Waite v. SAMSON DEVELOPMENT CO., INC.

348 N.W.2d 883, 217 Neb. 403, 1984 Neb. LEXIS 1079
CourtNebraska Supreme Court
DecidedMay 18, 1984
Docket83-485
StatusPublished
Cited by22 cases

This text of 348 N.W.2d 883 (Waite v. SAMSON DEVELOPMENT CO., INC.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waite v. SAMSON DEVELOPMENT CO., INC., 348 N.W.2d 883, 217 Neb. 403, 1984 Neb. LEXIS 1079 (Neb. 1984).

Opinion

McCown, J., Retired.

Plaintiff filed suit in the district court for Valley County against Samson Development Company, Inc. (Samson), and Inland Insurance Company, Inc. (Inland), to recover for work done on a construction *404 project. He was unable to obtain service upon Samson, and the action proceeded against Inland only. The trial court entered summary judgment in favor of Inland, and the plaintiff has appealed.

The petition alleged (1) that Samson entered into a contract with Friesen Building Corporation in September 1973, whereby Friesen was to complete construction of a low-rent housing project on property owned by Samson in Ord, Nebraska; (2) that Friesen entered into a labor and material payment bond with Inland in October 1973 to cover the performance of the contract and that plaintiff was within the class of persons covered by that bond; (3) that Friesen engaged plaintiff to do certain work as a subcontractor on the project; (4) that plaintiff completed the work and that nothing remained to be done under his contract; (5) that he furnished labor to the property from July 22 to October 14, 1974; (6) that the defendant promised to pay the plaintiff for the labor but that there remained due $4,541.40; (7) that on January 14, 1975, plaintiff filed a mechanic’s lien in the office of the register of deeds of Valley County, Nebraska; (8) that Samson and Friesen and the city housing authority were notified of the lien; (9) that an action by plaintiff against Friesen, filed March 20, 1975, resulted in a judgment against Friesen for $4,541.40, plus costs and interest from July 25, 1975, which judgment had not yet been satisfied; (10) that plaintiff had been notified by a June 30, 1975, letter that Samson had transferred the mechanic’s lien to an undertaking filed with the clerk of the district court, as per Neb. Rev. Stat. § 52-121 (Reissue 1978) (since repealed); and (11) that the action fell under Neb. Rev. Stat. § 44-359 (Reissue 1978) as to Inland and that an attorney fee would therefore be proper. The prayer of the petition reads:

WHEREFORE, Plaintiff prays for judgment against the Defendants, and each of them, in the amount of $4,541.40 plus interest from the 25th *405 day of July, 1975, and the costs of this action, including the $73.00 costs taxed by the District County Court of Valley County, Nebraska, and for an attorney’s fee to be taxed to the Defendant, Inland Insurance Company, as per Section 44-359, R.R.S., 1943, as amended; that the same be declared to be a statutory lien upon the fund presently on deposit with the office of the Clerk of the District Court of Valley County, Nebraska, as provided by Section 51-121 and 122, R.R.S., 1943, as amended, and for such other, further and different relief as to the Court may seem just and equitable in the premises.

Attached to the petition was a copy of the mechanic’s lien and a copy of the labor and material bond.

Inland admitted (1) the existence of the contract between Friesen and Samson; (2) the execution of the labor and material bond; (3) the oral contract between Friesen and plaintiff; and (4) that plaintiff filed a mechanic’s lien and that notice of the lien was given certain parties. Inland denied (1) that plaintiff was within the class of persons protected by the labor and material bond; (2) that the plaintiff’s work was completed; (3) that plaintiff furnished labor between July 22 to October 14, 1974; (4) that defendant agreed to pay plaintiff for labor and that $4,541.40 remained to be paid; (5) that the mechanic’s lien was a claim against the material bond; (6) that plaintiff had filed suit and obtained judgment against Friesen; (7) that plaintiff was notified of the transfer of the mechanic’s lien by letter from Samson dated June 30, 1975; and (8) that the case was a proper case for an attorney fee.

Inland further alleged that, since Samson had not been served and the surety on the transfer bond had not been joined, no proper action had been brought on the transfer bond within the time period of § 52-121 (since repealed) and that the benefits of the lien had been forfeited.

*406 Two particular sections of the labor and material bond are directly relevant.

1. A claimant is defined as one having a direct contract with the Principal or with a Subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.
2. The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.

Both parties moved for summary judgment. Inland argued as the bases for its motion that, according to the prayer of the petition, the plaintiff was suing on a mechanic’s lien transfer bond and that since Samson was not served and the surety on that transfer bond was not a party here and Inland was not the surety on the transfer bond, plaintiff had lost all of his lien rights.

Inland also maintained that since plaintiff had secured a personal judgment against Friesen, he could not maintain an equitable action here, because he had an adequate remedy at law.

The district court sustained Inland’s motion for summary judgment, and plaintiff has appealed.

Inland’s position in support of the summary judg *407 ment is that the plaintiff brought suit on the mechanic’s lien transfer bond, failed to get service on Samson, sued the wrong surety, and lost his lien rights as a result.

Inland argues in its brief that the suit on a labor and material bond is a law action, triable to a jury, and that the instant case is in equity. Inland claims that pleading the lien, attaching it, and pleading the notice to sue, when coupled with the language of the prayer, established that this was a suit on the transfer bond.

Inland cites language from previous cases that a pleading should be construed with reference to the general theory upon which it proceeds and should not be uncertain as to which of two or more theories is relied on. B. C. Christopher & Co. v. Danker, 196 Neb. 518, 244 N.W.2d 79 (1976), citing Fellers v. Howe, 106 Neb. 495, 184 N.W. 122 (1921).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Funk v. Lincoln-Lancaster Cty. Crime Stoppers
885 N.W.2d 1 (Nebraska Supreme Court, 2016)
Trieweiler Ex Rel. Varsity Investments, Inc. v. Sears
689 N.W.2d 807 (Nebraska Supreme Court, 2004)
In Re Interest of Rondell B.
546 N.W.2d 801 (Nebraska Supreme Court, 1996)
Weatherly v. Blue Cross Blue Shield Insurance
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
Weatherly v. BLUE CROSS BLUE SHIELD INS.
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
McCurry v. School District of Valley
496 N.W.2d 433 (Nebraska Supreme Court, 1993)
Bowman v. City of York
482 N.W.2d 537 (Nebraska Supreme Court, 1992)
St. Paul Fire & Marine Insurance v. Touche Ross & Co.
452 N.W.2d 746 (Nebraska Supreme Court, 1990)
City of Wood River v. Geer-Melkus Construction Co.
444 N.W.2d 305 (Nebraska Supreme Court, 1989)
Edward Bender & Sons v. Ericson Livestock Commission Co.
421 N.W.2d 766 (Nebraska Supreme Court, 1988)
Bard v. Cox Cable of Omaha, Inc.
416 N.W.2d 4 (Nebraska Supreme Court, 1987)
Slusarski v. County of Platte
416 N.W.2d 213 (Nebraska Supreme Court, 1987)
BERGMAN BY HARRE v. Anderson
411 N.W.2d 336 (Nebraska Supreme Court, 1987)
Parriott v. Drainage Dist. No. 6 of Peru
410 N.W.2d 97 (Nebraska Supreme Court, 1987)
Meyers v. Meyers
383 N.W.2d 784 (Nebraska Supreme Court, 1986)
Cass Const. Co., Inc. v. Brennan
382 N.W.2d 313 (Nebraska Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
348 N.W.2d 883, 217 Neb. 403, 1984 Neb. LEXIS 1079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waite-v-samson-development-co-inc-neb-1984.