W. L. Reid Co. v. M-B Contracting Co.

285 P.2d 121, 46 Wash. 2d 784, 1955 Wash. LEXIS 548
CourtWashington Supreme Court
DecidedJune 23, 1955
Docket32998
StatusPublished
Cited by11 cases

This text of 285 P.2d 121 (W. L. Reid Co. v. M-B Contracting Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. L. Reid Co. v. M-B Contracting Co., 285 P.2d 121, 46 Wash. 2d 784, 1955 Wash. LEXIS 548 (Wash. 1955).

Opinion

Rosellini, J.

This is a suit to recover the balance alleged to be due on a sale of overhead doors for use in the construction of a government warehouse. The plaintiff, an Oregon corporation engaged in the business of wholesaling builders’ hardware, is the respondent and cross-appellant; and the defendant, a Washington corporation *786 engaged in business as a general contractor, is the appellant. We will refer to them as plaintiff and defendant.

The dispute as to the amount due arose in the following manner: In the spring of 1951, the Corps of Engineers issued specifications and invited bids for the construction of a warehouse at Elmendorf Field, in Alaska. Plaintiff, having learned that defendant was bidding on the prime contract, submitted to defendant its quotations on certain hardware mentioned in the specifications. Included in its bid was an offer to supply thirteen wooden overhead doors. Defendant obtained the prime contract and accepted plaintiff’s bid as to the overhead doors and appurtenant hardware. By telephone, defendant notified plaintiff that three of the doors were to be metal covered as provided in an addendum to the specifications. A transmittal letter accompanying defendant’s August, 1951, purchase order contained the following statement:

“It is understood that there will be an adjustment of this price to provide for metal covering Doors 44, 45, and 46.”

Some time later, defendant requested a quotation on four additional doors, three to be metal covered. On October 9, 1951, plaintiff replied with the following offer':

“Following our letter of October 2, and in answer to your letter of September 24, we are pleased to quote you the sum of $2,165.00, covering the four (4) additional overhead doors that will be required on this warehouse. Three of these doors will be metal covered with 18-gauge metal as requested in your letter. In placing your order for this additional, we would appreciate your sending us the exact size of the doors that will be required. Also, we would like to know whether they are to be metal covered on both sides. ...”

In a letter dated December 26, 1951, defendant’s agent stated that the quotation was “entirely satisfactory.” On January 17, 1952, plaintiff wrote a letter to defendant seeking information as to the specifications for the metal covering of doors 44, 45, and 46, and as to the sizes of the four additional doors. On January 24, 1952, defendant replied:

“The following doors are to be metal covered as per specifications contained in this letter.
*787 “Doors 44, 45 and 46
“3 only doors 10' 2X 12' 1" Total 6 doors.
“Specifications:
“ ‘5-28 subdivision b. Metal Covering: Doors shall be covered on both sides, edges, and ends with 24-gauge, zinc-coated steel sheets conforming to the requirements of Federal Specifications QQ-I-716. Seams shall be double locked and the sheets shall be nailed through the seams and the finished seams shall cover the nailed heads. Nails shall be not more than 6 inches on center. Sheet metal shall be applied under Section IX—Miscellaneous Metals and Sheet Metal, General—of these specifications.’
“The referred to General Specifications can undoubtedly be examined by you at the Corps of Engineers Office in Portland.
“This metal covering is to be furnished to us at approximately $25.00 per door.”

There were no specifications expressly relating to the manner in which metal was to be applied to the overhead doors. Defendant extracted from the original specifications the section relating to the application of metal to sliding doors and incorporated it in its letter of January 24, 1952, quoted above, as specifications to be followed by the plaintiff in the application of metal to the overhead doors. By this letter, the plaintiff was advised for the first time that the overhead doors were to be covered with a type of metal application known as Kalamein.

In the trade, á Kalamein or “metal clad” door is one to which the metal is applied evenly on all surfaces of the door: edges, top, bottom, inside, and outside.

Plaintiff sought bids from manufacturers and discovered that the cost of the metal covering would be greatly in excess of $25 per door. Mr. Reid, president of the plaintiff company, testified that he advised defendant of this fact by telephone; that at the time of the conversation the best (or only) bid he had been able to obtain was approximately $780 per door; and that defendant displayed little concern over the cost, but admonished him to get the doors covered as. quickly as possible. Plaintiff secured a lower quotation from a Portland manufacturer and placed the order there.

*788 It appears that the government specifications required only doors 44, 45, and 46 to be metal covered, and the defendant ordered the metal covering of the three additional doors on its own initiative. The six doors as ordered were identical in size and design. In June, 1952, the defendant pressed for delivery of the six metal-covered doors; and upon learning that only three were near completion canceled its order for metal covering of three doors, but did not specify whether the August or October order was the one canceled. To obtain immediate delivery of the three metal-covered doors, defendant paid to the Portland manufacturer the sum of $131.30 to reimburse it for overtime paid to its employees. All of the wooden doors ordered by the defendant were delivered, as well as the three metal-covered doors, which were installed in the' government warehouse for openings designated 44, 45, and 46. There is no contention that the work was not done in a satisfactory manner.

In this action, the plaintiff sought to recover the sum of $1,667.69, as compensation for covering the three overhead doors with metal, contending that the actual cost was the reasonable value of the metal covering. The trial court found that the reasonable value of metal covering of the doors was the sum of $400 per door, less the sum of $131.30, expended by the defendant, or $1,068.70, and entered a judgment in the sum of $2,525.14, which included an item of $1,456.44 not here in dispute. Defendant excepted to the entry of that judgment as being excessive; plaintiff excepted to it as being inadequate.

On this appeal, defendant does not argue or suggest that plaintiff was ever bound to deliver metal-covered doors for $25 per door or approximately that sum. It does argue that plaintiff was bound to furnish three metal-covered doors under its October quotation (approved by defendant in December and hereafter referred to as the “October contract”) ; that there was no showing that the order for these particular doors was canceled; that only three doors were delivered; and that plaintiff is entitled to collect no more than the price quoted in its letter of October 9, 1951.

*789 Defendant assigns error to the findings of fact that the cost to the plaintiff of the metal covering was $1,667.69, contending that there is no evidence to support it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Wilhelm
665 P.2d 407 (Court of Appeals of Washington, 1983)
Peeples v. Port of Bellingham
613 P.2d 1128 (Washington Supreme Court, 1980)
Peeples v. Port of Bellingham
588 P.2d 757 (Court of Appeals of Washington, 1978)
Ashley v. Lance
493 P.2d 1242 (Washington Supreme Court, 1972)
Douglas v. Bussabarger
438 P.2d 829 (Washington Supreme Court, 1968)
State v. White
433 P.2d 682 (Washington Supreme Court, 1967)
Malstrom v. Kalland
384 P.2d 613 (Washington Supreme Court, 1963)
McGuire v. UNITED BROTHERHOOD ETC.
314 P.2d 439 (Washington Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
285 P.2d 121, 46 Wash. 2d 784, 1955 Wash. LEXIS 548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-l-reid-co-v-m-b-contracting-co-wash-1955.