W. T. Andrew Co. v. Mid-State Surety Corp.
This text of 611 N.W.2d 305 (W. T. Andrew Co. v. Mid-State Surety Corp.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
after remand
The plaintiff, W. T. Andrew Company, Inc., was a sub-subcontractor on a construction project at the University of Michigan—Dearborn. It seeks to enforce a claim under the public works bond act. The circuit court’s judgment in favor of the plaintiff has twice been reversed by the Court of Appeals, whose judgment we now affirm.
i
When this case was before us in 1996, we set forth the facts:
In May of 1989, the University of Michigan decided to renovate buildings at its Dearborn campus. In order to facilitate this project, it hired A. Z. Shmina & Sons, a general contracting firm. Shmina secured its work by providing a labor and materials payment bond which it obtained through Cadillac Insurance Company. Cadillac, however, *630 went into receivership in January of 1990. The Michigan Commissioner of Insurance responded by assigning the bond to defendant Mid-State Surety Corporation. Defendant assumed all the rightful liabilities that Cadillac had under the bond. Specifically, the bond provided that Shmina and Cadillac were liable only to the parties who contracted directly with Shmina.
Shmina retained several different subcontractors to perform the renovations. One of the subcontractors was the Marino Mechanical Contractor Company. 1 Marino in turn contracted with plaintiff, the W. T. Andrew Company, to provide plumbing, heating, and air conditioning materials. During the construction period, Marino experienced financial difficulties. Consequently, it defaulted on its obligations to Shmina and plaintiff. Shmina was able to recover the amount of credit Marino had posted. However, plaintiff, as a supplier of materials to Marino, remained unpaid.
On March 24, 1992, plaintiff brought this action against defendant and Marino in Wayne Circuit Court, claiming approximately $70,000 as the unpaid balance. 2 Although admitting that it had no direct contact with Shmina, plaintiff argued that it was entitled to recover from defendant under the public works bond statute, MCL 129.201 et seq.-, MSA 5.2321(1) et seq. The Wayne Circuit Court granted summary disposition for plaintiff and a judgment was entered against defendant in the amount of $78,645.63. Defendant subsequently appealed, and, on October 20, 1994, the Court of Appeals reversed and remanded.
[450 Mich 655, 656-658; 545 NW2d 351 (1996).]
In the initial proceedings on appeal, the Court of Appeals held that the public works bond statute was inapplicable to the University of Michigan. The Court of Appeals thus concluded that the circuit court had erred in granting summary disposition in favor of *631 plaintiff. The Court instead entered judgment in favor of defendant Mid-State Surety, and dismissed the plaintiffs claims against Mid-State. 209 Mich App 308, 312-313; 529 NW2d 658 (1994).
We granted leave to appeal and reversed the judgment of the Court of Appeals, finding that “applying MCL 129.201 et seq.-, MSA 5.2321(1) et seq. to constitutionally autonomous entities such as the University of Michigan promotes the state’s general welfare and, accordingly, is a valid exercise of the Legislature’s police power.” 450 Mich 662-668. 1 We also held that plaintiff is a claimant under the public works bond statute. 450 Mich 669. We remanded the case to the Court of Appeals for resolution of the issue “whether plaintiff provided defendant with timely notice of its claim . . . .” 450 Mich 669.
*632 On remand, the Court of Appeals determined that plaintiff had failed to give proper notice of its claim. For that reason, the Court again reversed the judgment of the circuit court. 221 Mich App 438; 562 NW2d 206 (1997). 2
Plaintiff filed a second application in this Court, and we granted leave to appeal. 459 Mich 881 (1998).
n
A
The requirements regarding notice set forth in the statute are not the same as those stated in the bond.
The statute required plaintiff to provide written notice (a) to A. Z. Shmina & Sons within thirty days after plaintiff began supplying labor and materials and (b) to both Shmina and the University of Michigan within ninety days after plaintiff ceased supplying labor and materials. 3
*633 The bond did not include those notice requirements, but it did require written notice to the surety (originally Cadillac Insurance, now defendant Mid-State Surety) within ninety days after plaintiff was finished supplying labor and materials.
According to its complaint, plaintiff supplied materials for the project “[b]etween the fall of 1990 and March 20, 1991.” Later, plaintiff sent Cadillac Insurance a letter dated March 27, 1991, concerning its involvement in the project. 4 For the limited puipose *634 of arguing cross-motions for summary disposition on the issue of liability, counsel for defendant Mid-State Surety agreed that the surety received the notice required by the bond—notification within ninety days of the completion of the claimant’s efforts. However, argued defense counsel,
Plaintiff cannot have his cake and eat it, too, from the standpoint of picking and choosing what requirements he’s going to take.
He wants the benefit of the statute and none of these cases say in that situation he’s entitled to the minimal requirement of notice under a bond.
B
Clearly, plaintiff is not a claimant under the language of the bond. The bond identifies A. Z. Shmina & Sons Company as the “Principal” and provides:
A claimant is defined as one having a direct contract with the Principal, for labor, material, or both, used in the performance of the Contract; labor and material does not include water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.
This language excludes plaintiff, a sub-subcontractor that never executed a “direct contract” with A. Z. Shmina & Sons Company.
Accordingly, because plaintiff cannot qualify as a claimant under the bond, it is irrelevant that plaintiff *635 met the bond’s notice requirements. Plaintiff simply cannot recover under the terms of the bond.
Moreover, although we held in 1996 that plaintiff is a claimant under the statute, it is clear that plaintiff did not comply with the statutory notice requirements.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
611 N.W.2d 305, 461 Mich. 628, 2000 Mich. LEXIS 573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-t-andrew-co-v-mid-state-surety-corp-mich-2000.