Vision 2007, LLC v. Lexstar Development & Construction Co.

2011 WY 84, 255 P.3d 914, 2011 Wyo. LEXIS 85, 2011 WL 2027119
CourtWyoming Supreme Court
DecidedMay 25, 2011
DocketS-10-0020
StatusPublished
Cited by2 cases

This text of 2011 WY 84 (Vision 2007, LLC v. Lexstar Development & Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vision 2007, LLC v. Lexstar Development & Construction Co., 2011 WY 84, 255 P.3d 914, 2011 Wyo. LEXIS 85, 2011 WL 2027119 (Wyo. 2011).

Opinion

GOLDEN, Justice.

[11] Vision 2007, LLC (Vision) entered into a contract with Lexstar Development and Construction Company, LLC (Lexstar) for the construction of a hotel. After seventeen months of work on the project, Vision terminated the contract with Lexstar, and Lexstar subsequently filed a lien against the hotel property for amounts it claimed remained owing. Vision filed a petition to strike the lien pursuant to Wyo. Stat. Ann. § 29-1-311(b), which the district court denied on the ground that Vision failed to prove Lexstar knew, when it filed its claim of lien, that the lien was groundless or contained a material misstatement or false claim. Vision appeals, claiming the district court improperly placed the burden of proof on Vision and that the district court's factual findings were clearly erroneous.

[12] Although we agree the burden of proof under Wyo. Stat. Ann. § 29-1-811(b) is on the lien claimant, not on the project owner, we find the district court's ruling was properly based on the evidence presented by the lien claimant, Lexstar, and on the failure of Vision to allege proper grounds for relief under Wyo. Stat. Ann. § 29-1-311(b). We thus affirm.

ISSUES

[13] Vision presents the following issues on appeal:

I. Did the district court err in refusing to strike the corrected lien statement filed after the 120-day statutory limit?
II. Did the district court err in refusing to strike the lien statement and corrected *916 lien statement which did not include an itemized list setting forth and describing materials delivered or work performed, as required by Wyo. Stat. Ann. § 29-1-8017
III. Did the district court err in refusing to strike [the] lien statement which was untimely on its face?
IV. Did the district court err in placing the burden of proof under Wyo. Stat. Ann. § 29-1-311 upon the Petitioner?

FACTS

[14] On October 2, 2007, Vision contracted with Lexstar for the construction of a hotel in Campbell County, Wyoming. Seventeen months later, on March 5, 2009, Vision served Lexstar with a "Notice of Termination of Contract by Owner for Cause." On July 9, 2009, Lexstar filed a "Lien Statement" with the Campbell County Clerk, claiming a lien in the amount of $480,337.78 against the hotel property. The lien stated, "This amount represents the unpaid balance for goods, material and services furnished in the design, approval, construction oversight and materials on the above-described real property.”

[15] On August 17, 2009, counsel for Vision contacted counsel for Lexstar and advised that "the lien was filed on the 121st day after March 10, 2009." The following day, August 18, 2009, Lexstar filed a "Corrected Lien Statement." The "Corrected Lien Statement" changed the date when materials were last furnished by the lien claimant from March 10, 2009, to March 19, 2009. An affidavit attached to the "Corrected Lien Statement" and signed by Patrick Davidson, counsel for Lexstar, stated the change to the "Lien Statement" was the correction of a typographical error. The affidavit incorporated an e-mail communication from Lexstar to its counsel, dated prior to the filing of the original "Lien Statement," that indicated the last day work was performed by Lexstar was March 19, 2009.

[T6] On August 26, 2009, Vision filed a "Petition for Order Striking Lien Statements Pursuant to Wyo. Stat, § 29-1-811." On September 2, 2009, the district court issued an "Order to Show Cause Why Lien Statement and Corrected Lien Statement Should Not Be Stricken Pursuant to Wyo. Stat. § 29-1-811." On September 22, 2009, a hearing was held on the district court's order to show cause, and on October 28, 2009, the district court issued an "Order Denying Petitioner's Motion to Strike Lien Pursuant to Wyo. Stat. Ann. § 29-1-811." In so ordering, the district court reasoned:

Wyo. Stat. Ann. § 29-1-811 contemplates an abbreviated procedure because the de-seribed relief is warranted only under very limited cireumstances. Pursuant to the statute, Vision 2007 must demonstrate that Lexstar's Lien Statement and Corrected Lien Statement were either forged or that Lexstar knew at the time it filed the lien it was groundless, contained a material misstatement, or was false.
Patrick Davidson, counsel for Lexstar who prepared and filed the statements, testified at the hearing. The Court finds that there is no question that the documents were not forged. Therefore, Vision 2007 must demonstrate that Lexstar knew at the time it filed the statements that they were groundless, contained a material misstatement, or were false.
Vision 2007 argues the Lien Statement was invalid because either 1) the Lien Statement mistakenly identified the date work was last performed as March 10, 2009 instead of March 19, 2009; and/or 2) the lien statements failed to set forth an itemization list setting forth and describing the materials delivered or work performed. Vision 2007 has not provided any evidence that these alleged defects were committed with the specific knowledge of Lexstar, let alone with Lexstar's specific knowledge that the lien statements were groundless, contained a material misstatement, or were false. To the contrary, Patrick Davidson testified that at the time of filing he had a reasonable belief that Lexstar's claim to a lien was valid, and that any errors in the lien statements were either typographical or not errors at all. In either case, it argues Vision 2007 is not entitled to relief under Wyo. Stat. Ann. § 29-11-8311. The Court agrees with Lexstar.
*917 The evidence presented to the Court does not show that Lexstar filed the lien statements with specific knowledge that they were groundless, contained material misstatements, or were false. Wyo. Stat. Ann. § 29-1-811 is not the proper avenue for these issues or contentions, and, for the very limited purpose of these proceedings, the Court finds it should declare the lien valid pursuant to Wyo. Stat. Ann. § 29-1-311(b)(v).

[T7] After Vision filed its notice of appeal, and the parties were unable to agree on a statement of the record, the district court, on January 15, 2010, issued the "Court's Settlement of Record." The district court settled the record as follows:

1. Petitioner Vision 2007, LLC ("Vision 2007") is a limited liability company duly organized and existing under the laws of the state of South Dakota. Petitioner is the owner of a motel construction project in Campbell County, Wyoming, commonly known as the Settle Inn, situated near Cam-Plex (the project).
2. Respondent Lexstar Development and Construction Company, LLC ("Lexstar") is a limited liability company duly organized and existing under the laws of the state of North Dakota. Over the course of many months, Respondent has supplied materials for the motel project.
3. On July 9, 2009, Lexstar filed a verified Lien Statement against Vision 2007 with the Campbell County Clerk and Register of Deeds in the amount of $430,837.78. The verified Lien Statement stated that "[the date when materials were last furnished by the Lien Claimant was March 10, 2009."
4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2011 WY 84, 255 P.3d 914, 2011 Wyo. LEXIS 85, 2011 WL 2027119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vision-2007-llc-v-lexstar-development-construction-co-wyo-2011.