W. T. Crane Carriage Hardware Co. v. Belfatto

69 A. 1085, 76 N.J.L. 415, 47 Vroom 415, 1908 N.J. Sup. Ct. LEXIS 125
CourtSupreme Court of New Jersey
DecidedJune 8, 1908
StatusPublished

This text of 69 A. 1085 (W. T. Crane Carriage Hardware Co. v. Belfatto) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. T. Crane Carriage Hardware Co. v. Belfatto, 69 A. 1085, 76 N.J.L. 415, 47 Vroom 415, 1908 N.J. Sup. Ct. LEXIS 125 (N.J. 1908).

Opinion

The opinion of the court was delivered by

Bergen, J.

Joseph Talkowsky contracted with plaintiff in error to erect upon his building a fire-escape. The contract price was $800, payable as follows:' $200 when the beds and floors of the fire-escape were on and the balance when all the work was done. The contract was duly filed under the second section of the Mechanics’ Lien law (Pcuinph. L. 1898, p. 538), and on March 26th, 1906, the defendant in error, having furnished material for the work to the con[416]*416tractor, served upon the plaintiff in error a stop notice under the third section of the same act. The case shows that when the notice was served no part of the contract price had been paid,'but that on April 5th, 1906, the defendant in error wrote to the plaintiff in error that he might pay the contractor the first payment of $200, as there was then enough work done on account of the contract to pay the $200, and also the amount due them. It also appeared that after the payment of $200 there remained due1, and to become due on account of the contract when completed, the sum of $600, and that at the time of the trial the money remaining in the hands of the plaintiff in error was only $300, he having, notwithstanding the stop notice, paid to the contractor $300 of the $600. The plaintiff in error testified that it would require of the '$300 which he had not yet paid out at least $250 to finish the work according to the terms of the contract, and thereupon moved for a direction of a verdict in his favor, which the trial court refused. His claim was that as he only had $300 in hand, and it would cost $250 to complete the contract according to the plans and specifications, there was not in his hands money enough to pay what was due defendant in error. The verdict found by the jury was $300, and for that sum, with costs, judgment was entered. I think the trial resulted correctly, for there remained due, and to become due, on the contract after the stop notice was served, and after the consent had been given to the payment of $200 to the contractor, $600, out of which he was first entitled to finish the work according to the contract. This finishing, the case shows, can be done for $250, and the plaintiff in error should have had in his hands, if he had observed the contract regarding payments, at least $350 to appty towards the debt of the defendant in error. If he made payments out of the $600 before the contract was performed, he was liable to the defendant in error to the extent of its stop notice, certainly for the amount of the judgment, for that sum at least should have been in hand after deducting the $250, which he claims will fulfill the contract.

The judgment below will be affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
69 A. 1085, 76 N.J.L. 415, 47 Vroom 415, 1908 N.J. Sup. Ct. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-t-crane-carriage-hardware-co-v-belfatto-nj-1908.