IN THE SUPERIOR COURT FOR THE STATE OF DELAWARE
VRNS II, LLC, ) ) Appellant, ) ) v. ) C.A. No. N25A-07-003 CEB ) JOSEPH DESMARIAS, ) ) Appellee. ) ) )
Submitted: January 5, 2026 Decided: January 28, 2026
MEMORANDUM OPINION
Upon Appellant’s Appeal from the Court of Common Pleas: AFFIRMED.
John R. Weaver Jr., Esq., Wilmington, Delaware. Attorney for Appellant.
Robert C. McDonald, Esq., SILVERMAN, MCDONALD & FRIEDMAN, Wilmington, Delaware. Attorney for Appellee.
Butler, R.J. FACTUAL BACKGROUND
This is an appeal from a judgment of the Court of Common Pleas regarding a
contract dispute. Defendant-Appellee, Joseph Desmarias (“Desmarias”), was hired
by Plaintiff-Appellant VRNS II, LLC (“VRNS”) to demolish a home and remove
debris from a property owned by VRNS (“the Property”). 1 The agreement was F
negotiated by Desmarias and Praveen Patel (“Mr. Patel”), the property manager for
VRNS. 2 The only written evidence of the agreement’s existence was an estimate for 1F
$23,000 (“the Estimate”) to “REMOVE ALL UTILYS FENCE REMOVE HOUSE
AND HAUL AWAY FILL WITH STONE GRAVLE DIRT AND TOP.” 3 The 2F
Estimate required that VRNS pay a 50% deposit before the project was started but
notably contained no date for performance. 4 3F
After receiving the initial deposit, Desmarias obtained a demolition permit for
a three-month period from February 16, 2022, to May 16, 2022. 5 He rented an 4F
excavator and a Bobcat, and had 40 tons of dirt delivered to the site. 6 The house 5F
1 The facts are taken from the Court of Common Pleas June 9, 2025, Decision After Trial, C.A. No. CPU4-22-002095 [“Dec. at #”]. 2 The parties had worked together in the past and it was usual practice for Desmarias to survey a property and then provide an estimate, but Mr. Patel denied Desmarias access to the home located on the Property. It was also their usual practice that the Estimate would serve as a starting point and additional costs would be assessed throughout the demolition project. Trial Tr. 88:7-90:15. 3 Appellant’s Opening Br., Ex. B. 4 Id. 5 Dec. at 4. 6 Trial Tr. 99:3. 2 was demolished in just one day, but complications arose when it came to sorting and
disposing of the debris. 7 Sorting is a necessary step in a demolition project as some 6F
materials are expensive to dump while other materials can be recycled at a more
favorable rate. 8 Upon demolishing the house, Desmarias discovered the home was 7F
filled floor to ceiling with “every piece of furniture you could ever imagine” as it
was previously occupied by “hoarders.” 9 The dumpsters were rented at $550 for 8F
each load emptied and there was an additional fee for each ton brought to the
landfill. 10 9F
When some 20 tons of debris had been removed without making a dent,
Desmarias contacted Mr. Patel about the rising cost of debris removal and the need
for additional money beyond the Estimate. 11 The two agreed that Desmarias would 10F
purchase a dump truck to avoid the $550 per dumpster fee and keep costs low. 12 At 11F
this time, Mr. Patel procured a check for $8,000 and told Desmarias that the
remaining $1,000 on the Estimate would be paid to him following completion of the
project. 13 Desmarias then purchased a dump truck but it required immediate repairs, 12F
thus stalling the project. Desmarias testified that he communicated nearly every day
7 Dec. at 5. 8 Id. 9 Id. 10 Id. 11 Id. at 5-6. 12 Id. at 6. 13 Id. 3 with Mr. Patel regarding the delay and that at no time was he told the delay was
problematic or that VRNS expected performance at an earlier date. 14 13F
When Desmarias returned to the Property with an operable dump truck
sometime in the beginning of May, but before the expiration of the demolition
permit, he discovered that VRNS had hired a different contractor to complete the
job. 15 At trial, the president of VRNS, Mr. Vinod Patel (“Mr. Vinod”), claimed that 14F
Mr. Patel had repeatedly tried to contact Desmarias about returning to the Property
because there were complaints from the neighborhood about the unsightly scene and
VRNS had received an environmental violation from New Castle County. 16 15F
Desmarias’ testimony was that Mr. Patel knew he was fixing the dump truck with
the intention of returning to the Property to complete the job and that their last
correspondence was two days prior to Desmarias discovering he had been
replaced. 17 At the time of his replacement, Desmarias had been paid $22,000 of the 16F
original $23,000 estimate.
