KERN, Associate Judge:
Two issues are before us on this appeal: (1) the priority of mechanics’ liens held by appellants Waco Scaffold & Shoring Co. [Waco], ITT-Grinnell [ITT] and Maryland Steel Erectors, Inc. [Maryland Steel] as against a construction lender’s deed of trust securing a loan made to the predecessor of appellee 425 Eye Street Associates [Associates], and (2) the propriety of the trial court’s judgment in favor of Associates on Waco’s claim for damages in
quantum memit.
The property in issue is Lot 57, Square 516 in the District of Columbia, commonly known as 425 Eye Street N.W. The trial court’s findings of fact made in response to appellee’s motion to dismiss indicate that on October 8, 1971, a deed of trust was recorded as to this property to secure a promissory note for $9.4 million held by Girard Bank and Security National Bank the construction money lenders.
Appellants Maryland Steel, ITT and Waco, filed notices of intent to hold a lien on the property
on September 7, 1972, October 4, 1972, and March 15, 1973, respectively. The trial court found that sometime before these notices were filed, some $5,458,984 had been advanced by the construction money lenders to appellee or its predecessor in interest.
Appellants brought suit
to enforce their liens in September 1973, arguing that mechanics’ liens take priority over all other encumbrances except purchase-money mortgages or deeds of trust, and that mechanics’ liens attach at the commencement of the work.
See Deland v. Wagner,
62 App.D.C. 54, 64 F.2d 552 (1933); D.C.Code 1973, § 38-109. Appellant Maryland Steel alleged that it commenced work on the property in August 1971, before the deed of trust securing the construction money lender’s loan was recorded, while appellants ITT and Waco claimed they commenced work in February 1972, after
recordation of the deed of trust.
The trial court found as a fact that each appellant had commenced work before filing its notice of lien.
The property in question was sold at a foreclosure sale on August 26, 1974, for $4,630,983, an amount less than the total amount advanced by the construction money lender. Appellee moved to dismiss on September 16, 1974, on the ground that the mechanics’ liens which were the subject of the suit had been eliminated by the foreclosure sale at a price less than the total advances made prior to the commencement of work. This motion was granted on December 3, 1974, and appellants brought this appeal.
The issue before us, then, is the construction of D.C.Code 1973, § 38-109, which establishes the priorities accorded to various liens and encumbrances. Specifically, we must determine the relative priority of interests between a construction money lender who records its deed of trust to secure a construction loan
after
the commencement of work on the property by construction companies, and the construction company-mechanics’ lienor who commences work
prior to
the construction lender’s recordation but files a notice of intent to hold a lien
after
the lender has advanced money.
The relevant statute, § 38-109, provides in part:
The [mechanics’] lien hereby given shall be preferred to all . deeds of trusts, liens, and incumbrances which attach upon the building or ground affected by said lien subsequently to the commencement of the work upon the building, . . . except that nothing herein shall affect the priority of a mortgage or deed of trust given to secure the purchase money for the land, if the same be recorded within ten days from the date of the acknowledgment thereof. When a mortgage or deed of trust of real estate securing advances thereafter to be made for the purpose of erecting buildings and improvements thereon is given, . . . the [mechanics’] lien hereinbefore authorized shall have priority to all advances made after the filing of said notices of lien, and the lien shall attach to the right, title, and interest of the owner in said building and land to the extent of all advances which shall have become due after the filing of such notice of such lien
This statute was analyzed in our opinion in
Guardian Federal Savings & Loan Association v. Suskind,
D.C.App., 265 A.2d 295 (1970), a case that dealt with the priority of a purchase-money deed of trust within the context of a supplementary agreement. We stated there at 297:
In the absence of the subordination agreement, D.C.Code 1967, § 38-109 would establish the following priorities to the foreclosure sale proceeds: first, the purchase-money deed of trust; sec
ond, the construction loan deed of trust to the extent of disbursements prior to the filing date of the mechanics’ liens; third, the mechanics’ liens; and finally, the balance of the construction loan. [Footnote omitted.]
