Visitation Convent v. Kleinhoffer

76 Mo. App. 661, 1898 Mo. App. LEXIS 257
CourtMissouri Court of Appeals
DecidedNovember 15, 1898
StatusPublished
Cited by2 cases

This text of 76 Mo. App. 661 (Visitation Convent v. Kleinhoffer) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Visitation Convent v. Kleinhoffer, 76 Mo. App. 661, 1898 Mo. App. LEXIS 257 (Mo. Ct. App. 1898).

Opinion

Bland, P. J.

The petition in substance states that plaintiff is a corporation; that the plaintiff and defendants on January 22,1891, entered into a written agreement, whereby defendants agreed to do all the work included in rubble masonry, concrete footing, piers and pilasters, brick and iron work required in the basement and foundation work for plaintiff’s new academy and monastery building on Cabanne avenue in the city of St. Louis, agreeable to certain.drawings and specifications previously made by plaintiff’s architects, and to have said work wholly completed on or before April 23,1891, for which plaintiffs agreed to pay defend[665]*665ants $7,717. That about February 1,1891, defendant Alois ICIeinhoffer entered upon the performance of the work mentioned in the contract and laid about two hundred cubic yards of concrete footing, worth, when apportioned under the contract, $1,000, which $1,000 was paid to him by the plaintiff, but that the defendants thereafter (March 21, 1891) wholly failed and refused to proceed with the work and abandoned and left said work incomplete and unfinished. That the contract provided that in the event of the defendants’ failure or refusal in any respect to prosecute the work, that on such failure, etc., being certified by plaintiff’s architect, the plaintiff should be at liberty after three days’ written notice to defendants, to provide such labor and material as might be required to finish the work, and to deduct the cost thereof from any money that might be due on defendants’ contract, and that should the cost thereof exceed such unpaid balance, then defendants should pay such excess to plaintiff, and that said expense incurred by the plaintiff as herein provided for furnishing material and finishing said work should be audited and certified by the architect, which certificate should be conclusive on parties, and that these terms as to notices and furnishing architect’s certificates were complied with, and that for furnishing material and procuring work, necessary to finish and complete defendants’ contract work, it was compelled to pay and did pay for the whole of said work and material $9,713 (an itemized account of which is set forth in the petition), by reason of which it says it is damaged in the sum of $1,996.90, for which with interest it- asks judgment. John O’Leary, one of the makers of the contract, died before the institution of the suit' and his administrator H, M. Wilcox was made a party, who as such answered:

[666]*666I. That his intestate became a party to the contract sued on as surety and not as principal; that the plaintiff for a valuable consideration, settled with and released Kleinhoffer, the principal in the contract, from all liability under said contract whereby he says his intestate was also released.

II. That after the execution of the contract, plaintiff and Kleinhoffer without the knowledge or •consent of O’Leary changed the contract, whereby O’Leary was released.

III. That the plaintiff on or about April 20, 1891, compromised and settled for a valuable consideration its claim under said contract with O’Leary.

IV. That Kleinhoffer, his principal, had purchased and had on plaintiff’s grounds at the building a large amount of stone, sand, lime and other building material, which plaintiff took possession of and used in said building, for which it had rendered no account, nor given any credit. The plaintiff took possession of the work and wrongfully refused to permit Kleinhoffer to proceed with the work under his contract. To this answer a reply was filed denying the answer. Defendant Watson’s answer was a general denial. The other defendants were not served with process and the suit as to them was dismissed. A trial was had by a jury, who returned a verdict for the defendants. In due time plaintiff filed the following motion for a new trial:

“First. The verdict in said cause is against the evidence, against the weight of evidence, and against the law under the evidence.
“Second. The verdict was for the wrong party.
“Third. Because the verdict was dictated by passion and prejudice on the part of the jury and was not responsive to the issue herein.
“Fourth. The court erred in rejecting competent, relevant and material evidence offered by the plaintiff.
[667]*667“Fifth. The court erred in refusing the instructions asked by plaintiff.”

Said motion was by the court sustained for the following reasons: “The court having heard and duly considered the plaintiff’s motion for a new trial heretofore filed and submitted herein doth order that said motion t^e sustained and that the verdict and judgment herein be set aside and vacated on the ground that the-court erred in refusing instruction which declared that the defendants were original contractors and on the ground that the verdict is against the weight of evidence in the case.” From the order awarding a new trial Wilcox (administrator of O’Leary), deceased, alone appealed.

The instruction to which the court refers in its order granting a new trial,is as follows: “The court instructs the jury that defendants Watson and O’Leary signed the contract as co-partners as between the-plaintiff and themselves, and are not released by reason, of any change that may have been made.”

CONTRACT. The contract referred to in the pleadings and read in evidence on the trial reads in the opening paragraph as follows: “This agreement made the twenty-second day of January, 1891, by and between Alois Kleinhoffer as principal and Selmer Watson and John O’Leary as sureties, parties of the first part (hereinafter designated the contractors), and the Visitation Convent, a corporation, party of the second part (hereinafter designated the owner). Witnesseth, that the contractors, being the said parties of the first part, in consideration of the covenants and agreements herein contained on the part of the owner, being the said party of the second part, do covenant, promise and agree with the said owner, in manner following, that is to say.” Then follows sixteen clauses, none of [668]*668which are material to the issues in this case, except the twelfth one, which reads as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Stratford
65 N.Y.S. 1051 (Appellate Division of the Supreme Court of New York, 1900)
United States v. Hazzard
53 A.D. 410 (Appellate Division of the Supreme Court of New York, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
76 Mo. App. 661, 1898 Mo. App. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/visitation-convent-v-kleinhoffer-moctapp-1898.