VVP America, Inc. v. Design Build Development Services, Inc.

951 So. 2d 461, 2007 La. App. LEXIS 123, 2007 WL 258306
CourtLouisiana Court of Appeal
DecidedJanuary 31, 2007
DocketNos. 41,652-CA, 41,653-CA
StatusPublished
Cited by6 cases

This text of 951 So. 2d 461 (VVP America, Inc. v. Design Build Development Services, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VVP America, Inc. v. Design Build Development Services, Inc., 951 So. 2d 461, 2007 La. App. LEXIS 123, 2007 WL 258306 (La. Ct. App. 2007).

Opinion

DREW, J.

hThe Caddo Parish School Board (CPSB) appealed the judgment in favor of Roofing Supply, Inc. of Shreveport, which supplied material to a subcontractor on a CPSB building project. CPSB asserted that the trial court erred in applying the Louisiana Public Works Act (LPWA), La. R.S. 38:2241, et seq., since Roofing’s lien was filed beyond the statutory 45-day period. CPSB also assigned as errors the trial court’s ruling that Roofing proved the materials for which payment was sought were used in the CPSB project and concluding that Roofing was a qualified claimant under the LPWA. Roofing answered the school board’s appeal, asserting that the trial court erred in failing to award all the funds sought and refusing to award attorney’s fees. The judgment of the trial court is amended, and as amended, is affirmed.

FACTUAL AND PROCEDURAL BACKGROUND

In 1998, the CPSB entered a standard form AIA contract for $1,070,000.00 (later increased to $1,087,572.00) with the general contractor, Design Build Development Services, Inc., for the construction of the “Pine Grove” Classroom Wing Addition in Shreveport. The general contractor and the CPSB used several different permutations of the name, all of which referred to the general contractor.

[464]*464As work proceeded, CPSB made ten payments to the general contractor and issued its last check on August 6, 1999, but held back a retainage amount and other amounts. The school board occupied the building for the 1999-2000 school year. The architect, the school board, and Design Build Construction Services executed a Certificate of | ^Substantial Completion recorded November 17, 1999, in Caddo Parish under # 1680005 with a $14,000.00 punch list attached.

A dispute between the school board and the general contractor arose because the building was 500 to 520 square feet smaller than shown on the plans. The general contractor did not agree to a reduced contract price requested by the school board. The building had numerous problems including foundation and wall defects which resulted in the building’s demolition. Due to liens on record and construction defects, the school board never released the money held back.

Litigation spawned by this construction debacle involved, among others:

• Design Build Development Services, Inc., general contractor. (The trial court noted there was confusion among the parties as to the correct name of the general contractor. CPSB documents included the names “Design Build Development Services, Inc.,” DBSC Corporation, and DBCS Corporation. Finding the CPSB responsible for the confusion, the trial court treated varied names as referring to the general contractor.)
• Patterson Insurance Company, bonding company for the project.
• Roofing Supply, Inc. of Shreveport, plaintiff, which supplied roofing material to the Bullard Company.
• Bullard Company, roofing subcontractor, which obtained supplies from Roofing.
• WP America, Inc. d/b/a Binswanger Glass Company, which supplied material for the project.

The following suits resulted:

1. An action by the CPSB filed September 28, 2001, against the general contractor and other parties was resolved and dismissed prior to trial which was limited to the claims by the two suppliers below.
[s2. In its action to enforce a material-man’s lien and for judgment on open account, WP America, Inc. d/b/a Binswanger Glass Company (Bin-swanger) sued the CPSB, the bonding company, and the general contractor. CPSB filed a document in this court showing the portion of the judgment favoring Binswanger has been satisfied.
3. On November 17, 2000, Roofing sued the general contractor, Patterson Insurance (general contractor’s bonding company), and the school board, seeking to recover the $23,802.10 plus interest and attorney’s fees owed Roofing by the Bul-lard Company, with which Roofing had an open account relationship.

The record shows that Patterson was placed into receivership in 2003 and the Bullard Company went bankrupt. The general contractor was not active in this appeal, which is limited to the dispute between Roofing and the school board.

Co-owner with her husband, corporate officer, and bookkeeper of Roofing Supply, Debbie Sayers testified that Roofing was a wholesale distributor of roofing and vinyl siding products. In 1999, Bullard Company contacted Roofing about supplying roofing material for the CPSB project on which Bullard was the roofing subcontractor. Over a period of years, Bullard Company maintained an open line of credit on a single account with Roofing for all of the [465]*465supplies it purchased for a variety of construction jobs. Either through a Roofing salesman or through a phone call from Bullard Company to Roofing, Bullard placed orders for material for this school addition. Delivery was made by direct shipments via common carrier from the manufacturer, delivery via Roofing trucks or by Bullard employees picking up a particular order. Orders totaling $23,802.10 on the Pine Grove addition were not paid.

| ¿Sayers stated that Chuck Ashley, Roofing’s collections coordinator, prepared and filed a lien on July 20,1999. Although this lien contains a property description, it has no references to the CPSB or the Pine Grove addition project. Sayers stated it was company policy that notice of a lien be sent to the school board and the general contractor; Sayers had nothing in her file documenting that a copy of the hen was sent.

Ashley testified he did not specifically recall filing the July 20, 1999, lien, but that his practice was to determine who owned the property and send the landowner a copy of the lien. Normally, transmittal letters would have been sent also, although none were in Roofing’s file. Ashley recalled signing the affidavit on November 3, 2000, in which he stated he followed Roofing policy by sending a letter notifying the CPSB about Roofing’s filing the lien due to Bullard’s failure to pay for the supplies.

Sayers stated that on August 29, 2000, Roofing sent a letter to the general contractor requesting that the bonding company pay the unpaid invoices owed to Roofing by Bullard. Also filed into evidence was a September 26, 2000, letter from Roofing to the bonding company concerning nonpayment for the roofing materials Roofing supplied to Bullard.

On October 6, 2000, Roofing filed into the public records of Caddo Parish an amended lien naming the CPSB as owner, identifying the Pine Grove addition project, and naming the general contractor. This amendment referred to the initial lien filed July 20, 1999. Roofing also sent the CPSB a | Jetter dated October 6, 2000, informing the school board of the July 20, 1999, lien filed on the project for the outstanding debt of $23,802.10.

After the litigation commenced, Sayers testified that Roofing learned that the bonding company was in receivership. On September 30, 2003, Roofing filed a proof of claim with the Louisiana Insurance Commissioner’s office, which did not pay the claim.

On cross-examination, Sayers acknowledged that Roofing had no written agreement with Bullard to provide materials for the disputed project. When materials were delivered to the Pine Grove job site, Sayers considered the product used by Bullard for that particular job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCartney v. McCartney
256 So. 3d 1101 (Louisiana Court of Appeal, 2018)
Gootee Construction, Inc. v. Atkins
178 So. 3d 629 (Louisiana Court of Appeal, 2015)
J. Reed Constructors, Inc. v. Roofing Supply Group, L.L.C.
135 So. 3d 752 (Louisiana Court of Appeal, 2013)
David Trahan v. Morton International, Inc.
493 F. App'x 571 (Fifth Circuit, 2012)
Teche Electric Supply, L.L.C. v. M.D. Descant, Inc.
2 So. 3d 516 (Louisiana Court of Appeal, 2008)
Electric Supply Co. v. Great Amer. Ins. Co.
973 So. 2d 827 (Louisiana Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
951 So. 2d 461, 2007 La. App. LEXIS 123, 2007 WL 258306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vvp-america-inc-v-design-build-development-services-inc-lactapp-2007.