VMC Behavioral Healthcare Services v. United States

50 Fed. Cl. 328, 2001 U.S. Claims LEXIS 217, 2001 WL 1095297
CourtUnited States Court of Federal Claims
DecidedAugust 31, 2001
DocketNo. 01-473C
StatusPublished
Cited by4 cases

This text of 50 Fed. Cl. 328 (VMC Behavioral Healthcare Services v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VMC Behavioral Healthcare Services v. United States, 50 Fed. Cl. 328, 2001 U.S. Claims LEXIS 217, 2001 WL 1095297 (uscfc 2001).

Opinion

OPINION

BRUGGINK, Judge.

This is an action brought pursuant to the court’s bid-protest jurisdiction. See 28 U.S.C. § 1491(b) (1994 & Supp. V 1999). Plaintiff seeks injunctive relief related to a contract awarded by the Health Resources and Services Administration (“HRSA”) to defendant-intervenor, Magellan Behavioral Health (“Magellan”). Plaintiff, VMC Behavioral Health (“VMC”), challenges both the underlying contract award, which took place on December 1, 2000, and an August 10, 2001 modification to the contract which plaintiff alleges violates the Competition in Contracting Act (“CICA”).1 Plaintiff seeks a temporary restraining order to enjoin HRSA from implementing the modification to Magellan’s contract. The court, however, denied plaintiffs request in an August 16, 2001, Order.

At the court’s direction, the issue of the Magellan contract modification was isolated for separate, expedited consideration. Consequently, currently pending are plaintiffs motion to enjoin the modification of Magellan’s contract and defendant’s motion to dismiss, or, alternatively, for summary judgment with respect to the modification. Oral argument was held on August 30, 2001. Reserved for hearing on September 21, 2001, is plaintiffs request for permanent relief with respect to the underlying contract award. During oral argument, and over defendant and defendant-intervenor’s objection, the court agreed to consider the affidavits of Dr. Mary Vasquez, a principal in VMC, and to hear her limited live testimony. Because the court also held that it would allow no further supplementation of the record with respect to the possibility of a permanent injunction against the modification, counsel for VMC agreed that the record on the issue of the Magellan contract modification would be complete at the end of the August 30 hearing. Consequently, having a complete record in front of it, the court deems the merits of the modification question to be fully submitted for final ruling on permanent relief. For the reasons explained at the conclusion of the hearing, and as further set forth below, we deny plaintiffs request for injunctive relief and grant defendant’s motion for summary judgment, limited to the question of the contract modification.

BACKGROUND

VMC’s challenge to the Magellan contract modification must be grounded in that earlier award. Accordingly, the following background is necessary.

To help promote and maintain the physical and mental well-being of its employees, the federal government, through Federal Occupational Health (“FOH”), a division of the U.S. Public Health Service, Department of Health and Human Services (“HHS”), provides its employees and employees’ family members with Employee Assistance Program (“EAP”) services. These services include confidential consultation, assessment, counseling, problem solving and/or outside referral and follow-up services for alcohol, drug or other problems which may adversely impact an employee’s work performance.

On June 16, 2000, HHS, acting through the Health Resources Services Administration (“HRSA”), issued solicitation number DFOH-BO(O). The stated purpose of the solicitation was “to obtain Contractors who will provide EAP and Work/Life Programs to Federal employees and organizations located throughout the United States including the [330]*330Pacific Islands, Puerto Rico and the Virgin Islands.” AR at 481. “The Government resented] the right to make one contract award for the entire range of services ..., any combination of awards, or no awards .... ” AR at 325.

A limited number of solicitation provisions figure into the parties’ presentations. Attachments to the solicitation identified all of the federal agencies that currently had agreements with FOH for EAP services and listed 36 cities where EAP offices were expected to be maintained by the contractor. In addition, however, in section C of the solicitation, “Description/Speeification/Work Statement,” under the heading “Scope,” the following information also appeared with respect to the possible expansion of the contract to include United States Postal Service (“USPS”) employees:

Program services contracted as a result of this solicitation currently are stipulated to serve organizations that have agreements with FOH for services. These organizations may over time change resulting in increases or decreases in the numbers of participating organizations and clients. FOH also currently has separate contracts for EAP services that are provided to the U.S. Postal Service. Currently, these are separate contracts, however, at the Government’s option, services to the U.S. Postal Service may he added to this contract in the future.

When separate FOH contracts exist, Contractors are required to support each other when requested by FOH. For example, EAP Staff Counselors whose workloads are lower than normal capacity, may be required to provide service for U.S. Postal Service employees.

AR at 66-67 (emphasis added).

The solicitation also contained a “Level of Effort” provision that stated “[i]t is not possible to determine the exact quantities of service required over the term of this contract due to increases or decreases in FOH customer agency needs____The Government will negotiate significant changes in the level of effort.” AR at 9. The “Level of Effort” provision was later amended to include:

Based on the historical growth and future projections, it is estimated that annual increases in EAP services may occur. Therefore, customer organizations may have a need for additional services as described-in section C throughout the contract year.

Each year of the contract the Government may elect to exercise one or all of the following options in order to increase the level of effort due to annual growth.

Option B.l.a.(l)Annual direct labor effort shall be increased up to 5%.

Option B.l.a.(2)Annual direct labor effort shall be increased by up to 10%.

Option B.l.a.(3)Annual direct labor effort shall be increased by up to 15%.

AR at 336. In addition to the “Level of Effort” provision, the solicitation incorporated a standard Order Limitation clause, FAR 52.216-19, which provided that the contractor was not obligated to honor any order, or orders, under the contract that exceed 2,000,-000 covered lives.

On August 3, 2000, VMC timely submitted its technical and business proposals in response to the solicitation. In its technical proposal, VMC stated that it “understands that the estimated population for this project stands at approximately 351,000 employees and that this number may increase or decrease dependent upon the customer organizations’ workforces.” AR at 1466. VMC’s technical proposal also included numerous references to a separate contract for EAP services it currently holds with FOH that covers approximately 400,000 USPS employees. For example, in response to the government’s statement that the number of employees covered for EAP services is estimated and may vary as customer organizations increase or decrease, VMC stated:

For the past 16 years, [VMC] has successfully provided quality employee assistance program services to the [FOH] EAP Federal Agency Consortium with covered populations ranging from 6,000 to 70,000 employees. In addition, since 1993, VMC has provided EAP services to more than 400,000 employees of the U.S. Postal Service under an FOH contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tetra Tech, Inc. v. United States
131 Fed. Cl. 653 (Federal Claims, 2017)
American Apparel, Inc. v. United States
108 Fed. Cl. 11 (Federal Claims, 2012)
CESC Plaza Ltd. Partnership v. United States
52 Fed. Cl. 91 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
50 Fed. Cl. 328, 2001 U.S. Claims LEXIS 217, 2001 WL 1095297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vmc-behavioral-healthcare-services-v-united-states-uscfc-2001.