Von Eye v. United States

887 F. Supp. 1287, 1995 U.S. Dist. LEXIS 9032, 1995 WL 353670
CourtDistrict Court, D. South Dakota
DecidedMay 25, 1995
DocketCrim. 94-4020
StatusPublished
Cited by3 cases

This text of 887 F. Supp. 1287 (Von Eye v. United States) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Von Eye v. United States, 887 F. Supp. 1287, 1995 U.S. Dist. LEXIS 9032, 1995 WL 353670 (D.S.D. 1995).

Opinion

*1289 MEMORANDUM OPINION and ORDER

PIERSOL, District Judge.

This matter came on for oral arguments and to clarify the administrative record on Monday, May 15,1995, with Plaintiff appearing personally and by Bret Chancelor MerWe, and with Defendants appearing by Craig Peyton Gaumer. After consideration of the testimony, the arguments of counsel and the administrative record, the ASCS determination that work done by Plaintiff prior to November 14, 1991, is included in his commenced conversion exemption and that work undertaken after that date is not included is affirmed.

FACTS

Plaintiff owns Section 6 of Farm 276 and leases Section 7. 1 Testimony at the hearing described three wetland areas 2 and four drainage ditches. Wetland #2 is towards the east in Section 6. Water from Wetland # 2 drains into Channel C which runs west and then south around a hill; runs into Channel B which turns back towards the east; drains south through the “east culvert” and eventually reaches the slough in section 7. Channels C and B are both north of the township road. The second area consists of two wetlands towards the west in Section 6. Wetland # 1 drains through Channel A into Wetland # 3 located to the south and west, and on both the north and south sides of the township road. Channel D begins on the north side of the road, rims through the “west culvert,” and continues south of the road through Wetland #3 and drains into the slough in Section 7.

In 1984, Plaintiff began work to drain approximately 20 acres of wetland on his farm 276. Testimony by Plaintiff was that in September of 1988, in order to meet the statutory time limitation to qualify for a Swampbuster exemption, 3 he wrote out two paragraphs, long-hand, entitled “Drainage Plan for Farm 276” and submitted the plan to the Moody County ASCS Committee, 4 requesting a commenced conversion determination. The plan reads, in its entirety:

The drainage project was started in the summer of 1984 on the SW 1/4 of Sec. 6, 107-49 and the NW 1/4 of Sec. 7, 107-49. Rental of a backhoe and a dirt scraper would be needed. These pieces of equipment would be rented from the Van De Berg Brothers.
The areas to be drained are marked on an ASCS map. Channel A drains to Channel D. Channel C drains to Channel B. The channels were to be cut so all the farm ground would be drained.

Administrative Record [AR] at 120-21. On June 20, 1989, after a prior denial and upon reconsideration of the prior determination and examination of aerial photographs, ASCS granted Plaintiff a commenced determination exemption. 5 AR at 095, 088.

In 1990, Plaintiff determined that the wetlands were not draining as he had outlined in his plan because the culverts under the township road were not low enough to drain from north to south. Testimony by Plaintiff and by a member of the Township Board on *1290 November of 1990, showed that the west culvert was in need of repair and Plaintiff reported that fact to the Township Board on November 20 or 21, 1990. The culvert had been torn out by the time the Township Board arrived to inspect it, but the Board, nevertheless, agreed to pay for the replacement-of the west culvert. The west culvert was replaced with a culvert larger in diameter resulting in a lowering of the elevation 6" and a greater drainage capacity. AR at 012. Plaintiff testified that the west culvert needs to be lowered an additional feet in order to drain Wetlands # 2 and # 3 and complete his original conversion plan.

Plaintiff also testified that, at the time the west culvert was replaced, he personally authorized the construction company performing work to lower the east culvert two (2) feet. The Township Board did not inspect the area until after the work was finished. The Board refused to approve the completed project and Plaintiff paid for lowering the east culvert. AR at 008-16. Plaintiff had no authorization from the Township Board to lower either culvert. The Township Board responded promptly to Plaintiff’s notification regarding the east and west culverts. Approval of the Township Board was necessary to lower the elevation of either the east or west culverts. The Township Board did not authorize lowering either culvert.

On April 11, 1991, Plaintiff was notified by SCS that lowering the culverts was not included in his prior commenced determination and that he might be in violation of the FSA. AR at 075-76. After a hearing on the matter, the ASCS County Executive Director notified Plaintiff on August 11, 1992, that:

the lowering of the culvert will be considered as part of the commenced conversion determination and that no other work or action on culverts, channels, ditching, draining will be allowed or included as part of the commenced determination after the 11-14-91 date.

AR at 41. This determination was appealed through all channels available to Plaintiff, 6 and is the subject of the present action.

SCOPE OF REVIEW

Plaintiffs prayer for relief requests a number of things, including a trial de novo pursuant to 5 U.S.C. § 706(2)(F), a reversal of the ASCS determination, and an affirmative order permitting Plaintiff to complete his conversion project. This case is, in fact, an administrative appeal of the commenced determination and this Court’s jurisdiction is limited to review of agency actions when authorized by statute or when there has been a final agency action. 5 U.S.C. § 704 (1977). Plaintiff has exhausted the administrative appeals provided by 7 C.F.R. § 780 and this is a final agency action.

An agency’s actions will be set aside only if found to be “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). Arbitrary and capricious review examines: (1) whether the agency considered what it was supposed to consider; (2) whether the agency considered something it was not supposed to consider; and (3) whether there is a rational relationship between the evidence and the decision. See Childress & Davis, Federal Standards of Review, § 15.07 at 15 — 41 (2d ed. 1992) (citing Motor Vehicles Manufacturers Ass’n v. State Farm, Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 2867, 77 L.Ed.2d 443 (1983)).

The Court reviews only the administrative record. 5 U.S.C. § 706 (1977);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
887 F. Supp. 1287, 1995 U.S. Dist. LEXIS 9032, 1995 WL 353670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/von-eye-v-united-states-sdd-1995.