Vogel v. Sloan

98 N.J. Eq. 300
New Jersey Court of Chancery·Decided November 5, 1925·Published·Cited by 2 cases

Opinion

This is an interpleader suit under the Mechanics' Lien act. The defendant Sloan, by contract in writing and duly filed, agreed to build a house for the complainant for $12,000. He defaulted on his contract and complainant was obliged to complete the work, after which there remained a balance of $827.71 due Sloan under the contract. Numerous stop-notices were given to complainant by mechanics, subcontractors *Page 302 and materialmen having claims aggregating $3,663.37. Hence this suit. The sole question here involved is as to the priority between the claim of the defendant Newark Parquet Flooring Company and that of Heidritter Lumber Company. No question as to the priority of other claims is involved. The testimony shows that the Newark Parquet Flooring Company, on May 14th, 1925, served a stop-notice on the architect employed by the complainant, Vogel, who was the owner of the building involved; that at that time the complainant, Vogel, was in Massachusetts, where he remained until May 29th, 1925. The officer of the claimant who served the notice on the architect was unable to locate the complainant, and, on inquiry, found that he was out of the state, and thereupon delivered the stop-notice to the architect as mentioned above. Immediately upon Dr. Vogel's return the architect delivered the stop-notice to him. On the same day, or within a day or two thereafter, the officer of the claimant who gave the notice to the architect called on the complainant personally, told him of the stop-notice and asked if he had received it. The complainant replied that he had received it from the architect and that he understood its purport. The stop-notice of the complainant Heidritter Lumber Company was served upon the complainant on June 3d 1925. It is clear, therefore, and, in fact, undisputed, that the stop-notice of the claimant Newark Parquet Flooring Company came into the actual possession of the complainant at least two days prior to the service of the stop-notice by the claimant Heidritter Lumber Company.

The solicitor of Heidritter Lumber Company insists that the claim of that company is entitled to priority because the stop-notice of Newark Parquet Flooring Company was not properly served within the meaning of section 3 of the Mechanics' Lien act (Comp. Stat. p. 3294), and cites, in support of his argument, the case of Lloyd v. Connella, 94 N.J. Eq. 322. It is admitted that the stop-notice of Heidritter Lumber Company was properly served.

The contention of counsel for Heidritter Lumber Company is that section 3 of the Mechanics' Lien act requires service *Page 303 of a stop-notice upon the owner personally, or, at least, upon an agent of the owner authorized to accept such service, and that the architect here was not the agent of the owner and had no authority to accept service for him. That portion of section 3 of the Mechanics' Lien act pertinent to this inquiry reads as follows:

"And it shall be the duty of such * * * materialman or subcontractor to give notice in writing to the owner or owners of such building * * * and of the amount due to him or them and so demanded."

Liens perfected under this section are payable in the order of priority of service of notice, and not pro rata. Board ofEducation v. Tait, 80 N.J. Eq. 94; affirmed, 81 N.J. Eq. 161.

The purpose of section 3 of the Mechanics' Lien act, above cited, I apprehend, is to secure to materialmen, subcontractors,c., payment of their bills so far as possible upon default by the contractor.

In McNab Harlan Manufacturing Co. v. Paterson BuildingCo., 72 N.J. Eq. 929, the court of errors and appeals held that while the "mechanics' lien laws are, as a rule, to be construed strictly against the claimant and in favor of the owner of the land in so far as they require the owner to pay a debt that he did not contract and for a consideration that he may have already paid to the contractor," * * * "no such strict construction should be given to the provisions of the third section of our Mechanics' Lien law." In other words, that section of the act should be liberally construed in favor of the stop-notice claimant in order to effectuate the object of the statute so long as it does not work a hardship on the owner.

In the case of Lloyd v. Connella, supra, the facts were that the stop-notice was served upon an employe of an attorney who, as attorney for a building and loan association mortgagee, was disbursing the mortgage funds, and, incidentally, for the purpose of such disbursement, represented the owner-mortgagor. Vice-Chancellor Foster held in that case that *Page 304 the person upon whom the stop-notice was served was not the agent of the owner, and that, therefore, the service was void as against other claimants who had subsequently properly served the stop-notice upon the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Vogel v. Sloan, 98 N.J. Eq. 300 (N.J. Ct. App. 1925).

98 N.J. Eq. 300 (Vogel v. Sloan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

ELLIOT-FARBER ROOFING, ETC. CO. v. Saitta
192 A.2d 318 (New Jersey Superior Court App Division, 1963)
Apex Roofing Supply Co. v. HW Elliot Co.
145 A.2d 823 (New Jersey Superior Court App Division, 1958)