VRNS hired three contractors to replace Desmarias and they completed the
job in around two weeks. 18 VRNS filed this breach of contract action in the Court 17F
14 Id. 15 Id. at 7. 16 Tr. 49:11 – 50:10. 17 Dec. at 6-7. 18 Id. at 8. 4 of Common Pleas seeking $43,916.30 for the cost of hiring the replacement
contractors. 198F
DECISION OF THE COURT OF COMMON PLEAS
The Court of Common Pleas found that a contract existed between Desmarias
and VRNS and that both parties had breached the contract by failing to perform. 20 19F
The determinative question then was which party breached first and excused the
other party’s nonperformance. VRNS argued that Desmarias breached first by
failing to complete the job in a timely manner. 21 Desmarias argued that there was 20F
no breach on his part because the parties had never specified a time for performance
and he could have performed within a reasonable time, namely before the expiration
of the permit on May 16th. 22 Mr. Patel did not testify at trial so Desmarias’ testimony 21F
was the only evidence before the Court as to their communications. VRNS’ position
was undermined by the absence of any testimony from Mr. Patel, who was the person
employed by VRNS that arranged the contract with Desmarias.
The Court of Common Pleas held that the unchallenged testimony of
Desmarias demonstrated that VRNS was aware that Desmarias intended to perform
within a reasonable time and that the delay was caused by both parties’ interest in
19 Id. 20 Id. 21 Id. at 9. 22 Id. 5 lowering costs through the use of a dump truck. 23 VRNS deviated from its normal 22F
course of business and expected the job to be completed in a timeframe not
contemplated by the agreement, therefore Desmarias did not commit a breach. 24 The 23F
fact that replacement contractors hired by VRNS completed the job within two
weeks suggested that Desmarias reasonably could have performed before the
expiration of the permit. 25 The Court’s ultimate conclusion was that VRNS had 24F
wrongfully repudiated the agreement and was not entitled to recover damages. 26 25F
STANDARD OF REVIEW “When sitting as an intermediate court of appeals, and unless otherwise
mandated by statute, the Superior Court’s function is basically the same as the
Delaware Supreme Court.” 27 This Court must determine “whether the factual 26F
findings made by the trial judge are adequately supported by the record and are the
product of an orderly and logical deductive process.” 28 In doing so, this Court “will 27F
23 Id. at 10. 24 Id. at 11. 25 Id. at 10. 26 Id. at 13. 27 Baker v. Connell, 488 A.2d 1303, 1309 (Del. 1985). 28 Massey v. Nationwide Assurance Co., 2018 WL 4692488, at *2 (Del. Super. Sept. 28, 2018) (quoting Wyatt v. Motorola, Inc., 1994 WL 714006, at *2 (Del. Super. Mar. 11, 1994)). 6 not make its own factual findings, weigh evidence, or make credibility
Free access — add to your briefcase to read the full text and ask questions with AI
IN THE SUPERIOR COURT FOR THE STATE OF DELAWARE
VRNS II, LLC, ) ) Appellant, ) ) v. ) C.A. No. N25A-07-003 CEB ) JOSEPH DESMARIAS, ) ) Appellee. ) ) )
Submitted: January 5, 2026 Decided: January 28, 2026
MEMORANDUM OPINION
Upon Appellant’s Appeal from the Court of Common Pleas: AFFIRMED.
John R. Weaver Jr., Esq., Wilmington, Delaware. Attorney for Appellant.
Robert C. McDonald, Esq., SILVERMAN, MCDONALD & FRIEDMAN, Wilmington, Delaware. Attorney for Appellee.