We agree that this is the proper interpretation of the statute at issue here, for it comports with the plain meaning of the words used. This construction also supplies the simplest resolution to the problem of the two competing sets of priorities created in the statute by treating the second set of priorities as a modification of the priorities described generally in the first sentence. If Congress had intended that the second set of priorities take effect only if no construction work had commenced, it would have included this condition in the statute. Since it did not, we must construe the statute as a whole and reconcile the two provisions.
See
2 A Sutherland, Statutory Construction § 46.05 (4th ed. 1973). This is apparently the view taken by the trial court, and under the circumstances his dismissal of appellants’ claims was correct.
The three appellants here all filed their notices of intent to hold a lien
after
the construction money lender had received and recorded a deed of trust securing its loan and had advanced significant sums,
viz.,
$5,458,984, for the construction of the building. Consequently the claims of the construction money lenders up to the amount of the advances made before appellants filed notices took priority over appellants’ mechanics’ liens. The property in issue was purchased at the foreclosure sale by Union-America Mortgage and Equity Trust, successor to Girard Bank and Security National Bank and the holder of the promissory note secured by the deed of trust. Since the purchase price of the property was less than the amount of advances made under the loan, which constituted a superior interest, appellants’ liens were extinguished and their claims were properly dismissed.
See Rosslyn Steel & Cement Co. v. Etchison,
61 App.D.C. 43, 57 F.2d 409,
cert. denied,
287 U.S. 614, 53 S. Ct. 17, 77 L.Ed.
Free access — add to your briefcase to read the full text and ask questions with AI
KERN, Associate Judge:
Two issues are before us on this appeal: (1) the priority of mechanics’ liens held by appellants Waco Scaffold & Shoring Co. [Waco], ITT-Grinnell [ITT] and Maryland Steel Erectors, Inc. [Maryland Steel] as against a construction lender’s deed of trust securing a loan made to the predecessor of appellee 425 Eye Street Associates [Associates], and (2) the propriety of the trial court’s judgment in favor of Associates on Waco’s claim for damages in
quantum memit.
The property in issue is Lot 57, Square 516 in the District of Columbia, commonly known as 425 Eye Street N.W. The trial court’s findings of fact made in response to appellee’s motion to dismiss indicate that on October 8, 1971, a deed of trust was recorded as to this property to secure a promissory note for $9.4 million held by Girard Bank and Security National Bank the construction money lenders.
Appellants Maryland Steel, ITT and Waco, filed notices of intent to hold a lien on the property
on September 7, 1972, October 4, 1972, and March 15, 1973, respectively. The trial court found that sometime before these notices were filed, some $5,458,984 had been advanced by the construction money lenders to appellee or its predecessor in interest.
Appellants brought suit
to enforce their liens in September 1973, arguing that mechanics’ liens take priority over all other encumbrances except purchase-money mortgages or deeds of trust, and that mechanics’ liens attach at the commencement of the work.
See Deland v. Wagner,
62 App.D.C. 54, 64 F.2d 552 (1933); D.C.Code 1973, § 38-109. Appellant Maryland Steel alleged that it commenced work on the property in August 1971, before the deed of trust securing the construction money lender’s loan was recorded, while appellants ITT and Waco claimed they commenced work in February 1972, after
recordation of the deed of trust.
The trial court found as a fact that each appellant had commenced work before filing its notice of lien.
The property in question was sold at a foreclosure sale on August 26, 1974, for $4,630,983, an amount less than the total amount advanced by the construction money lender. Appellee moved to dismiss on September 16, 1974, on the ground that the mechanics’ liens which were the subject of the suit had been eliminated by the foreclosure sale at a price less than the total advances made prior to the commencement of work. This motion was granted on December 3, 1974, and appellants brought this appeal.
The issue before us, then, is the construction of D.C.Code 1973, § 38-109, which establishes the priorities accorded to various liens and encumbrances. Specifically, we must determine the relative priority of interests between a construction money lender who records its deed of trust to secure a construction loan
after
the commencement of work on the property by construction companies, and the construction company-mechanics’ lienor who commences work
prior to
the construction lender’s recordation but files a notice of intent to hold a lien
after
the lender has advanced money.
