W K Contracting Co., Inc. v. Ashland Oil & Refining Co.
This text of 478 F.2d 1046 (W K Contracting Co., Inc. v. Ashland Oil & Refining Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
This case involves an appeal from a judgment of the District Court of the Western District of Kentucky that Appellant, W K Contracting Co. (W K), was not entitled to payment for work which it contended was extra and beyond that contemplated by the contract between W K and Appellee, Ashland Oil & Refining Co. (Ashland). It was alleged that the work had been ordered by Ashland during the performance of the contract which provided for the construction of a pipeline from Patoka, Illinois to Owens-boro, Kentucky. The District Court did permit recovery by Appellant of $24,-332.46 withheld by Appellee as a setoff against claims paid by Ashland to various property owners along the pipeline right-of-way for damage allegedly done by W K during the completion of the contract. The Court held that Ashland had withheld payment of this money contrary to the terms of the contract, which required Ashland to furnish an itemized statement showing the amount paid in settlement of any damage claims. Appellant contends it is entitled to recover interest on the money improperly withheld.
With regard to the alleged extra work, Appellant contends that it is entitled to payment under any one of three separate theories. First, it argues that the written contract requires payment for this work. The District Court found that Section 8 of the written contract anticipated the possibility of extra work and provided for a condition precedent to payment for the work — submission of invoices supported by time sheets, payroll records or other evidence of the validity of the charges. 1 Appellant contends that *1048 the existence of a condition precedent has never been raised by Ashland and that the contract cannot be interpreted as providing for such a condition. We find it unnecessary to determine whether the submission of invoices was a condition precedent to payment for extra work, since we have determined that the finding of fact of the District Court that W K had submitted invoices for the extra work which it performed, is not clearly erroneous. As the Court found, W K had, during the course of the construction, submitted 39 such invoices supported by daily time records for work which it considered extra. 2 All of these invoices were paid. No other invoices for extra work were submitted nor was any claim for payment for other work made during the entire construction period. We thus do not find the determination of the District Court that Appellant performed only its required work to be clearly erroneous. 3 See Strickler v. *1049 Pfister Associated. Growers, Inc., 319 F.2d 788, 790 (6th Cir. 1963).
Appellant’s second and third contentions must also fall on the basis of the District Court’s findings of fact. It is contended that there were parol modifications of the written contract and that there was an implied contract that the extra work done would be paid for. The District Court found no evidence that the parties had agreed to modify the contract. 4 Appellant has not attacked this finding as clearly erroneous and we do not find it to be so. 5 Nor can we accept Appellant’s claim that Ashland impliedly agreed to pay for the extra work, in view of the District Court’s finding that the work done by W K was required by the contract and W K was therefore already bound to perform the work.
The remaining question to be considered is whether Appellant is entitled to interest on the judgment of $24,-332.46. Under Kentucky law, if there is a claim for a liquidated debt, interest is payable from the date payment is due. Perry v. Ernest R. Hamilton Associates, Inc., 485 S.W.2d 505 (Ct.App.Ky.1972), even if the refusal to pay is based on a good-faith denial of liability, Shanklin v. Townsend, 434 S.W.2d 655 (Ct.App.Ky. 1968). Thus, the question becomes whether W K’s claim is for a liquidated debt. The amount withheld by Ashland was money owed for work completed. This money was withheld because of the damages for which Ashland claimed W K was responsible. Ashland, however, did not furnish W K with any itemized statement of damages paid and thereby failed to comply with the terms of the contract in withholding payment. There was no justification, therefore, for the refusal to make payment. Since the money was due at a specified date and in a known amount, we find that the claim is for a liquidated debt. Interest
is due, therefore, from the date payment of the money was due.
The judgment of the District Court is affirmed as modified.
. Section 8 of the contract provides :
At any time or times prior to the completion of the work covered by this contract, Company may, by written notice to Contractor, make changes in the plans, specifications, and drawings by way of additions, omissions, or other alterations thereto, such changes to be authorized and signed by Company’s authorized representative and delivered to Contractor’s authorized representative, who shall receipt therefor in writing, or by letter agreement and/or other formal contract revision between the parties hereto. All such changes shall be reduced to writing prior to commencement of work by Contractor on the changes so authorized. For any such changes authorized by Com *1048 pany in the above manner which will increase or decrease the cost and expense of work to Contractor, there shall be a corresponding increase or decrease in the compensation herein provided. Where such changes shall require extra work resulting in an increase of the cost and expenses to Contractor, he shall be paid a price which has been agreed upon prior to commencement of the extra work, or, if no such price is agreed upon, the sum of the following: (1) Actual cost (net after cash discount) of materials and supplies furnished by Contractor in connection with the extra work (to be evidenced by invoices) plus 10 per cent thereon ; (2) Charges for Contractor’s direct labor (including applicable insurances taxes, payroll benefits, travel and subsistence allowances and fringe benefits, overtime premiums, small tools, overhead and profit) and Contractor’s equipment (actual operating hours of work on maintained basis including gasoline, oil, grease, other fuel and supplies, repair parts, repair labor, taxes, license fees, rentals, supervision, overhead, profit, and all other costs incident to use of equipment furnished by Contractor) used in connection with the extra work, at rates not exceeding the maximum rates set forth in the Wage and Equipment Rate Schedule in Paragraph 11.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
478 F.2d 1046, 1973 U.S. App. LEXIS 9667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-k-contracting-co-inc-v-ashland-oil-refining-co-ca6-1973.