Butler, R.J. FACTUAL BACKGROUND
This is an appeal from a judgment of the Court of Common Pleas regarding a
contract dispute. Defendant-Appellee, Joseph Desmarias (“Desmarias”), was hired
by Plaintiff-Appellant VRNS II, LLC (“VRNS”) to demolish a home and remove
debris from a property owned by VRNS (“the Property”). 1 The agreement was F
negotiated by Desmarias and Praveen Patel (“Mr. Patel”), the property manager for
VRNS. 2 The only written evidence of the agreement’s existence was an estimate for 1F
$23,000 (“the Estimate”) to “REMOVE ALL UTILYS FENCE REMOVE HOUSE
AND HAUL AWAY FILL WITH STONE GRAVLE DIRT AND TOP.” 3 The 2F
Estimate required that VRNS pay a 50% deposit before the project was started but
notably contained no date for performance. 4 3F
After receiving the initial deposit, Desmarias obtained a demolition permit for
a three-month period from February 16, 2022, to May 16, 2022. 5 He rented an 4F
excavator and a Bobcat, and had 40 tons of dirt delivered to the site. 6 The house 5F
1 The facts are taken from the Court of Common Pleas June 9, 2025, Decision After Trial, C.A. No. CPU4-22-002095 [“Dec. at #”]. 2 The parties had worked together in the past and it was usual practice for Desmarias to survey a property and then provide an estimate, but Mr. Patel denied Desmarias access to the home located on the Property. It was also their usual practice that the Estimate would serve as a starting point and additional costs would be assessed throughout the demolition project. Trial Tr. 88:7-90:15. 3 Appellant’s Opening Br., Ex. B. 4 Id. 5 Dec. at 4. 6 Trial Tr. 99:3. 2 was demolished in just one day, but complications arose when it came to sorting and
disposing of the debris. 7 Sorting is a necessary step in a demolition project as some 6F
materials are expensive to dump while other materials can be recycled at a more
favorable rate. 8 Upon demolishing the house, Desmarias discovered the home was 7F
filled floor to ceiling with “every piece of furniture you could ever imagine” as it
was previously occupied by “hoarders.” 9 The dumpsters were rented at $550 for 8F
each load emptied and there was an additional fee for each ton brought to the
landfill. 10 9F
When some 20 tons of debris had been removed without making a dent,
Desmarias contacted Mr. Patel about the rising cost of debris removal and the need
for additional money beyond the Estimate. 11 The two agreed that Desmarias would 10F
purchase a dump truck to avoid the $550 per dumpster fee and keep costs low. 12 At 11F
this time, Mr. Patel procured a check for $8,000 and told Desmarias that the
remaining $1,000 on the Estimate would be paid to him following completion of the
project. 13 Desmarias then purchased a dump truck but it required immediate repairs, 12F
thus stalling the project. Desmarias testified that he communicated nearly every day
7 Dec. at 5. 8 Id. 9 Id. 10 Id. 11 Id. at 5-6. 12 Id. at 6. 13 Id. 3 with Mr. Patel regarding the delay and that at no time was he told the delay was
problematic or that VRNS expected performance at an earlier date. 14 13F
When Desmarias returned to the Property with an operable dump truck
sometime in the beginning of May, but before the expiration of the demolition
permit, he discovered that VRNS had hired a different contractor to complete the
job. 15 At trial, the president of VRNS, Mr. Vinod Patel (“Mr. Vinod”), claimed that 14F
Mr. Patel had repeatedly tried to contact Desmarias about returning to the Property
because there were complaints from the neighborhood about the unsightly scene and
VRNS had received an environmental violation from New Castle County. 16 15F
Desmarias’ testimony was that Mr. Patel knew he was fixing the dump truck with
the intention of returning to the Property to complete the job and that their last
correspondence was two days prior to Desmarias discovering he had been
replaced. 17 At the time of his replacement, Desmarias had been paid $22,000 of the 16F
original $23,000 estimate.
VRNS hired three contractors to replace Desmarias and they completed the
job in around two weeks. 18 VRNS filed this breach of contract action in the Court 17F
14 Id. 15 Id. at 7. 16 Tr. 49:11 – 50:10. 17 Dec. at 6-7. 18 Id. at 8. 4 of Common Pleas seeking $43,916.30 for the cost of hiring the replacement
contractors. 198F
DECISION OF THE COURT OF COMMON PLEAS
The Court of Common Pleas found that a contract existed between Desmarias
and VRNS and that both parties had breached the contract by failing to perform. 20 19F
The determinative question then was which party breached first and excused the
other party’s nonperformance. VRNS argued that Desmarias breached first by
failing to complete the job in a timely manner. 21 Desmarias argued that there was 20F
no breach on his part because the parties had never specified a time for performance
and he could have performed within a reasonable time, namely before the expiration
of the permit on May 16th. 22 Mr. Patel did not testify at trial so Desmarias’ testimony 21F
was the only evidence before the Court as to their communications. VRNS’ position
was undermined by the absence of any testimony from Mr. Patel, who was the person
employed by VRNS that arranged the contract with Desmarias.
