Vp Consolidated Holdings v. Hunt, E-08-025 (3-6-2009)

2009 Ohio 1129
CourtOhio Court of Appeals
DecidedMarch 6, 2009
DocketNo. E-08-025.
StatusUnpublished
Cited by2 cases

This text of 2009 Ohio 1129 (Vp Consolidated Holdings v. Hunt, E-08-025 (3-6-2009)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vp Consolidated Holdings v. Hunt, E-08-025 (3-6-2009), 2009 Ohio 1129 (Ohio Ct. App. 2009).

Opinion

DECISION AND JUDGMENT
{¶ 1} This appeal comes to us from a judgment entered by the Erie County Court of Common Pleas, regarding claims for payment for materials furnished in the *Page 2 construction of a public improvement project. Because we conclude the trial court erred in granting summary judgment in favor of appellees, Mosser Construction Inc. ("Mosser") and Travelers Casualty Surety Company of America ("Travelers"), and in its determination of personal liability against appellant, Robert S. Hunt ("Hunt"), we reverse.

{¶ 2} Appellant, VP Consolidated Holdings, Inc. ("VP Consolidated"), filed suit against Robert S. Hunt, and appellees Mosser and Travelers, claiming that payment had not been made for materials provided to Mosser during a public improvement project for the city of Sandusky, Ohio. Mosser was the construction company in control of the entire project. Travelers issued the bond to guarantee payment to subcontractors and other materialmen. Hunt was the president of Horner Construction Company Inc. ("HCCI"), which served as a conduit between VP Consolidated and Mosser for building materials. Stipulations by the parties filed on September 4, 2007, included the following:

{¶ 3} 1. Horner Construction, Inc., charter number 594698, was voluntarily dissolved by the Secretary of State of the State of Ohio on November 27, 1991.

{¶ 4} 2. Horner Construction, Inc., was dissolved as a result of its sale to Horner Construction Company, Inc.

{¶ 5} 3. Horner Construction Company, Inc., charter number 79089, was incorporated on February 1991. Robert Hunt has been the president of Horner Construction Company, Inc., since its incorporation. *Page 3

{¶ 6} Ultimately, all parties filed motions for summary judgment. The trial court granted Mosser's and Travelers' motion on the basis that VP Consolidated's notice of furnishing was not timely served on Mosser. The court denied VP Consolidated's and Hunt's motions. Based upon the evidence submitted, the trial court then found Hunt personally liable on the amounts owed by HCCI to VP Consolidated.

{¶ 7} VP Consolidated now appeals from the grant of summary judgment, arguing the following sole assignment of error:

{¶ 8} "Under R.C. 153.56, subcontractors and materials suppliers seeking to protect their rights under a public improvement must serve notice of furnishing on the principal contactor. R.C. 153.56(C) requires that this notice be in the form provided in R.C. 1311.261. Under R.C. 1311.261, if a notice of furnishing is sent by certified mail, service is complete on the date of mailing. In its April 24, 2007 Judgment Entry, the trial court erred in granting summary judgment in favor of Mosser and Travelers and holding that under R.C. 153.56, service of VP's Notice of Furnishing made by certified mail was complete on the date it was received by Mosser as opposed to the date it was mailed by VP."

{¶ 9} Robert S. Hunt also appeals from the court's judgment and argues the following sole assignment of error:

{¶ 10} "The trial court erred when it entered judgment finding that Robert S. Hunt was personally liable to VP as an agent for an undisclosed principal when the manifest weight of the evidence, the facts stipulated by the parties and the court's own findings of *Page 4 fact proved that Robert S. Hunt did disclose the existence of his agency and the identity of his principal."

I.
{¶ 11} Appellant, VP Consolidated, argues that the trial court erred in determining that service of its notice of furnishing was complete when received by Mosser. We agree.

{¶ 12} Along with its bid for a public improvement contract, a person must file a bid guaranty: either a bond for the full amount of the bid, or a certified check, cashier's check or letter of credit equal to ten percent of the bid. R.C. 153.54. R.C. 153.56, which applies to creditors of public improvements, provides, in pertinent part, that:

{¶ 13} "(A) Any person to whom any money is due for labor or work performed or materials furnished in a public improvement as provided in section 153.54 of the Revised Code, at any time after performing the labor or work or furnishing the materials, but not later than ninety days after the completion of the contract by the principal contractor and the acceptance of the public improvement * * * shall furnish the sureties on the bond, a statement of the amount due to the person.

{¶ 14} "(B) A suit shall not be brought against sureties on the bond until after sixty days after the furnishing of the statement described in Division (A) of this section. * * *

{¶ 15} "(C) To exercise rights under this section, a subcontractor or materials supplier supplying labor or materials that cost more than thirty thousand dollars, who is *Page 5 not in direct privity of contract with the principal contractor for the public improvement, shall serve a notice of furnishing upon the principal contractor in the form provided in section 1311.261 of theRevised Code." (Emphasis added.)

R.C. 1311.261 provides the requirements and the form to be used for the notice of furnishing when the materials have been provided for a public improvement project; R.C. 1311.05 provides the same information regarding mechanics liens on private construction.

{¶ 16} R.C. 1311.19(B) provides, in pertinent part, that:

{¶ 17} "(B) For purposes of this chapter, service is complete upon receipt by the party being served except as provided in division (H) of section 1701.07 of the Revised Code and except, for the purposes ofsections 1311.05 and 1311.261 of the Revised Code, if service of anotice of furnishing is made by certified mail, service is complete onthe date of the mailing. * * *" Thus, when a notice of furnishing for either a private or public improvement is sent by certified mail, service is considered complete on the date of mailing.

{¶ 18} In this case, VP Consolidated sent its notice of furnishing to Mosser and HCI by certified mail on April 5, 2005. Consequently, service was complete on April 5, 2005, the date of mailing. Contrary to appellees' argument, the service for the notice of furnishing is prerequisite to and separate from service of a suit for collection against the bond. Therefore, the trial court erred in determining that service of the notice of furnishing was not complete until the notice was received. *Page 6

{¶ 19} Accordingly, appellant VP Consolidated's sole assignment of error is well-taken.

II.
{¶ 20}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RYS Holdings, L.L.C. v. Virus Gaming Network, L.L.C.
2025 Ohio 2261 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2009 Ohio 1129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vp-consolidated-holdings-v-hunt-e-08-025-3-6-2009-ohioctapp-2009.