W & W Contractors, Inc. v. Tunica County Airport Commission

881 So. 2d 358, 2004 Miss. App. LEXIS 858, 2004 WL 1879503
CourtCourt of Appeals of Mississippi
DecidedAugust 24, 2004
DocketNo. 2003-CA-01801-COA
StatusPublished
Cited by1 cases

This text of 881 So. 2d 358 (W & W Contractors, Inc. v. Tunica County Airport Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W & W Contractors, Inc. v. Tunica County Airport Commission, 881 So. 2d 358, 2004 Miss. App. LEXIS 858, 2004 WL 1879503 (Mich. Ct. App. 2004).

Opinion

MYERS, J.,

for the Court.

¶ 1. W & W Contractors, Inc. (W&W) appeals from an order of the Circuit Court of Tunica County, Mississippi which affirmed the decision of the Tunica County Airport Commission (Commission) to award a contract to Cobb Land Development (Cobb). On appeal, W&W asks this Court to reverse the order of the circuit court and void the contract between the Commission and Cobb and award W&W monetary damages of the difference between its bid and Cobb’s bid for the project. W&W raises three issues on appeal for this Court’s consideration.

ISSUES PRESENTED

I. Whether the Commission’s decision to award the bid to Cobb was arbitrary and capricious because the Commission completely disregarded contractual provisions governing the form and substance of responsive bids and authorized post bid modifications by Cobb?

II. Whether the Commission’s award to Cobb was an action beyond the agency’s scope or powers because it did not have legal authority to amend the contract after sealed bids were submitted?

III. Whether the Commission’s award of the contract to Cobb was contrary to Mississippi law because Cobb failed to possess a Certificate of Responsibility for one or more major classifications and therefore did not comply with regulations regarding certification?

STATEMENT OF FACTS

¶ 2. In August 2000, the Commission advertised for sealed bids in connection with a site preparation contract. W&W and Cobb along with eight other contractors submitted bids for the project. The last paragraph of the “Notice to Contractors” contained the following provision:

The award, if made, will be made to the party submitting the bid deemed most favorable to the TUNICA COUNTY AIRPORT COMMISSION at the time the conditions are stipulated. The TU-NICA COUNTY AIRPORT COMMISSION reserves the right to reject any and all bids and to waive any informalities or irregularities in the bids received.

¶ 3. On September 8, 2000, the Commission received bids. W&W submitted a bid that totaled $4,319,279.20. Cobb did not state a figure for the total base bid. After all bids were taken under advise[361]*361ment by the Commission, several problems arose with Cobb’s bid.

¶4. The first issue which arose concerned the unit price for fencing which was pay item #33 on the bid sheet. Cobb provided the price of “eight hundred seventy-five” written in words but had “8.75” written in numbers. The second issue concerned the Disadvantage Business Enterprise (DBE) Plan requirements of the Commission. Cobb failed to list qualified DBEs to perform 9.15% of the total project as required by Commission guidelines. Also, Cobb listed itself as a DBE when in fact it was not. On October 2, 2000, Cobb amended its bid materials and complied with the Commission’s requirements by submitting a list of certified DBEs it planned to use as subcontractors.

¶ 5. Due to the irregularities in Cobb’s bid, the Commission sought an opinion from the Attorney General. On October 6, 2000, the Attorney General issued his official opinion to the Commission which states in pertinent part: “However, if the Commission determines that Cobb’s actual intended bid is, in fact, evident on the face of the bid, and the Commission finds that any irregularity does not give Cobb an advantage over other bidders, then the Commission may waive the irregularity and accept the Cobb bid.” Considering the Attorney General’s opinion, on October 16, 2000, the Commission accepted Cobb’s bid and awarded it the contract. W & W appealed the decision of the Commission to the Circuit Court of Tunica County on October 24, 2000. A hearing was conducted on April 29, 2003, and the circuit court affirmed the decision of the Commission on July 28, 2003. W & W timely perfected its appeal to this Court following the order.

LEGAL ANALYSIS

¶ 6. W & W argues that the decision of the Commission should be reversed because the decision was arbitrary and capricious, and the Commission acted beyond its powers and violated statutory provisions and W & W’s rights. We apply the same standard of review to the decision of the-Commission as we apply to our review of administrative agency decisions. Falco Lime Inc. v. Mayor and Aldermen of the City of Vicksburg, 836 So.2d 711, 721 (¶ 42) (Miss.2002). We must uphold the decision unless it was “unsupported by substantial evidence; was arbitrary or capricious; was beyond the agency’s scope or powers; or violated the constitutional or statutory rights of the aggrieved party.” Id. (quoting Bd. of Law Enforcement Officers Standards & Training v. Butler, 672 So.2d 1196, 1199 (Miss.1996)).

I. WHETHER THE COMMISSION’S DECISION TO AWARD THE BID TO COBB WAS ARBITRARY AND CAPRICIOUS BECAUSE THE COMMISSION COMPLETELY DISREGARDED CONTRACTUAL PROVISIONS GOVERNING THE FORM AND SUBSTANCE OF RESPONSIVE BIDS AND AUTHORIZED POST BID MODIFICATIONS BY COBB?

¶ 7. As its first point of error, W & W cites two instances where the Commission allowed Cobb to modify its bid post submission, the unit price for fencing and the DBE requirement. As evinced from the bid sheet, Cobb did not submit a total base bid. The column was left blank. All other bidders included a total. There was also a discrepancy in Cobb’s bid concerning the unit price for security fencing. In words, Cobb provided the price as “eight hundred seventy-five” but in numbers Cobb provided “8.75.” The bidders were provided requirements of the project prior to bidding and one specification read, “Unit prices are lump sum prices provided in both words and figures. In case of discrepancy, the amount shown in words [362]*362shall govern.” W & W argues that using Cobb’s amounts as stated in words, Cobb’s total bid would have been- $7,223,827 and not the lowest bid.

¶ 8. Upon opening the bids, the Commission discovered the discrepancy in Cobb’s bid. ' Based on this, the Commission sought an opinion of the Attorney General on whether the' irregularity could be waived and the contract awarded to Cobb based on the bid. The Attorney General informed the Commission that if it determined that the actual intended bid was evident from the face of the document and that the irregularity did not give Cobb an advantage over other bidders, the Commission could waive the irregularity and accept Cobb’s bid. The Commission considered the opinion and compared Cobb’s figure to those submitted by other bidders. If the Commission interpreted the unit price in words, the price would be over $800 a foot more than any other bidder. The numerical value, however, placed Cobb in line with other bidders on the price for fencing.

¶ 9. The Commission waived the irregularity and interpreted Cobb’s unit price for fencing as $8.75 per foot. W & W labels this action by the Commission an erroneous post-submission modification. W & W cites the case of Hemphill v. City of Laurel, 760 So.2d 720 (Miss.2000), as authority on this point. The Commission distinguishes Hemphill and argues that it simply interpreted the bid in light of its most logical meaning and fulfilled its obligations to the taxpayers of Tunica County by awarding the contract to the lowest bidder.

¶ 10. • In Hemphill, the supreme court stated that the city had overstepped its authority by allowing a bidder to amend its bid causing an increase after the bids were open.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
881 So. 2d 358, 2004 Miss. App. LEXIS 858, 2004 WL 1879503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-w-contractors-inc-v-tunica-county-airport-commission-missctapp-2004.