Wacker v. Essex

119 N.E. 466, 67 Ind. App. 584, 1918 Ind. App. LEXIS 183
CourtIndiana Court of Appeals
DecidedMay 3, 1918
DocketNo. 9,542
StatusPublished
Cited by4 cases

This text of 119 N.E. 466 (Wacker v. Essex) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wacker v. Essex, 119 N.E. 466, 67 Ind. App. 584, 1918 Ind. App. LEXIS 183 (Ind. Ct. App. 1918).

Opinion

Hottel, J.

The facts which gave rise to the litigation in which the judgment was rendered from which this appeal is prosecuted are in substance as follows: On February 8,1913, the appellees, S. Herbert Essex and Lenora Essex, hereinafter referred to as “E and E,” obtained a ninety-nine year lease on ground fronting seventy-four feet on Meridian street and forty-two feet and eight inches on Louisiana street, in the city of Indianapolis. On the same day E and E subleased said ground to the Meridian Hotel Company, a corporation, for a period of twenty-five years from September 1, 1913, with a condition that a six-story hotel building would be erected thereon, ready for occupancy by August. 21, 1913, for which said hotel company agreed to pay a rental of $1,000 a month. Charles E. Bacon, an architect of Indianapolis, was employed by E and E to draw the plans and specifications and superintend the construction of said building. No general contract was made or let by E and E for the erection of said hotel, but they contracted with various persons, firms and corporations for the material and work that entered into its construction.

The first of these contracts was one between E and E and this appellant, Charles Waeker, purporting to have been made April 15, 1913, for the furnishing of all the material and labor for the erection and construction of all the concrete work, both plain and reinforced, required in the erection of said building. Afterwards other contracts were let for the furnish[586]*586ing of material and labor necessary in the construction of said building, which, for the purposes of this appeal, need not be set out.

It is sufficient to say that most of said contractors filed notices of mechanics’ liens on said building for the respective balances claimed to be due them for labor and material furnished and used therein under their respective contracts made with E and E. The Security Trust Company of Indianapolis, trustee, held a first and! second mortgage on the ninety-nine year leasehold of E and E for approximately $80,000.

' The building was not ready for occupancy until in January, 1914, and E and E’s rentals did not begin until February 1,1914. On March 2,1914, Mr. Bacon, the architect, gave to appellant Wacker a final certificate for $2,275.20, and on .the same day issued another certificate for $608.30 for extras. These certificates were presented to appellee Herbert Essex for payment, and he refused to pay them.

Appellant also filed notice of a mechanic’s lien on said building, and in a proceeding instituted by Herbert, M. Woolen and Harry C. Callón, partners, he and other lienholders were made defendants. Cross-complaints were filed by such lienholders, and these cases drifted along until there was an application for a receiver for the hotel property. By agreement of the parties, the Security Trust Company agreed to put up an additional $10,000 to pay judgments and cover the outstanding claims, and the'liens on said real estate were transferred to said fund. In said proceedings all said claimants and lienholders have been compromised and settled with, except appellant and the appellee the D. Y. Reedy Elevator Company.

[587]*587The appellant, by way of cross-complaint in said, proceedings, sought to recover against E and E on his said contract the amount due as shown by the two certificates above referred to as issued to him by said architect, and also a further item of $75 for water rent paid by him for water furnished in the erection of said building. He also sought to foreclose a mechanic’s lien.

This cross-complaint was answered by a general denial and by three affirmative paragraphs. The second paragraph, designated a set-off, sets out the terms of the contract with reference to the time for the completing of said work, and alleges a failure on appellant’s part to so complete it and damages resulting therefrom, viz., damages resulting from loss of rental for sixty-two days, aggregating $2,066.46. This paragraph also alleges that E and E, on account of such delay, were required to pay said hotel company, as damages resulting to said company from 142 days’ delay in the completion of said work, $1,600, and alleges that three-sevenths of said delay was caused by appellant, and that he should pay appellees as damages the further sum of $685, making a total of $2,751.46 asked in said paragraph by way of set-off.

The third paragraph sets pp certain defects 0in the work and material furnished by appellant, and asks, on account thereof, $150 damages by way of set-off.

The fourth paragraph is designated a counterclaim, and it sets out in detail wherein said work was not done in accord with the plans and specifications and wherein it..is faulty and defective, and alleges the amount of the damages resulting from each item of such faulty and defective work; that the total dam[588]*588age resulting therefrom is $3,350, and asks for judgment accordingly.

To these answers the appellant filed a reply in general denial and a special reply to said second paragraph of answer, in which he alleges that the delay in the completion of his part of said building was due to the acts, orders and conduct, particularly set out, of E and E and the architect, and by bad weather and strikes of his employes, over which he had no control and for which he was not responsible; that he did his work as fast as he was permitted to do it by 'E and E. It is also alleged that E and E waived the provisions of article 7 of said contract, hereinafter set out, and assured appellant that the several delays set out in said reply, and causes as therein set out, would in each instance be added to the original time given for the completion of said work, without any written request for such extension.

Upon these issues a trial by the court resulted in a general finding in favor of appellant on his cross-complaint against S. Herbert Essex in the sum of $2,774.70, and a finding for said Essex on the counterclaim of E and E in the sum of $4,210.57. The court further found for Lenora Essex on appellant’s cross-complaint, and that she take nothing by her counterclaim. Upon this finding the court rendered judgment that S. Herbert Essex recover of appellant on his counter-claim $1,435.87 and his costs, and that Lenora Essex recover her costs.

A motion for new trial filed by appellant was overruled. This ruling is assigned as error, and in his brief, under the heading “Errors rejied upon for reversal,” the appellant says that he relies on his first assignment, viz.: “The court erred in overruling ap[589]*589pellant’s motion for a new trial.” This statement of the error relied on is immediately followed by a subhead as follows: “(a) The decision of the court is contrary to law.”

This statement is followed with the heading “Propositions and Authorities,” under which eight propositions are stated.

The motion for new trial contains twenty-five separate grounds or reasons, but neither of appellant’s propositions is specifically addressed to either of said grounds, except as above indicated.

It is insisted by appellees, in effect, that appellant, by said brief, has eliminated ad grounds of his motion for new trial, except that challenging the decision of the trial court as being contrary to law, and that his propositions of law, if they can be held to apply to either of the grounds of such motion, should at least be limited to the one ground. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips v. GREEN STREET CORP.
237 N.E.2d 590 (Indiana Court of Appeals, 1968)
Huntington Post, American Legion v. Arnold
109 N.E.2d 98 (Indiana Court of Appeals, 1952)
Van Dyck Heating & Plumbing Co. v. Central Iowa Building Co.
205 N.W. 650 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
119 N.E. 466, 67 Ind. App. 584, 1918 Ind. App. LEXIS 183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wacker-v-essex-indctapp-1918.