The relevant statute, § 38-109, provides in part:
The [mechanics’] lien hereby given shall be preferred to all . deeds of trusts, liens, and incumbrances which attach upon the building or ground affected by said lien subsequently to the commencement of the work upon the building, . . . except that nothing herein shall affect the priority of a mortgage or deed of trust given to secure the purchase money for the land, if the same be recorded within ten days from the date of the acknowledgment thereof. When a mortgage or deed of trust of real estate securing advances thereafter to be made for the purpose of erecting buildings and improvements thereon is given, . . . the [mechanics’] lien hereinbefore authorized shall have priority to all advances made after the filing of said notices of lien, and the lien shall attach to the right, title, and interest of the owner in said building and land to the extent of all advances which shall have become due after the filing of such notice of such lien
This statute was analyzed in our opinion in
Guardian Federal Savings & Loan Association v. Suskind,
D.C.App., 265 A.2d 295 (1970), a case that dealt with the priority of a purchase-money deed of trust within the context of a supplementary agreement. We stated there at 297:
In the absence of the subordination agreement, D.C.Code 1967, § 38-109 would establish the following priorities to the foreclosure sale proceeds: first, the purchase-money deed of trust; sec
ond, the construction loan deed of trust to the extent of disbursements prior to the filing date of the mechanics’ liens; third, the mechanics’ liens; and finally, the balance of the construction loan. [Footnote omitted.]
We agree that this is the proper interpretation of the statute at issue here, for it comports with the plain meaning of the words used. This construction also supplies the simplest resolution to the problem of the two competing sets of priorities created in the statute by treating the second set of priorities as a modification of the priorities described generally in the first sentence. If Congress had intended that the second set of priorities take effect only if no construction work had commenced, it would have included this condition in the statute. Since it did not, we must construe the statute as a whole and reconcile the two provisions.
See
2 A Sutherland, Statutory Construction § 46.05 (4th ed. 1973). This is apparently the view taken by the trial court, and under the circumstances his dismissal of appellants’ claims was correct.
The three appellants here all filed their notices of intent to hold a lien
after
the construction money lender had received and recorded a deed of trust securing its loan and had advanced significant sums,
viz.,
$5,458,984, for the construction of the building. Consequently the claims of the construction money lenders up to the amount of the advances made before appellants filed notices took priority over appellants’ mechanics’ liens. The property in issue was purchased at the foreclosure sale by Union-America Mortgage and Equity Trust, successor to Girard Bank and Security National Bank and the holder of the promissory note secured by the deed of trust. Since the purchase price of the property was less than the amount of advances made under the loan, which constituted a superior interest, appellants’ liens were extinguished and their claims were properly dismissed.
See Rosslyn Steel & Cement Co. v. Etchison,
61 App.D.C. 43, 57 F.2d 409,
cert. denied,
287 U.S. 614, 53 S. Ct. 17, 77 L.Ed. 534 (1932).
Appellant Waco also argues that the trial court committed error in granting judgment in favor of appellee Associates on Waco’s claim for damages in
quantum meruit.
After considering the evidence presented at a hearing on this claim, the trial court found that appellant had not shown any negotiations between the parties or any circumstances suggesting “either a contractual or other implicit understanding by the parties.” Accordingly, the court concluded that appellant “failed to establish by convincing proof a basis for relief.”
There are four elements of a claim in
quantum meruit:
(1) valuable services being rendered;
(2) for the person sought to be charged;
(3) which services were accepted by the person sought to be charged, used and enjoyed by him or her; and (4) under suph circumstances as reasonably notified the person sought to be charged that the plaintiff, in performing such services, expected to be paid by him or her.
[In Re Rich,
D.C.App., 337 A.2d 764, 766 (1975).]
The trial court’s order indicates that there was an inadequate showing on the fourth element of Waco’s claim,
viz.,
appellee’s knowledge of appellant’s expectation of payment, since the court found there was no showing of an understanding between the parties. Given the scarcity of testimo
ny in support of this claim
we cannot conclude that the trial court’s ruling was “plainly wrong,” and consequently we must affirm. D.C.Code 1973, § 17-305(a).
So ordered.