W. Va. Dept. of Highways v. Arbogast

201 S.E.2d 492, 157 W. Va. 359, 1973 W. Va. LEXIS 227
CourtWest Virginia Supreme Court
DecidedDecember 18, 1973
DocketNo. 13400; No. 13401
StatusPublished
Cited by2 cases

This text of 201 S.E.2d 492 (W. Va. Dept. of Highways v. Arbogast) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. Va. Dept. of Highways v. Arbogast, 201 S.E.2d 492, 157 W. Va. 359, 1973 W. Va. LEXIS 227 (W. Va. 1973).

Opinion

Neely, Justice:

These cases are original actions in prohibition brought by the West Virginia Department of Highways against the Honorable George R. Triplett, Judge of the Circuit Court of Randolph County, and certain landowners to prohibit the judge from proceeding to trial with four separate actions in condemnation. The proceedings in prohibition have been consolidated for decision because they present almost identical questions of law and fact.

On April 26, 1973 the West Virginia Department of Highways brought condemnation proceedings to condemn four pieces of property owned by respondent landowners. The subject land is rural property in Randolph County, West Virginia, which is within the contemplated right-of-way of Appalachian Corridor H, a proposed four-lane highway crossing much of eastern West Virginia. The West Virginia Department of Highways brought its proceedings in condemnation pursuant to Chapter 54, [361]*361Article 2, Section 14a of the Code of West Virginia, 1931, and in conformity with the provisions of that section deposited allayment funds, i.e., funds available for immediate distribution to the landowners to relieve the hardship of relocation, with the circuit court, which were paid by the court to the landowners. These allayment funds represented the Department of Highways’ estimate of the fair market value of the land. Code, 54-2-14a provides:

“Before entry, taking possession, appropriation, or use, the applicant shall pay into court such sum as it shall estimate to be the fair value of the property, or estate, right, or interest therein, sought to be condemned, including, where applicable, the damages, if any, to the residue beyond the benefits, if any, to such residue, by reason of the taking.”
Under this section a party may accept the allayment funds without prejudicing his rights to a commissioners’ award or a jury verdict; however, should the award or verdict be less than the allayment funds, the landowner is required to repay the difference between the award and the allayment funds.

The allayment funds granted by the Deparment of Highways and the awards of the appointed commissioners for the four tracts of land in question, were as follows:

Department of Highways
Commissioners’ Award
No. 73-88 10,500 32,750
73-89 21,000 62,250
73-90 14,260 30,000
73-91 29,700 45,000

Exceptions were taken to the commissioners’ awards by both the State and the landowners, and all four cases were set for trial on August 27, 1973, approximately four months after the condemnation proceedings were begun. [362]*362The Department of Highways moved the Circuit Court to continue the condemnation proceedings until a reasonable time had elapsed for the completion of construction on the properties in question, and as authority for their motion to continue, the Department cited Chapter 54, Article 2, Section 14 of the Code of West Virginia, 1931, as amended, which provides that in condemnation proceedings instituted under that statute:

“. . . such proceedings shall proceed to final award or judgment after a reasonable time has elapsed for completion of the work upon the particular property so entered upon and taken possession of, and the applicant shall pay to the owner of the land the amount of compensation and damages as finally determined in such proceedings . . . .”

The circuit court overruled the motion for a continuance, apparently upon the grounds that Code, 54-2-14a, the section under which the condemnation proceedings were brought, does not provide for an automatic continuance. The relevant portion of Code, 54-2-14a says:

“. . . such proceeding shall proceed to final award or judgment, and the amount of compensation and any damages as finally determined in such proceeding shall be paid in the manner provided by this section.”

Respondent landowners argue that Section 14a is designed to provide for more expeditious payment to condemnees than Section 14, and that it was the express intent of the legislature to eliminate, as a ground for continuance, the lack of completion of a project. Respondents argue that once proceedings are brought under Section 14a, that section governs all aspects of the action to the exclusion of any provision in Section 14.

A proper resolution of whether the Department of Highways is entitled to a continuance under Code, 54-2-14a requires an analysis of the interaction of two aspects of the law: first, the constitutional rights of a landowner to just compensation, and secondly, the legislative policy [363]*363with respect to condemnation proceedings as reflected by Code, 54-2-14, as amended, and Code, 54-2-14a.

In McGibson v. County Court, 95 W.Va. 338, 121 S.E. 99 (1924), this Court recognized that where land is taken by condemnation proceedings “there must be . . . some remedy to the owner whereby he may have compensation within a reasonable time. . . . He must not be put to risk or unreasonably delay.” In McGibson this Court held that a statute permitting a county court to “enter upon any lands, other than those prohibited by law, and locate and build [a] road, and sixty days after said road is completed . . . .” then ascertain fair compensation, is unconstitutional because it fails to provide a remedy to the landowner by which he can enforce compensation within a reasonable time after the taking. Therefore, any procedure in condemnation which does not provide for compensation within a reasonable time is unconstitutional, and the fact that a project has not been completed cannot constitutionally support a motion for continuance if it appear to the court that the time necessary to complete the project is unreasonable.

Converging upon this problem from the opposite direction is this Court’s holding in State ex rel. State Road Commission v. Taylor, 151 W.Va. 535, 153 S.E.2d 531 (1967) in which a writ of prohibition was awarded under a factual situation similar to the cases for decision, except in Taylor the proceedings were brought under Section 14, rather than Section 14a of the Code. In Taylor, the circuit court had set the condemnation proceedings for trial approximately fourteen months after they were instituted although the State Road Commission alleged that the project had not been completed and that the jury would be prejudiced by innumerable pieces of heavy equipment on the property along with the noise, disruption and mud on the premises and on the access road. This Court said at 151 W.Va. 542, 153 S.E.2d 535:

“ . . . Section 14 confers certain rights upon both the state and the condemnee in a condemnation [364]*364proceeding and one of the rights secured to the state is the right to delay proceedings until a reasonable time has elapsed for completion of the work upon the land sought to be condemned. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hinkle v. Black
262 S.E.2d 744 (West Virginia Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
201 S.E.2d 492, 157 W. Va. 359, 1973 W. Va. LEXIS 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-va-dept-of-highways-v-arbogast-wva-1973.