Vollenweider v. Helwig Const. Co., Inc.

40 So. 3d 185, 9 La.App. 5 Cir. 505, 2010 La. App. LEXIS 558
CourtLouisiana Court of Appeal
DecidedApril 15, 2010
Docket09-CA-505
StatusPublished

This text of 40 So. 3d 185 (Vollenweider v. Helwig Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vollenweider v. Helwig Const. Co., Inc., 40 So. 3d 185, 9 La.App. 5 Cir. 505, 2010 La. App. LEXIS 558 (La. Ct. App. 2010).

Opinion

i statement of the case

CLARENCE E. McMANUS, Judge.

Mel and Karen Vollenweider (“the Vol-lenweiders”) suffered flood damage to their home, located at 4733 Avron St. in Metairie, LA, as a result of Hurricane Katrina. The Vollenweiders contracted with Helwig Construction Company (“Hel-wig”) for the demolition of the damaged flooring, sheetrock and other materials in the house. This demolition work was completed and the Vollenweiders paid the total amount due on the demolition contract.

Thereafter, the Vollenweiders executed a Close Walls Contract with Helwig for certain repair work to the home. This contract did not include the installation of flooring. Extra repair items were later added to the contract, represented in a list on the Final Bill, including the installation of owner supplied wood flooring at $3.00 per square foot, for a total cost of $3,185.00. The Vollenweiders purchased the hard wood flooring materials from Lumber Liquidators. Helwig hired Rene Portillo of Gulf Coast Resurfacing as a subcontractor to install the wood flooring purchased by the Vollenweiders.

Approximately thirty days after the wood flooring was installed, the Vollen-weiders observed the wood flooring cupping and buckling. Mel Vollenweider contacted Rick Helwig to inspect the problem. Helwig acknowledged that something was wrong, however, the Vollenweiders contend nothing , further was done to correct the problem.

^Thereafter, the Vollenweiders hired William Summers, an expert in hard wood flooring installation and testing. Summers examined the flooring and determine that it must be removed. He tested the floor and found the moisture content level coming from the concrete slab was high. He found this moisture was the reason the floors had cupped and buckled. Summers concluded that a moisture barrier must be installed to prevent this problem. The *188 Vollenweiders then had the buckled wood floor removed and they purchased new wood flooring that was installed by a different contractor.

On August 21, 2007, the Vollenweiders filed a petition for damages against Helwig Construction, alleging Helwig’s repair and replacement of the wood floors was completed in a defective, unworkmanlike and unacceptable manner because Helwig failed to place a moisture barrier beneath the wood floor. The Vollenweiders alleged they had to hire another contractor to demolish the defective flooring and reinstall new flooring, and incurred additional expenses for moving furniture because of these defects. The Vollenweiders further alleged Helwig damaged the leg of their pool table, which required repair. Finally, the Vollenweiders alleged Helwig violated the Louisiana Residential Lien Law, as well as the Federal Fan Debt Collection Act, when the company placed a lien on the residence for the amount not paid on the contract.

Helwig filed an answer and reconven-tional demand on October 3, 2007 alleging the Vollenweiders still owed $24,230.00 for labor, services and materials pursuant to then contract. The Vollenweiders answered the reconventional demand on October 11, 2007 admitting that Helwig had made some repairs and provided certain materials, however, the Vollenweiders claimed the work was not performed in a proper and workmanlike fashion and the work was defective, requiring remediation at substantial additional costs.

LA bench trial was held on March 5, 2009. The trial court issued a judgment April 14, 2009 awarding the Vollenweiders $11,654.95, plus interest and costs. The trial court further found the Vollenweiders were not entitled to $1,000.00 for demolition fees, nor damages for the lien. The trial court also dismissed Helwig’s recon-ventional demand, without reasons.

Helwig now appeals the trial court’s judgment. The Vollenweiders have filed an answer to the appeal. For the reasons which follow, we affirm in part and reverse in part, and amend the trial court’s judgment.

DISCUSSION

On appeal, Helwig argues the trial court erred in concluding that it improperly installed the wood floor and damaged the pool table. Helwig argues the trial court erred in rendering a money judgment in favor of the Vollenweiders and dismissing its reconventional demand.

The Vollenweiders have answered the appeal and argue the trial court’s judgment should be affirmed finding they are entitled to damages from Helwig for the improperly installed wood floors and damaged pool table. They also argue the trial court should have awarded them attorney fees and penalties under the Louisiana Lien Law and the Federal Fair Debt Collection Act.

A court of appeal may not set aside a trial court’s finding of fact in the absence of manifest error or unless it is clearly wrong. Stobart v. State, through Dept. of Trans. and Development, 92-1328, (La.4/12/93), 617 So.2d 880. The Louisiana Supreme Court has set forth a two-part test for the reversal of a factfinder’s determinations: 1) the appellate court must find from the record that a reasonable factual basis does not exist for the finding of the trial court, and 2) the appellate court must further determine that the record establishes that the finding is clearly wrong (manifestly erroneous). Id. This test dictates that a reviewing court |r,must do more than simply review the record for some evidence which supports or controverts the trial court’s finding. Id,. The *189 reviewing court must review the record in its entirety to determine whether the trial court’s finding was clearly wrong or manifestly erroneous. Id.

First, we agree with the trial court and find the Vollenweiders are entitled to damages for the demolition and replacement of the wood floors installed by Helwig, through the subcontractor, Rene Portillo of Gulf Coast Resurfacing. Mr. Vollenweider testified at trial that about thirty days after the wood flooring was installed, he noticed the wood started buckling up about six inches. Mr. Vollen-weider contacted Rick Helwig, who came immediately, saw the wood, and said “something is wrong.” Mr. Vollenweider claimed there was complete cupping throughout every room where the hardwood floors had been installed by Helwig. Mr. Vollenweider further testified that the wood in the master bedroom was about six to seven inches off the concrete and the bedroom door could not be opened or shut.

Rick Helwig testified that he received notice from Mr. Vollenweider regarding the problem with the floor. He went to the home and observed the floor in the back bedroom buckled against the rear wall. Helwig believed that the problem was caused by the floors not being acclimated because the Vollenweiders had not left the air conditioner on to regulate the temperature, or that there was a water leak in the bathroom behind the bedroom.

Rene Portillo, the subcontractor that installed the wood flooring for Helwig, also testified that he went to the Vollenweiders’ home and saw a big buckle right by the door frame in the bedroom where there is a bathroom. He performed a chloride test to determine the moisture content of the slab. According to Portillo, the test indicated the moisture levels were low enough that a moisture barrier was | finot required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
40 So. 3d 185, 9 La.App. 5 Cir. 505, 2010 La. App. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vollenweider-v-helwig-const-co-inc-lactapp-2010.