W. T. Congleton Co. v. Craft

103 S.W.2d 287, 267 Ky. 750, 1937 Ky. LEXIS 391
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedMarch 16, 1937
StatusPublished
Cited by2 cases

This text of 103 S.W.2d 287 (W. T. Congleton Co. v. Craft) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. T. Congleton Co. v. Craft, 103 S.W.2d 287, 267 Ky. 750, 1937 Ky. LEXIS 391 (Ky. 1937).

Opinion

Opinion op the Court by

Creal, Commissioner—

Reversing.

• For a number of years Thomas L. Craft has been the owner of two lots in Jackson, a city of the fourth class, one of which is made up of two separate parcels which he acquired by different deeds and will be referred to as lot No. 1. This lot fronts about 400 feet on Main street. The other lot is at the corner of Main and Washington streets and fronts about 50 feet on the former.

During the years 1929-1930, W. T. Congleton Company, a corporation, under contracts let pursuant to the provisions of section 3563 et seq., and section 3579a-l, Kentucky Statutes, constructed or improved Main street with concrete pavement and also constructed sewer lines along such street and abutting the property of Craft. The ordinance provided for the construction and improvement of the street under the ten-year payment plan and for the construction of the sewer under the five-year plan with the right reserved to property owners to pay their entire assessment in cash as provided by statute. After the improvements had been completed, the city engineer submitted to the city council his estimates and apportionments of costs to each property owner which were approved. The apportionment against lot No. 1 for the street improvement was $1,662.04 and against lot No. 2 was $207.76. The apportionment against lot No. 1 for the sewer improvement was $712.52 and against lot No. 2 was $89.07.

Thereafter, Thomas L. Craft entered into an agreement in writing with the city to pay 10 annual installments as provided in section 3575 of the Statutes and in conformity with such section agreed in consideration of such privilege that he would make no objection to an illegality or irregularity with regard to the tax *752 against the property and he would pay same in the manner provided in the agreement. He signed a similar written agreement with the city to pay his sewer tax in five annual installments. Bonds sold in anticipation of the collection of the taxes for improvements made on the installment plan were purchased by the contractor and Craft having defaulted in the payment of the principal and interest, the bondholder exercised its option to declare all the installments with interest and penalties due and payable; and instituted this action seeking to recover the amounts of its bonds with interest and penalties and for the enforcement of its lien.

S. B. Howard and J. E. Craft were named parties defendant in the petition and it was alleged that Howard had a lien against the second tract but that same was inferior to those of plaintiff and that the defendant, J. E. Craft, was asserting a claim or interest in the property of Thomas L. Craft described in the petition.

By answer Thomas L. Craft attacked the validity of the assessments against his property on grounds which will be unnecessary to enumerate for reasons presently discussed. He alleged that before the ordinances providing for the sewer and street improvements had been passed and before he had signed the waiver agreements, he had executed to the Hargis Bank &. Trust Company, a mortgage on the property to secure the payment of a note for $2,200 and had also executed to J. H. Johnson a second mortgage to secure the payment of a note for $1,500, which mortgages had been duly put to record; that thereafter he procured from S. B. Howard $210 to be applied as a payment on the Hargis Bank & Trust Company mortgage with an understanding that Howard should have a lien on the property to secure the payment of the sum so furnished and that pursuant to the agreement he had executed and delivered to Howard a mortgage on the property; that he also entered into an agreement with J. E. Craft whereby the latter was to pay the Johnson mortgage in installments of $75 per month; that Johnson agreed to withhold the enforcement of his mortgage lien and accept payment of $75 per month from J. E. Craft and to assign the mortgage to him when same had been paid; that pursuant to the agreement J. E. Craft did *753 pay Johnson two installments of $75 each and to that extent was entitled to be subrogated to the rights of J ohnson.

J. E. Craft and S. B. Howard filed answer setting up payment by them as alleged in the answer of Thomas L. Craft and asked that to the extent of such payments they be subrogated to the rights of the mortgagees and by intervening petition Howard alleged that tract Ño. 2 was sold by the commissioner pursuant to judgment in the case of J. H. Johnson v. T. L. Craft for the enforcement of the lien to secure the balance due on the Johnson mortgage and that Craft became the purchaser; that he signed the sale bond as surety for the purchaser and was required to and did pay the sum of $191.81 in satisfaction thereof on October 27, 1932, and thereafter by order of the court, the judgment was assigned to him and to the extent of such payment he was entitled to be subrogated to the rights of the original mortgagor.

By these pleadings of defendants it was alleged that the assessments against the lots exceeded one-half of their value, and since the mortgagees did not sign the waiver agreement, the assessments to the extent of such excess were void as against the mortgagees.

By reply plaintiff alleged that after it acquired its lien, a building which was on lot No. 1 was destroyed by fire and appellant collected insurance on the building in the sum of $1,100.41, which sum was applied as a payment on the Hargis Bank & Trust Company mortgage; that after it acquired its lien, a building on lot No. 2 was destroyed by fire and Thomas E. Craft collected insurance on the building in the sum of $1,900 which was applied to the payment of the balance due on the Hargis Bank & Trust Company mortgage and the remainder was applied as a payment on the Johnson mortgage; that at the time the apportionment was made and the taxes levied to pay same the lots described in the petition were reasonably worth the sum of $5,000 but are now not worth $2,500; that Thomas L. Craft and the mortgagors had received as proceeds of the property by way of the insurance on the building more than one-half of the value of the property as of the date of the levy of the taxes to pay the assessments against same. A traverse of the reply completed the issues.

*754 The city of Jackson and the school board thereof intervened and set np certain taxes due them against the property which they alleged were a prior and superior lien and no question was made concerning the amount or validity of their claims.

On final hearing it was adjudged that the city of Jackson and the school board recover taxes aggregating $97.25 with interest; that plaintiff recover the sums sued for with interest; that J. E. Craft recover of Thomas L. Craft the sum of $150 with interest from August 12, 1931, and that S. B. Howard recover of Thomas L. Craft the sum of $19 with interest from October 27, 1923; that the city and school board had a lien prior and superior to all others; that two-thirds of the lien should be satisfied out of lot No.. 1 and one-third out of lot No. 2; that plaintiff had a lien on a one-half undivided interest in lot No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parente v. Day
241 N.E.2d 280 (Ohio Court of Appeals, 1968)
Wilson v. Wilson
200 S.W.2d 258 (Court of Appeals of Texas, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
103 S.W.2d 287, 267 Ky. 750, 1937 Ky. LEXIS 391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-t-congleton-co-v-craft-kyctapphigh-1937.