Vogelgesang v. CECOS International, Inc.

619 N.E.2d 1072, 85 Ohio App. 3d 339, 1993 Ohio App. LEXIS 1478
CourtOhio Court of Appeals
DecidedMarch 15, 1993
DocketNo. CA92-07-077.
StatusPublished
Cited by3 cases

This text of 619 N.E.2d 1072 (Vogelgesang v. CECOS International, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vogelgesang v. CECOS International, Inc., 619 N.E.2d 1072, 85 Ohio App. 3d 339, 1993 Ohio App. LEXIS 1478 (Ohio Ct. App. 1993).

Opinions

William W. Young, Judge.

Appellant and cross-appellee, Gary G. Vogelgesang, Clermont County Auditor (“Auditor”), appeals a decision of the Board of Tax Appeals (“BTA”) that determined the taxable value of a now-closed hazardous waste facility owned by appellee and cross-appellant, CECOS International, Inc. (“CECOS”). The tax year in question is 1987 and the applicable tax lien date is January 1, 1987.

The subject property consists of approximately 207.96 acres located at 5092 Aber Road, Williamsburg, Ohio (“the facility”). The facility was composed of a sanitary landfill, administrative buildings, shop and maintenance buddings, a truck wash, leachate 1 storage facilities and eleven secure chemical management facility (“SCMF”) cells. 2 As of the tax lien date, Cell Nos. 1-8 were closed, 3 Cell No. 9 was receiving waste and nearly completed, Cell No. 10 had recently started receiving waste, and Cell No. 11 was excavated and under construction. CECOS also planned to construct additional cells, Nos. 12-15.

The facility has a history of intervention by both the Ohio and United States Environmental Protection Agencies (“OEPA” and “EPA,” respectively) which we will briefly review. CECOS’s parent company, Browning-Ferris Industries, Inc., purchased the facility in 1983. In late 1983, CECOS had to stop the construction of Cell No. 8 due to a sagging side wall caused by water-bearing sand deposits. The OEPA required CECOS to submit a proposal for reconstruction of the failed slope. This failure resulted in a temporary shutdown of the entire facility.

Next, in November 1984, a pumping problem caused water to be discharged from Cell No. 7 into a drainage ditch. The OEPA subsequently closed the facility. The OEPA allowed CECOS to reopen when it agreed to comply with the Final Findings and Orders issued by the Director of the OEPA on November 26, *343 1984. These orders required CECOS to submit plans addressing surface water management and construction of a truck-wash facility.

The OEPA next closed the facility in May 1985 when a hydrogeology study revealed widespread groundwater contamination. The OEPA permitted CECOS to reopen three months later on the condition that a detailed hydrogeologic assessment of the facility would be performed. CECOS’s groundwater assessment consultant released its report in May 1986, which confirmed the existence of groundwater contamination. The sources of the contamination were Cell Nos. 1 and 2, which the previous owner constructed, and the intermediate landfill.

CECOS’s problems continued in July 1986 when it discovered a large sand deposit or “channel sand” during the construction of Cell No. 11. CECOS also found channel sand in proposed Cell Nos. 12-14. Channel sand is detrimental to the operation of a SCMF cell, as it increases the possibility of water mobility and contamination. As a result of the channel sand discovery, the OEPA, in February 1987, ruled that Cell Nos. 11 and 12 were unsuitable for the disposal of hazardous waste. The OEPA also required Cell Nos. 13 and 14 to be reduced in size.

Also during 1987, the EPA issued an administrative order calling for corrective action at the facility. Specifically, the EPA order forced CECOS to create measures controlling potential releases of contamination and to remediate already contaminated areas.

In August 1988, CECOS voluntarily closed the facility in order to comply with the OEPA’s water management requirements. One month later, the facility neared the end of operations as both the OEPA and the EPA denied its “Part B” final operating permit. 4

Finally, on April 6, 1990, CECOS signed a consent decree with the Ohio Attorney General through which it agreed to permanently close the facility. CECOS also pleaded guilty to one count of violating Ohio’s hazardous waste laws and agreed to pay $3.5 million in civil penalties. In addition, CECOS retained liability for closure and post-closure costs and agreed not to transfer the facility to any entity which would engage in hazardous waste operations.

The present case began in 1988 when the Northeastern Local School District filed a complaint with the Clermont County Board of Revision (“board”) objecting to the Auditor’s valuation of the facility. The Auditor had assessed the facility at *344 a true value of $1,814,000 and a taxable value of $634,900. The board then reassessed the facility at a true value of $45,246,260 and a taxable value of $15,836,191. CECOS appealed the board’s reassessment to the BTA on December 30, 1988.

In its decision, the BTA relied primarily on the report of CECOS’s appraiser, William McCann. In his report, McCann first formulated a preliminary estimate of market value “assuming the facility was not defective.” McCann’s preliminary analysis consisted of two steps. First, McCann utilized the three standard valuation methods, the cost approach, the market approach and the income approach, to compute three estimations of value. 5 Second, McCann reconciled the three figures and, giving the most weight to the market and income approaches, concluded that the facility had a value of $2,150,000 on January 1, 1987, assuming no environmental defects.

To account for what McCann characterized as “defects” at the facility, he then deducted $44,200,000 in estimated liabilities from the reconciled amount and concluded that the facility had a negative value of $42,050,000. The liability deduction included the cost of compliance with the 1984 OEPA Final Findings and Orders, the cost of remediating contaminated Cell Nos. 1 and 2, closure costs, and post-closure costs.

The BTA agreed with McCann’s calculation of value until the deduction for liabilities. Finding the liabilities to be speculative, premature costs not incurred as of January 1, 1987, the BTA refused to deduct those amounts from McCann’s initial determination of value. Thus, the BTA ruled that the true value of the facility as of January 1, 1987 was $2,150,000, over $43,000,000 less than the board’s total.

On appeal, the Auditor presents a single assignment of error:

“The reviewing body abused its discretion to the substantial prejudice of appellant in admitting testimony, over appellant’s objection, regarding events occurring two years after the tax lien date where such evidence was offered to demonstrate the value of appellee’s real property.”

In its cross-appeal, CECOS presents two assignments of error:

Assignment of Error No. 1:

“The BTA erred by failing to determine that the contamination must be utilized to reduce the facility’s value as of January 1, 1987.”

Assignment of Error No. 2:

*345 “The BTA erred by failing to consider the impact of pollution control certificates on the value of the facility.”

Three basic principles guide our analysis- on both the appeal and the cross-appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boekeloo v. Board of Review of City of Clinton
529 N.W.2d 275 (Supreme Court of Iowa, 1995)
Mercury Machine Co. v. Limbach
640 N.E.2d 261 (Ohio Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
619 N.E.2d 1072, 85 Ohio App. 3d 339, 1993 Ohio App. LEXIS 1478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vogelgesang-v-cecos-international-inc-ohioctapp-1993.