W. D. Bunn & Company entered into a written contract, dated May 15, 1913, with the board of supervisors of Dickenson county to build a county road. After the completion of the road the company presented to the board an account for a balance alleged to be due and unpaid for work done under the contract. This account was disallowed by the board, and the company appealed to the circuit court. The case was heard without the intervention of a jury and resulted in a final judgment for the board, which we are now asked to review. We will hereinafter refer to Bunn & Company as the plaintiffs, and to the board of supervisors as the defendant.

The decision turns largely upon the construction of two provisions of the contract. The first of these appears in the form of a proposal or bid by the plaintiffs, incorporated into and made a part of the contract by appropriate reference, in the words and figures following:

“We will complete the road according to plans and specifications and profiles for lump sum of $39,900.00, or we will build the road as per the above classified bid so as not to exceed $41,000.00.”

In explanation of the reference to the classified bid in the foregoing proposition, it is well to state that [410]*410the defendant had previously advertised for bids, had furnished forms upon which the bids were to be made, and had received a number of bids, all of which were made for unit prices—that is, the yardage, pipes, concrete, tile, etc., were seperated and the prices to be paid therefor itemized in the bids as so much per cubic yard of earth excavation, so much per lineal foot of pipe, etc. These bids had all been rejected and, on the same day, the plaintiffs submitted the above proposal, which was promptly accepted by the board of supervisors, forwarded to the State Highway Commissioner and approved by him.

The other provision which, along with the one first above quoted, requires interpretation, was written into the contract by the State Highway Commissioner, as follows:

“To construct complete according to plans and specifications on file at the clerk’s office in Clintwood, Va., a road from Clintwood to the ford of McClure river in Dickenson county. The party of the second part reserving the right to make such minor changes in the location of said road as may to them or their engineer seem best, provided the party of the first part shall be paid at the unit prices set out in the proposal hereto attached for any excess in total quantities that the changed location may have over the location shown on the plans.”

Soon after the work was started, defendant’s engineer began to make what he called “shifts,!’ but what the plaintiffs then and ever since insisted were “minor changes,” in the location of the road, by virtue of which the line of the road was thrown further into the hillsides, thus requiring the plaintiffs to excavate much more material than would have been required under the location upon which the contract was based. [411]*411These shifts or changes, according to figures made by the engineers of the defendant (which are less than the figures as claimed by the plaintiffs, but which, under the terms of the contract, we think, are conclusive as to the quantity of excavation), required the plaintiffs to excavate from the cuts 20,718.1 cubic yards more than they would have had to excavate if the center of the line of the road, as originally located, had been adhered to. The claim for compensation for this yardage constitutes the principal item in controversy.

It is clear that if this additional excavation was an “excess in total quantities,” within the meaning of the contract, and was rendered necessary by “minor changes,” the demand of the plaintiffs must be sustained; and upon these questions of construction, it seems to us that the ease is plainly with the plaintiffs. We are unable to appreciate the distinction between a minor change of location and a shift of location. The contract uses only the one term, “minor change,” and we are given no expert definitions showing any difference between that and a shift of the line. The effort of the defendant’s engineer to explain the difference fell short of the mark, and amounted to a demonstration that in this ease these two expressions are to be regarded as synonymous in effect and in meaning. We must, upon familiar principles of interpretation, give some significance to this section of the contract; and it cannot be reasonably construed to mean anything but that, if any changes in the line, however slight, were made, and resulted in an increase of the total quantities over those shown on the plans, the plaintiffs should be paid therefor.

But it is contended that this increase in excavation was not “any excess in total quantities,” because the embankments or fills were thereby decreased. The [412]*412embankments or fills, if the original location had been followed, would have exceeded the amount of dirt taken from the cuts; the shifts or minor changes were made for the purpose of supplying the deficiency; and the controversy is, therefore, narrowed down to the question whether the plaintiffs were bound, under their contract, to find the additional dirt necessary for this purpose at their own expense. The defendant relies upon the fact that the proposal of the plaintiffs was to complete the road; the argument being that this language means to complete not only the excavation but the embankments, regardless of whether the excavation shown on .the original plans and specifications would have been sufficient for this purpose or not. A sufficient answer to this contention is that, while the plaintiffs did make a lump bid, that bid was in terms confined to the completion of the road according to plans, specifications and profiles which were distinctly made a part of the contract, and which warranted the plaintiffs in assuming that it would be proper and safe for them to follow the custom shown by the evidence to prevail in such cases, to bid merely upon the excavation from cuts as shown upon the original line, and to assume that if the cuts and fills did not balance each other the plaintiffs would be directed by the engineer of the defendant to get the additional dirt necessary either from the sides of the cuts already indicated or from borrow pits, and that in either event they would be paid therefor.

In the specifications are found the following provisions, the italics being added:

“Excavations shall include the removal and placing in embankments (as hereinafter described) of all materials taken from side cuts, side drains, drainage [413]*413ditches, channel changes, or borrow pits, as may be directed by the engineer . . .

“All material shall be measured and paid for in excavation only

“In cases where the excavation inside the regular slopes and widths are insufficient to construct the adjacent embankments, as may be directed by the engineer, the deficiency shall be supplied by regularly widening the excavation or from borrow pits.”

There was also in the specifications an approximate estimate which placed the amount of excavation at 99,139 cubic yards. After the first set of bids had been rejected and before the plaintiffs’ second bid was made, there was a general discussion between the contractors and the representatives of the county, which showed that both parties believed this approximate estimate to be excessive.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
89 S.E. 872, 119 Va. 408, 1916 Va. LEXIS 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-d-bunn-co-v-dickenson-county-va-1916.