Wagner v. St. Peter's Hospital

79 P. 1054, 32 Mont. 206, 1905 Mont. LEXIS 155
Montana Supreme Court·Decided March 13, 1905·No. No. 2,055·Published·Cited by 2 cases

Opinion

ME. COMMISSIONER CLAYBERG

prepared the opinion for the court. Appeal from a judgment.

The suit was to recover a balance alleged to be due on a contract for repairing and altering St. Peter’s Hospital, in the city of Helena. The full contract price was $4,748, of which the defendant had paid the sum of $4,348, but refused to pay the balance of $400, because it claimed that plaintiff had failed to fully complete his contract.

Plaintiff alleges that he entered into a subcontract with one Burley R. Streets to do the painting according to the specifications, and under the directions and to the satisfaction of the architects, and “which painting was thereafter done and performed by said Streets”; that thereafter Streets commenced [211] an action against plaintiff to recover the contract price- of $350; that appellant had full notice of such suit; that Streets recovered a judgment against plaintiff for $371.50 damages and $26.80 costs of suit; that by said judgment it was in effect decided and determined that Streets had fully and completely performed his said subcontract for painting according to the specifications for said work; tbat plaintiff bad paid sucb judgment; tbat be bad furnished all materials and performed all tbe work under and in pursuance of said contract, and bad duly completed tbe same, and in all respects fully performed all tbe conditions of said contract on bis part to be performed; wherefore be prayed judgment for $400, tbe balance due on tbe contract, and tbe further sum of $26.80 which Streets bad recovered against him for costs, together with interest. It is apparent from this complaint tbat plaintiff relied on tbe Streets judgment as being res adjudicata against appellant on tbe proposition tbat plaintiff bad fully performed bis contract.

Tbe appellant filed its answer, and denied tbat tbe judgment of Streets against tbe plaintiff was res adjudicata against it at all; and for further answer alleged, after setting forth a portion of tbe contract between it and plaintiff, tbat be failed to complete tbe painting specified in tbe contract and specifications, and tbat it bad demanded of him tbat be do sucb painting; tbat be bad refused, and tbat it bad caused tbe same to be completed at a cost of $305. Tbe answer further alleged tbat plaintiff bad entered into a subcontract with one Gust G. Minter for placing a roof on tbe building, at a price of $159.25, and tbat plaintiff failed to pay Minter any amount other than tbe sum of $110; tbat Minter filed a mechanic’s lien for tbe balance of $49.25, which tbe appellant paid in order to release tbe lien, and alleged tbat under tbe terms of tbe contract it was entitled to retain tbat amount out of any moneys due plaintiff on tbe contract. It was then alleged tbat there was only a balance of $44.75 due tbe plaintiff, which it was ready and willing to pay, and admitted that plaintiff was entitled to a judgment for tbat amount. In tbe replication a [212] portion of this new matter was denied, and a portion admitted. The cause came on for trial before a jury. After the presentation of plaintiffs testimony, counsel for defendant requested the court to instruct the jury to find a verdict for plaintiff for the sum of $44.75, which request was refused. Defendant offered no testimony. The court, upon request of plaintiff, instructed the jury to bring in a verdict for him for the sum of $400. Such verdict was rendered, and a judgment entered thereon, from which this appeal is taken.

The main question presented in the briefs of the respective counsel, and on their argument before this court, was as to the effect of the Streets judgment, counsel for appellant contending that said judgment was not res adjudicata against it for any purpose, and counsel for respondent contending that said judgment was res adjudícala as to the proposition that the contract between the appellant and respondent had been fully performed.

Counsel for respondent cite to the court and rely very strongly upon, the case of Hoppaugh v. McGrath, 53 N. J. L. 81, 21 Atl. 106, as being conclusive upon tbis proposition in tbeir favor. An examination of tbis decision leaves us of tbe opinion tbat it has no bearing upon tbe case at bar. In tbat case A, tbe owner of property, let a contract to B to erect certain buildings tbereon. B subcontracted witb 0 to do tbe masonry work. A sued B for breach of contract because of defective masonry work. B notified C of tbe pendency and object of tbis suit, and called on bim to come in and help defend it, wbicb C disregarded. A recovered a judgment. B then sued C for breach of contract because of defective masonry work,- and tbe court held tbat tbe judgment of A against B was conclusive against C. We are of tbe opinion tbat tbis decision is correct, on tbe principle tbat C, by failing to perform bis contract witb B, to B’s damage, and having notice of A’s suit, was liable therefor. A recovered a judgment against B for a breach of the contract between them. Tbis breach was caused by tbe act of C, and be was clearly [213] liable over to B for whatever damages A sustained because of such breach. The case comes clearly within the principles uniformly adopted and enforced in cases where a city is held liable for negligence occurring through the fault or act of some third person, and other cases of similar character. In such cases such third- party is always liable over, upon the principle that, except for his act, no liability whatever would have existed. The same court which decided the Hoppaugh Case afterward held that a judgment procured by a subcontractor against the principal contractor, for which the subcontractor sought to enforce a lien against the owner of the premises, was not conclusive upon such owner, and says: “Nor do we think the owner is bound by the fact that a judgment has been recovered against the contractor by the claimant. The recovery of such judgment is evidential of the amount due upon his claim, and, without other proof, may be conclusive. But this does not prevent the owner from showing that the claim is' excessive, and the judgment thereon is likewise so, or that it is fraudulent.” (Taylor v. Wahl, 69 N. J. L. 471, 55 Atl. 40.) Counsel for respondent says that this opinion does not refer to the Hoppaugh Case, and therefore does not overrule it. There was no occasion to refer to that case or overrule it. These decisions are entirely consistent with each other, and, in our judgment, properly announce the law.

Free access — add to your briefcase to read the full text and ask questions with AI

Wagner v. St. Peter's Hospital, 79 P. 1054, 32 Mont. 206, 1905 Mont. LEXIS 155 (Mo. 1905).

79 P. 1054 (Wagner v. St. Peter's Hospital) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cascade Electric Co. v. Associated Creditors, Inc.
224 P.2d 146 (Montana Supreme Court, 1950)
Eberle v. Drennan
1912 OK 795 (Supreme Court of Oklahoma, 1912)