Wagner v. MSE Technology Applications, Inc.

2016 MT 215, 383 P.3d 727, 384 Mont. 436, 2016 Mont. LEXIS 790
CourtMontana Supreme Court
DecidedAugust 30, 2016
DocketDA 15-0448
StatusPublished
Cited by6 cases

This text of 2016 MT 215 (Wagner v. MSE Technology Applications, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wagner v. MSE Technology Applications, Inc., 2016 MT 215, 383 P.3d 727, 384 Mont. 436, 2016 Mont. LEXIS 790 (Mo. 2016).

Opinion

CHIEF JUSTICE McGRATH

delivered the Opinion of the Court.

¶1 Chris Wagner appeals from the District Court’s dismissal of his claims at trial pursuant to M. R. Civ. P. 50. We affirm in part and reverse in part.

¶2 We restate the issues on appeal as follows:

Issue 1: Did the District Court err in dismissing Wagner’s intentional interference claims against all defendants and granting them judgment as a matter of law pursuant to M. R. Civ. P. 50(a)? Issue 2: Did the District Court err in dismissing Wagner’s claims by granting Shea Realtors summary judgment, and judgment as a matter of law pursuant to M. R. Civ. P. 50(a)?

FACTUAL AND PROCEDURAL BACKGROUND

¶3 In 2009 Wagner sought to buy land in Butte to establish a commercial nursery. He hired Shea Realtors as his agent in purchasing approximately sixty acres of land from the Montana Tech Foundation. Shea became the agent of both Wagner and the Foundation, and in November 2009 Wagner and the Foundation entered a buy-sell agreement under which Wagner would purchase the land. Shea agreed to not engage in negotiations with any other persons or to show the property while the buy-sell agreement was in place. The parties agreed to close the purchase on January 8, 2010.

¶4 Wagner inserted four contingencies into the buy-sell agreement with the Foundation. Those were that he would not be required to bore underneath adjacent railroad tracks for utility installation; that he not be required to use city water for irrigation; that he could subdivide the property; and that his business would meet zoning requirements. There are numerous references in this case to an “easement” condition, but no such condition appears on the face of the buy-sell.

¶5 In December 2009 Wagner hired Gaston Engineering to advise him about the feasibility of subdividing the property and selling the majority of it to others. Gaston identified access as an issue and concluded that the only feasible access was an existing road that was *438 on adjacent property owned by MSE. A Gaston representative spoke to MSE Vice President Tretheway about securing an easement for use of the existing road. Tretheway told Gaston that MSE “would not stand in the way” of Wagner’s purchase and would not “throw monkey wrenches” into the process. After additional investigation Gaston advised Wagner that it was feasible for him to subdivide the land into six parcels and to sell five of them.

¶6 MSE requested that Gaston provide more information about Wagner’s plans for the land. On January 5, 2010, Gaston responded with a simple “conceptual plan” that showed possible boundaries for dividing the land into six lots. The Foundation agreed to extend the closing date to January 29, 2010. Wagner waited to hear from MSE about an easement and testified that his several attempts to contact MSE about this were unsuccessful. The Foundation agreed to extend the closing date again, to February 15, 2010.

¶7 On January 29, 2010, representatives of the Butte Local Development Corporation (BLDC), the Foundation and MSE met to discuss the property. During the meeting, Mr. Kebe from MSE called Shea to ask whether Wagner would be interested in purchasing a forty-seven-acre parcel owned by MSE adjacent to the land he was trying to buy from the Foundation. At Shea’s request Wagner visited the property and then told Shea that he was not interested in it. While the forty-seven-acre parcel contained the existing road that Wagner needed for access to the sixty acres, Wagner never knew this and never obtained an easement from MSE.

¶8 On February 9, 2010, the same persons who were at the January 29 meeting met again to work out an agreement for BLDC to buy the sixty acres from the Foundation and for MSE to provide the necessary easements. On or after February 11, 2010, Shea began working to implement BLDC’s purchase of the sixty acres from the Foundation. Wagner knew nothing about the January 29 or February 9 meetings and knew nothing about Shea’s involvement. Shea claimed at trial that on or about February 11 Wagner told him he was no longer interested in buying the sixty acres. Wagner denied saying that.

¶9 The February 15, 2010 closing date on the Wagner-Foundation buy-sell agreement passed and Wagner did not close. On February 26, 2010, BLDC purchased the land from the Foundation for the same price contained in the buy-sell with Wagner, and MSE granted easements over its land to BLDC.

¶10 In July 2010 Wagner sued the MSE entities and BLDC, contending that they had improperly interfered with his attempt to purchase the sixty acres from the Foundation. Wagner later amended *439 the complaint to add Shea Realtors as a defendant. The case stagnated and Wagner could not get the District Court to issue a scheduling order or to rule on pending motions. In May 2014 Wagner applied to this Court for a writ of supervisory control. This Court granted relief, ordering the District Court to rule on pending motions and to issue a scheduling order, including a trial date. After the District Court’s rulings on motions and two more amendments to the complaint, Wagner’s claims were distilled to intentional interference with his prospective economic advantage against all defendants; constructive fraud against Shea and MSE; professional negligence against Shea; breach of contract against Shea; and breach of the covenant of good faith and fair dealing against Shea. Prior to trial the District Court granted partial summary judgment against Wagner by dismissing the professional negligence claim against Shea because Wagner did not have an expert to establish the standard of care for a realtor.

¶11 The case went to jury trial on the remaining claims in June 2015, and Wagner presented his case-in-chief over four days. Witnesses who testified included defendant Shea; Mike Johnson, former president of the Foundation; Jeremy Olson from Gaston Engineering; Mr. Tretheway, former vice president of MSE; Jim Smitham, executive director of BLDC; William Kebe, a member of the board of directors of both MSE and BLDC; and Chris Wagner. At the close of Wagner’s case the District Court granted the defendants’ M. R. Civ. P. 50 motions for judgment as a matter of law in their favor.

¶12 The District Court concluded that Wagner had not presented sufficient evidence to allow the jury to reasonably find facts that would support a verdict against any of the defendants. The District Court found that Wagner failed to present any evidence that any of the defendants prevented him from purchasing the land from the Foundation. To the contrary the District Court noted Wagner’s own testimony that he was free to purchase the Foundation land up to the final closing date (February 15,2010), and that none of the defendants prohibited him from doing so. The District Court determined that Wagner presented insufficient evidence that any of the defendants intentionally interfered with his prospective economic advantage and that the claims for tortious interference must fail. 1

*440

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miske v. DNRC
2023 MT 241 (Montana Supreme Court, 2023)
Greene v. McDowell
2023 MT 49N (Montana Supreme Court, 2023)
Young v. Era Advantage
2022 MT 138 (Montana Supreme Court, 2022)
Odom v. Bank of N.Y. Mellon
2020 MT 58N (Montana Supreme Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 215, 383 P.3d 727, 384 Mont. 436, 2016 Mont. LEXIS 790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wagner-v-mse-technology-applications-inc-mont-2016.