 502 (M.D. Florida, 1996)
Cottingham v. State
656 So. 2d 597 (District Court of Appeal of Florida, 1995)
Auerbach v. McKinney
549 So. 2d 1022 (District Court of Appeal of Florida, 1989)
Tewksbury v. MJK, Inc. (In re MJK, Inc.)
18 B.R. 76 (S.D. Florida, 1982)
Hunt v. Hiland
366 So. 2d 42 (District Court of Appeal of Florida, 1978)
Ago
Florida Attorney General Reports, 1978
Carberry v. Foley
213 So. 2d 873 (Supreme Court of Florida, 1968)
Van Hoose v. Robbins
165 So. 2d 209 (District Court of Appeal of Florida, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
166 So. 449, 123 Fla. 31, 1936 Fla. LEXIS 934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waits-v-orange-creek-turpentine-corp-fla-1936.