The Court of Common Pleas held that the unchallenged testimony of
Desmarias demonstrated that VRNS was aware that Desmarias intended to perform
within a reasonable time and that the delay was caused by both parties’ interest in
19 Id. 20 Id. 21 Id. at 9. 22 Id. 5 lowering costs through the use of a dump truck. 23 VRNS deviated from its normal 22F
course of business and expected the job to be completed in a timeframe not
contemplated by the agreement, therefore Desmarias did not commit a breach. 24 The 23F
fact that replacement contractors hired by VRNS completed the job within two
weeks suggested that Desmarias reasonably could have performed before the
expiration of the permit. 25 The Court’s ultimate conclusion was that VRNS had 24F
wrongfully repudiated the agreement and was not entitled to recover damages. 26 25F
STANDARD OF REVIEW “When sitting as an intermediate court of appeals, and unless otherwise
mandated by statute, the Superior Court’s function is basically the same as the
Delaware Supreme Court.” 27 This Court must determine “whether the factual 26F
findings made by the trial judge are adequately supported by the record and are the
product of an orderly and logical deductive process.” 28 In doing so, this Court “will 27F
23 Id. at 10. 24 Id. at 11. 25 Id. at 10. 26 Id. at 13. 27 Baker v. Connell, 488 A.2d 1303, 1309 (Del. 1985). 28 Massey v. Nationwide Assurance Co., 2018 WL 4692488, at *2 (Del. Super. Sept. 28, 2018) (quoting Wyatt v. Motorola, Inc., 1994 WL 714006, at *2 (Del. Super. Mar. 11, 1994)). 6 not make its own factual findings, weigh evidence, or make credibility
determinations.” 29 For errors of law, the standard of review is de novo. 30 28F 29F
ANALYSIS VRNS’s sole contention on appeal is that Desmarias breached first when he
“took over two months to be in a position to complete the work on a permit issued
by the County with date certain that it terminates.” 31 VRNS argues that the 3 F
expiration of the demolition permit substitutes as the time for performance and since
there was no way Desmarias could have completed the job in time, VRNS was
justified in hiring contractors who could do the job before the permit expired.
Under Delaware law, if a contract does not specify a time for performance,
the party has a reasonable amount of time to perform. 32 “The party asserting a right 31F
based on a reasonable time period must provide evidence of what is a reasonable
time to perform under the contract.” 33 What constitutes a reasonable time to perform 32F
is generally a question of fact. 34 33F
29 Meyers v. Chatham Cove Association of Unit Owners, 2025 WL 1744378, at *2 (Del. Super. June 24, 2025). 30 Robert J. Smith Companies, Inc. v. Thomas, 2001 WL 1729143, at *2 (Del. Super. Dec. 10, 2001). 31 Appellant’s Opening Br. at 6. 32 Pivotal Payments Direct Corp. v. Planet Payment, Inc., 2020 WL 7028597, at *8 (Del. Super. Nov. 30, 2020). 33 Id. (quoting Gluckman v. Holzman, 51 A.2d 458, 467 (Del. Ch. 1947)). 34 Id. (quoting HIFN, Inc. v. Intel Corp., 2007 WL 1309376, at *11 (Del. Ch. May 2, 2007)). 7 The Court of Common Pleas conducted significant fact finding on this issue
at trial. The parties never expressly agreed on a timeframe and while the three-
months allowed by the permit could have supplied the reasonable time for
performance, Desmarias testified that VRNS knew the job would take longer
because of the sizeable amount of debris in the home. The Court of Common Pleas
found Desmarias’ testimony to be credible and due to Mr. Patel’s absence from the
trial, the Court found no reason to doubt his statements that VRNS agreed that the
dump truck was a good idea and permitted him time to conduct repairs. After
weighing the evidence, the Court of Common Pleas followed “an orderly logical
process” in concluding that Desmarias’ delay while repairing the truck was not
unreasonable in light of the parties’ oral agreement.
Furthermore, even if the reasonable time to perform was prior to the expiration
of the permit, there was no evidence supporting VRNS’ conclusion that Desmarias
would not have been able to complete the work in the two weeks between his return
to the Property and the end of the permit. He testified at trial that he believed he
could have finished the job in that time and the replacement contractors did in fact
complete the job in around two weeks. The Court of Common Pleas’ finding was
adequately supported by the record.
“Under Delaware law, repudiation is an outright refusal by a party to perform
a contract or its conditions entitling ‘the other contracting party to treat the contract 8 as rescinded.’” 35 “[A] party may repudiate through a voluntary and affirmative act 34F
rendering performance apparently or actually impossible” and “[a] party's good faith
belief that the other is already in breach of the agreement does not privilege a party
to repudiate its obligations.” 36 5F
The record supports the finding of the Court of Common Pleas that VRNS
repudiated the contract by replacing Desmarias before allowing him a reasonable
time to perform. Absent testimony from Mr. Patel, there was no reason for the Court
to doubt Desmarias’ statements that he had been ousted from the Property without
any warning from VRNS.
CONCLUSION
For all of the foregoing reasons, the rulings of the Court of Common Pleas are AFFIRMED.
IT IS SO ORDERED.
/s/ Charles E. Butler Charles E. Butler, Resident Judge
35 Concrete v. CDE Glob., ID, 2025 WL 3083282, at *10 (Del. Super. Nov. 3, 2025) (citing CitiSteel USA, Inc. v. Connell Ltd. P'ship, 758 A.2d 928, 931 (Del. 2000)). 36 Id. (first quoting Level 4 Yoga, LLC v. CorePower Yoga, LLC, 2022 WL 601862, at *16 (Del. Ch. Mar. 1, 2022); and then quoting HIFN, Inc., 2007 WL 1309376, at *14). 9